HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1198-2023
Submission Date : 05-01-2023 05:05:00 PM
Applicant Type : Company
Project Type: NEW




EMPERIUM DEVELOPERS PVT. LTD.
4, TOLSTOY MARG, NEW DELHI-110001
9896387642 (Number Shared by Promoter in Public)
sujatali@emperium.in
http://www.emperium.in
XXXX062M
U70109DL2021PTC382173
 
 


 
 


 
 


 
 







EMPERIUM PALM DRIVE-II
VILLAGE SIMLAMOLANA, SECTOR 19A
PANIPAT
PANIPAT
9896387642 (Number Shared by Promoter in Public)
sujatali@emperium.in
ANURAG BARGOTI
9896387642 (Number Shared by Promoter in Public)
sujatali@emperium.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150451404-01-2023256500ICICI BANK LIMITED, PANIPATHRERA Panchkula







5.90625 (Acre)
1.00
1.55
5.90625 (Acre)
LICENSE NO. 216 OF 2022 DATED29.12.2022 (VALID UPTO 28.12.2027)
Yes







2666.00 Lakhs
1316.00 Lakhs
0.00 Lakhs
735.00 Lakhs
615.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 2.90000
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 1.84625
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0.45000
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0.59000
12ANY OTHER 0
13COMMERCIAL 0.12000
Total5.90625




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS198.45AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM73.50AS PER PROJECT REPORT
3STORM WATER DRAINAGE73.50AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM183.75AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL73.50AS PER PROJECT REPORT
6STREET LIGHTING44.10AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS88.20AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


29-12-2022 (date)
NA (date)
15-01-2023
04-08-2027
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 146.44 5
2 108.701 6
3 113.509 6
4 149.705 1
5 100.450 1
6 103.204 1
7 105.590 1
8 108.696 1
9 111.442 1
10 114.188 1
11 116.934 1
12 119.681 1
13 122.427 1
14 123.819 1
15 135.983 9
16 149.948 1
17 131.214 1
18 112.442 1
19 93.708 1
20 93.822 2
21 112.67 4
22 149.948 2
23 131.366 1
24 112.632 1
25 133.914 25
26 114.656 1
27 90.294 1
28 133.914 6
29 123.447 1
30 104.300 1
31 90.331 1
32 135.80 6
Total93


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.4410.4410.4410.44
Water Supply System3.873.873.873.87
Sewerage treatment & garbage disposal3.873.873.873.87
Electricity Supply System9.679.679.679.64
Storm Water Drainage3.873.873.873.87
Parks and Playgrounds4.644.644.644.64
Clubhouse/community centres0000
Shopping area0000
Other2.322.322.322.32

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.4410.4410.4410.44
Water Supply System3.873.873.873.87
Sewerage treatment & garbage disposal3.873.873.873.87
Electricity Supply System9.679.679.679.67
Storm Water Drainage3.873.873.873.87
Parks and Playgrounds4.644.644.644.64
Clubhouse/community centres0000
Shopping area0000
Other2.322.322.322.32

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.4410.4410.4410.44
Water Supply System3.873.873.873.87
Sewerage treatment & garbage disposal3.873.873.873.87
Electricity Supply System9.679.649.679.67
Storm Water Drainage3.873.873.873.87
Parks and Playgrounds4.644.644.644.64
Clubhouse/community centres0000
Shopping area0000
Other2.322.322.322.32

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.4410.4410.4410.44
Water Supply System3.873.873.873.87
Sewerage treatment & garbage disposal3.873.873.873.87
Electricity Supply System9.679.679.679.67
Storm Water Drainage3.873.873.873.87
Parks and Playgrounds4.644.644.644.64
Clubhouse/community centres0000
Shopping area0000
Other2.322.322.322.32

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.4410.4410.44
Water Supply System3.873.873.87
Sewerage treatment & garbage disposal3.873.873.87
Electricity Supply System9.679.679.67
Storm Water Drainage3.873.872.87
Parks and Playgrounds4.644.644.64
Clubhouse/community centres000
Shopping area000
Other2.322.322.32












Yes
No
ICICI BANK GOL MARKET MODEL TOWNPANIPAT
661905601437
ICIC0006619
132229003
6619
Sh. RAVINDER SAUND R/o H NO. A-881-ASUSHANT LOK PHASE-1 GALLERIA DLF-IVFARUKHNAGAR GURGAON HARYANA-122009Sh. HARDEEP SINGH R/O H NO 575 MODELTOWN PANIPAT-132103
Uploaded in upload section.











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 216 OF 2022ALREADY BEEN OBTAINED29-12-2022








Yes


Yes


The provisions of RERA Act and Rules have been incorporated in the draft agreements.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE BEING PLOTTED.
2WALL FINISHING DETAILSNOT APPLICABLE BEING PLOTTED.
3KITCHEN DETAILSNOT APPLICABLE BEING PLOTTED.
4BATHROOM FITTINGSNOT APPLICABLE BEING PLOTTED.
5WOOD WORK ETCNOT APPLICABLE BEING PLOTTED.
6DOORS AND WINDOS FRAMESNOT APPLICABLE BEING PLOTTED.
7GLASS WORKNOT APPLICABLE BEING PLOTTED.
8ELECTRIC FITTINGSNOT APPLICABLE BEING PLOTTED.
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE BEING PLOTTED.
10CUPBOARD DETAILSNOT APPLICABLE BEING PLOTTED.
11WATER STORAGENOT APPLICABLE BEING PLOTTED.
12LIFT DETAILSNOT APPLICABLE BEING PLOTTED.
13EXTERNAL GLAZINGSNOT APPLICABLE BEING PLOTTED.
13.1WINDOWS/GLAZINGSNOT APPLICABLE BEING PLOTTED.
14DOORSNOT APPLICABLE BEING PLOTTED.
14.1MAIN DOORSNOT APPLICABLE BEING PLOTTED.
14.2INTERNAL DOORSNOT APPLICABLE BEING PLOTTED.
15AIR CONDITIONINGNOT APPLICABLE BEING PLOTTED.
16ELECTRICAL FITTINGSNOT APPLICABLE BEING PLOTTED.
17CNG PIPE LINENOT APPLICABLE BEING PLOTTED.
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE BEING PLOTTED.
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE BEING PLOTTED.
20INTERNAL FINISHINGNOT APPLICABLE BEING PLOTTED.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
1 . 2 WALLSNOT APPLICABLE BEING PLOTTED.
1 . 3 CEILINGNOT APPLICABLE BEING PLOTTED.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
2 . 2 WALLSNOT APPLICABLE BEING PLOTTED.
2 . 3 CEILINGNOT APPLICABLE BEING PLOTTED.
2 . 4 MODULAR WARDROBESNOT APPLICABLE BEING PLOTTED.
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
3 . 2 WALLSNOT APPLICABLE BEING PLOTTED.
3 . 3 CEILINGNOT APPLICABLE BEING PLOTTED.
3 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED.
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED.
3 . 6 FITTING/FIXTURESNOT APPLICABLE BEING PLOTTED.
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
4 . 2 WALLSNOT APPLICABLE BEING PLOTTED.
4 . 3 CEILINGNOT APPLICABLE BEING PLOTTED.
4 . 4 WARDROBESNOT APPLICABLE BEING PLOTTED.
5 . TOILET
5 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
5 . 2 WALLSNOT APPLICABLE BEING PLOTTED.
5 . 3 CEILINGNOT APPLICABLE BEING PLOTTED.
5 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED.
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE BEING PLOTTED.
5 . 6 FIXTURESNOT APPLICABLE BEING PLOTTED.
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
6 . 2 WALLSNOT APPLICABLE BEING PLOTTED.
6 . 3 CEILINGNOT APPLICABLE BEING PLOTTED.
6 . 4 COUNTERSNOT APPLICABLE BEING PLOTTED.
6 . 5 FIXTURESNOT APPLICABLE BEING PLOTTED.
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE BEING PLOTTED.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
7 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED.
7 . 3 TOILETNOT APPLICABLE BEING PLOTTED.
7 . 4 BALCONYNOT APPLICABLE BEING PLOTTED.
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE BEING PLOTTED.
8 . 2 WALLS & CEILINGNOT APPLICABLE BEING PLOTTED.
8 . 3 RAILINGSNOT APPLICABLE BEING PLOTTED.
8 . 4 FIXTURESNOT APPLICABLE BEING PLOTTED.












Sr. No.Document DescriptionDate of Document UploadView Document
1 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 03-01-2023 View Document
2 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 05-01-2023 View Document
3 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 03-01-2023 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 05-01-2023 View Document
5 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 05-01-2023 View Document