HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1203-2023
Submission Date : 24-01-2023 12:36:14 PM
Applicant Type : Company
Project Type: NEW




ALPHA CORP DEVELOPMENT PRIVATE LIMITED
6TH FLOOR, GOLF VIEW CORPORATE TOWER - A, GOLF COURSE ROAD, SECTOR - 42, GURUGRAM, HARYANA - 122002
01244831111
8448693434 (Number Shared by Promoter in Public)
secretarial@alphacorp.in
http://www.alphacorp.in
XXXX259Q
U45201PB2003PTC45680
 
 


 
 


 
 







ALPHACORP HANU ENCLAVE
VILLAGE KAILASH, SECTOR - 28 A,
KARNAL
KARNAL
9996003883 (Number Shared by Promoter in Public)
avi.r@alphacorp.in
AVI RANA
9996003883 (Number Shared by Promoter in Public)
avi.r@alphacorp.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1024-01-2023117350HDFC BANKHRERA Panchkula







5.087 (Acre)
100
100
5.087 (Acre)
LICENSE NO 218 OF 2022 DATED 29/12/2022
Yes







2962.26 Lakhs
2034.80 Lakhs
0 Lakhs
757.06 Lakhs
170.40 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD12691.0592
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS4083.11075
4PAVEMENTS0
5PARKS AND PLAYGROUNDS118.656
6GREEN BELTS1574
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION19
9CLUB HOUSE2100.5
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total20586.32595




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS89YET TO BE PREPARED
2WATER SUPPLY SYSTEM40.29YET TO BE PREPARED
3STORM WATER DRAINAGE37.64YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM87.48YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL19.52YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS2.50YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER108.99YET TO BE PREPARED


29-12-2022 (date)
NA (date)
01-07-2023
27-12-2027
Plot Area(In Square Meter)Number of plots in the project
143.6689
113.254
90.6001
90.6001
113.2504
143.6689
148.5001
131.479517
120.2502
120.2502
131.479517
121.001
138.6001
139.42505
138.6401
127.806014
113.38321
103.5001


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots2084.67

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots170.06192.56

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots131.2174.9898.8393.72

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments00
Shops00
Plots97.4718.74




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.674.67
Water Supply System2.112.11
Sewerage treatment & garbage disposal1.021.02
Electricity Supply System4.594.59
Storm Water Drainage1.981.98
Parks and Playgrounds0.130.13
Clubhouse/community centres00
Shopping area00
Other5.725.72

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.674.674.454.45
Water Supply System2.112.112.012.01
Sewerage treatment & garbage disposal1.021.020.980.98
Electricity Supply System4.594.594.374.37
Storm Water Drainage1.981.981.881.88
Parks and Playgrounds0.130.130.120.12
Clubhouse/community centres0000
Shopping area0000
Other5.725.725.455.45

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.454.454.674.67
Water Supply System2.012.012.112.11
Sewerage treatment & garbage disposal0.980.981.021.02
Electricity Supply System4.374.374.594.59
Storm Water Drainage1.881.881.981.98
Parks and Playgrounds0.120.120.130.13
Clubhouse/community centres0000
Shopping area0000
Other5.455.455.725.72

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.674.676.236.23
Water Supply System2.112.112.822.82
Sewerage treatment & garbage disposal1.021.021.371.37
Electricity Supply System4.594.596.126.12
Storm Water Drainage1.981.982.632.63
Parks and Playgrounds0.130.130.170.17
Clubhouse/community centres0000
Shopping area0000
Other5.725.727.637.63

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.236.235.343.56
Water Supply System2.822.822.421.61
Sewerage treatment & garbage disposal1.371.371.170.78
Electricity Supply System6.126.125.253.50
Storm Water Drainage2.632.632.261.51
Parks and Playgrounds0.170.170.150.10
Clubhouse/community centres0000
Shopping area0000
Other7.637.636.544.36












Yes
No
YES BANK LIMITED, FORTUNE GLOBAL ARCADE, SIKANDERPUR, GURGAON
000272500000311
YESB0000002
110532003
00002
Mr. Santosh Agarwal, Golf View Corporate Tower , Tower -A, 6th Floor, Golf Course Road, Sector -42, Gurgaon, Haryana-122002
Attached











Yes
Yes
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. ELECTRICITY LOADYET TO FILE FOR APPROVALNA








Yes


Yes


NA













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN13-01-2023 View Document
2A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS13-01-2023 View Document
3DEMARCATION PLAN13-01-2023 View Document
4CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT13-01-2023 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND13-01-2023 View Document
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT13-01-2023 View Document
7SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN13-01-2023 View Document
8ZONING PLAN13-01-2023 View Document
9IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN13-01-2023 View Document
10NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT13-01-2023 View Document
11DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.24-01-2023 View Document