HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1262-2023
Submission Date : 25-01-2023 03:56:23 PM
Applicant Type : Company
Project Type: NEW




METRO EDUCATION & WELFARE PRIVATE LIMITED
6TH FLOOR, M3M TEE POINT NORTH BLOCK, SECTOR-65, GURUGRAM
1244732000
9711348349 (Number Shared by Promoter in Public)
metroeducation1204@gmail.com
Https://www.metroeducationwelfare.com
XXXX683E
U70100HR2010PTC086524
 
 


 
 


 
 


 
 







M3M CROWN PHASE 1
SECTOR-111
GURGAON
GURUGRAM
1244732000
8929012754 (Number Shared by Promoter in Public)
metroeducation1204@gmail.com
PRAVEEN SEHGAL
1244732000
9711348349 (Number Shared by Promoter in Public)
metroeducation1204@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150087611-01-20235488800ICICI BANK LTDHRERA Gurugram
250087511-01-20231882040ICICI BANK LTDHRERA Gurugram
351421930-01-20231287730ICICI BANK LTDHRERA Gurugram







15.9938 (Acre)
3.60
2.92
11.6022 (Acre)
License No. 213 of 2022 dated 27-Dec-22 valid upto 26-Dec-27
Yes







230674.96 Lakhs
79246.62 Lakhs
98400.24 Lakhs
7145.53 Lakhs
45882.56 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS6.69
3CONSTRUCTION OF ROADS2.84
4PAVEMENTS0
5PARKS AND PLAYGROUNDS2.09
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total11.62




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS338.24AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM72.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE125.00AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM590.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL250.00AS PER PROJECT REPORT
6STREET LIGHTING76.00AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING192AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER697.41AS PER PROJECT REPORT
15STP262.50AS PER PROJECT REPORT
16PARKING52.59AS PER PROJECT REPORT
17RAIN WATER HARVESTING125.00AS PER PROJECT REPORT
18ELECTRIC SUB STATION621.83AS PER PROJECT REPORT
19UNDERGROUND WATER TANK135.00AS PER PROJECT REPORT
20BOUNDARY WALL237.12AS PER PROJECT REPORT
21SWITCHING STATION703.26AS PER PROJECT REPORT
22HARDSCAPE AND SOFTSCAPE2538.57AS PER PROJECT REPORT
23MAIN ENTRANCE129.02AS PER PROJECT REPORT
24BOUNDARY WALL237.12AS PER PROJECT REPORT


25-01-2023 (date)
25-01-2023 (date)
25-01-2023
31-01-2028
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings145041.19133211





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments641192325635514
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments8577109581036710202
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments115601146380365401
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments4111309419631167
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments859
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2027)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
ICICI BANK LTD & M3M TEE POINT, SECTOR-65, GURUGRAM BRANCH
777705242010
ICIC0007242
110229338
007242
1. Amarjot Kaur Sahni -D/O Swarnjeet Singh , 3/66, SubashNagar , Tagore Garden ,West Delhi 2. Vyom Shakti Nigam-D3/103 Paras City , Bhopal, Madhya Pradesh 3.ShubhraBakshi- 10/6 DLF Phase I , Gurugram. 4. Surbhi- Flat no. 3-905 , Sec 103 , Gurugram 5. Vidhya Sagar - 3G - 208 ,Faridabad 6. Pratap Singh - 10 A Pocket 2 , Mayur ViharPhase III, Delhi. 7. Pradeep Kumar Katiyar- 357 Bakothi ,Kanpur , Uttar Pradesh
Uploaded











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED27-12-2022
II. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED10-05-2021
III. FOREST NOCALREADY BEEN OBTAINED07-08-2018
IV. ARAVALI NOCALREADY BEEN OBTAINED27-08-2018








Yes


Yes


AS PER THE HARERA NORMS













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES/LAMINATEDWOODEN FLOOR/CERAMIC TILE
2WALL FINISHING DETAILSPLASTER WITH OBD
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESEXTERNAL ALUMINIUM WITH GLASSINTERNAL – WOODEN
7GLASS WORKONLY EXTERNAL DOOR/WINDOW
8ELECTRIC FITTINGSAS PER APPROVED MAKE
9CONDUCTING AND WIRING DETAILSAS PER APPROVED MAKE
10CUPBOARD DETAILSNA
11WATER STORAGEAS PER NORMS
12LIFT DETAILSLIFTS AS PER BUILDING PLANS
13EXTERNAL GLAZINGSGLASS WITH ALUMINIUM FRAMINGSLIDING
13.1WINDOWS/GLAZINGSGLASS WITH ALUMINIUM FRAMINGSLIDING
14DOORSNA
14.1MAIN DOORSHARD WOOD DOOR FRAME WITHFLUSH DOOR /LAMINATE
14.2INTERNAL DOORSHARD WOOD DOOR FRAME WITHFLUSH DOOR /LAMINATE
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSAS PER APPROVED MAKE
17CNG PIPE LINESERVICE PROVIDER
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEWATER PROOF PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSPLASTER /OBD
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES/LAMINATE WOODENFLOORING
2 . 2 WALLSPLASTER + OBD
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTISKID CERAMIC TILES
3 . 2 WALLSPLASTER +DADO
3 . 3 CEILINGGRID FALSE CEILING/OBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSAS PER APPROVED MAKE
3 . 6 FITTING/FIXTURESAS PER APPROVED MAKE
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES/LAMINATE WOODENFLOORING
4 . 2 WALLSPLASTER /OBD
4 . 3 CEILINGOBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTISKID CERAMIC TILES
5 . 2 WALLSPLASTER +DADO
5 . 3 CEILINGGRID FALSE CEILING/OBD
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSAS PER APPROVED MAKE
5 . 6 FIXTURESAS PER APPROVED MAKE
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSPLASTER+DADO
6 . 3 CEILINGOBD
6 . 4 COUNTERSSTONE / MARBLE
6 . 5 FIXTURESAS PER APPROVED MAKE
6 . 6 KITCHEN APPLIANCES NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI SKID VITRIFIED TILES
7 . 2 WALLS & CEILINGPLASTER + PAINT
7 . 3 TOILETANTI SKID CERAMIC TILES
7 . 4 BALCONYANTI SKID CERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DEMARCATION PLAN05-01-2023 View Document
2CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT09-01-2023 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN09-01-2023 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND05-01-2023 View Document
5ZONING PLAN05-01-2023 View Document
6SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN09-01-2023 View Document
7A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-01-2023 View Document
8DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD31-01-2023 View Document
9T1-2 (4TH TO 23RD FLOOR)31-01-2023 ------
10TOWER TYPE-A (1, 2, 3, 4, 6)- STRUCTURAL PLAN31-01-2023 ------
11CASH FLOW STATEMENT OF THE PROPOSED PROJECT31-01-2023 View Document
12AAI NOC31-01-2023 ------
13T1 TYPICAL FLOOR_FIRE FIGHTING LAYOUT31-01-2023 ------
14WATER SUPPLY SITE PLAN31-01-2023 ------
15FIRE FIGHTING SITE PLAN31-01-2023 ------
16T2 (STILT, GROUND FLOOR PLAN)31-01-2023 ------
17ELEVATIONS & SECTION PLAN31-01-2023 ------
18T6 (TERRACE PLAN & AREA CALCULATIONS)31-01-2023 ------
19ENVIRONMENT CLEARANCE31-01-2023 ------
20IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN31-01-2023 View Document
21BASEMENT 1,2,3 UNDER COMMERCIAL31-01-2023 ------
22FOREST NOC31-01-2023 ------
23SITE PLAN STORM WATER DRAINAGE31-01-2023 ------
24PERT CHART METRO31-01-2023 ------
25IRRIGATION SITE PLAN31-01-2023 ------
26LANDSCAPE PLAN31-01-2023 ------
27TOWER TYPE-D (5, 8, 11, 13, 15) STRUCTURAL PLAN31-01-2023 ------
28ELECTRICAL AND STREET LIGHTING LAYOUT01-02-2023 ------
29T1 & T2 20TH_FIRE FIGHTING LAYOUT31-01-2023 ------
30ASSURANCE- SEWERAGE31-01-2023 ------
31ELEVATION PLAN 331-01-2023 ------
32SECTION AA31-01-2023 ------
33TOWER TYPE-F (5, 8, 11, 13, 15) STRUCTURAL PLAN31-01-2023 ------
34T12 & 14 (2ND TO 23RD FLOOR)31-01-2023 ------
35TOWER TYPE-C (1, 2, 3, 4, 6) STRUCTUREAL PLAN31-01-2023 ------
36FIRE APPLICATION31-01-2023 ------
37ASSURANCE- STORM WATER31-01-2023 ------
38T8-9 & 11 (1ST FLOOR)31-01-2023 ------
39T8-9 & 11 (2ND TO 23RD FLOOR)31-01-2023 ------
40AIRPORT HEIGHT CLEARANCE31-01-2023 ------
41ELEVATION PLAN 131-01-2023 ------
42BASEMENT 231-01-2023 ------
43SECTION BB31-01-2023 ------
44SEWERAGE LAYOUT SITE PLAN31-01-2023 ------
45T8, T9 & T11 TYPICAL FLOOR_FIRE FIGHTING LAYOUT31-01-2023 ------
46T12 & T14_TYPICAL FLOOR_FIRE FIGHTING LAYOUT31-01-2023 ------
47T13 (TERRACE AREA CALCULATION)31-01-2023 ------
48TOWER TYPE-B (5, 8, 11, 13, 15)- STRUCTURE31-01-2023 ------
49SERVICE ESTIMATE APPLICATION31-01-2023 ------
50T8-9 (TERRACE & GROUND COVERAGE)31-01-2023 ------
51T13 (2ND TO 23RD FLOOR)31-01-2023 ------
52ARAVALLI NOC31-01-2023 ------
53ASSURANCE- DRINKING WATER31-01-2023 ------
54ASSURANCE- STP TREATED WATER31-01-2023 ------
55BASEMENT 1 AREA DIAGRAM31-01-2023 ------
56NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT31-01-2023 View Document
57DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.31-01-2023 View Document
58T13 (5TH TO 29TH FLOOR PLAN)31-01-2023 ------
59DEMARCATION SUPERIMPOSED ON SITE PLAN31-01-2023 ------
60ELECTRICITY ASSURANCE31-01-2023 ------
61ELEVATION PLAN 231-01-2023 ------
62METRO EDUCATION- 15.99 ACRES- LOI ISSUED FOR MLU31-01-2023 ------
63NON- ENCUMBRANCE CERTIFICATE31-01-2023 ------
64STORM WATER SITE PLAN31-01-2023 ------
65T1 & T2 FIRST FLOOR_FIRE FIGHTING LAYOUT31-01-2023 ------
66T1-2 (5TH TO TERRACE)31-01-2023 ------
67T6 (STILT TO 30TH FLOOR PLAN)31-01-2023 ------
68T7 & 10 (TERRACE FLOOR AREA CALCULATIONS)31-01-2023 ------
69T7 (S TO 30TH FLOOR PLAN) &T10; (S TO 32ND FLOOR)31-01-2023 ------
70T8-9 & 11 (AREA CALCULATIONS)31-01-2023 ------
71T12 & 14 (5TH TO 29TH FLOOR)31-01-2023 ------
72T12 & 14 (AREA CALCULATION OF ALL FLOORS)31-01-2023 ------
73TOWER TYPE-E (1, 2, 3, 4, 6) STRUCTURE PLAN31-01-2023 ------
74BR-III ISSUED- METRO EDUCATION- 15.99375 ACRES31-01-2023 ------
75ROAD LAYOUT31-01-2023 ------