HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1182-2022
Submission Date : 24-12-2022 09:06:31 PM
Applicant Type : Firm
Project Type: NEW


M/S. AGROHA DEVELOPERS AND PROMOTERS
NH-9, AGROHA, NEAR PUNJAB NATIONAL BANK, AGROHA, DISTRICT HISAR
9812191999 (Number Shared by Promoter in Public)
ravibeniwal091999@gmail.com
0612202200084
ABYFA4598G





























AGROHA ENCLAVE
SECTOR - 2, AGROHA
HISAR
HISAR
9812191999 (Number Shared by Promoter in Public)
ravibeniwal091999@gmail.com
RAVI BENIWAL
9812191999 (Number Shared by Promoter in Public)
ravibeniwal091999@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
179305-12-2022350000HDFC BANKHRERA Panchkula







15.31875 (Acre)
65
56.63
15.31875 (Acre)
190 of 2022
No
Address     H.NO. 58/2 KAMLA NAGAR, HISAR
Address     VILLAGE AGROHA, TEHSIL & DISTRICT - HISAR
Annexure-B- PROMOTER/ DEVELOPER
YES
Yes
COPY ATTACHED
No
No
Yes







1472.1 Lakhs
0.00 Lakhs
0.00 Lakhs
1030.95 Lakhs
441.15 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD7.9367
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.00
3CONSTRUCTION OF ROADS3.78715
4PAVEMENTS0.00
5PARKS AND PLAYGROUNDS1.1563
6GREEN BELTS0.52480
7VEHICLE PARKINGS0.00
8ELECTRICITY SUB-STATION0.00
9CLUB HOUSE0.00
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.00
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1.5319
12ANY OTHER0.3819
Total15.31875




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS306.375AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM160.8468AS PER PROJECT REPORT
3STORM WATER DRAINAGE30.6375AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM145.5281AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL153.1875AS PER PROJECT REPORT
6STREET LIGHTING15.31875AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0.00YET TO BE PREPARED
8PLAYGROUNDS AND PARKS53.6156AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0.00YET TO BE PREPARED
10SHOPPING AREA0.00YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0.00YET TO BE PREPARED
12SCHOOL0.00YET TO BE PREPARED
13HOSPITAL/DISPENSARY0.00YET TO BE PREPARED
14ANY OTHER165.4425AS PER PROJECT REPORT


22-11-2022 (date)
NA (date)
05-01-2023
31-12-2025
Plot Area(In Square Meter)Number of plots in the project
149.987
110.629
149.813
143.1139
123.701
131.411
149.971
146.0311
149.8832
147.4076
143.4118
145.9517
145.361
139.451
132.251
125.051
117.851
110.651
103.451
96.261


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements61.27561.27530.637530.6375
Water Supply System0032.1693632.16936
Sewerage treatment & garbage disposal0030.637530.6375
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0013.403913.4039
Clubhouse/community centres0000
Shopping area0000
Other0016.544216.5442

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements30.637530.637530.637530.6375
Water Supply System16.0846816.0846816.0846816.08468
Sewerage treatment & garbage disposal15.3187515.3187515.3187515.31875
Electricity Supply System36.382036.382036.382036.3820
Storm Water Drainage15.3187515.3187500
Parks and Playgrounds13.403913.403900
Clubhouse/community centres0000
Shopping area0000
Other16.544216.544216.544216.5442
Street Light7.65937.6593

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System16.0846816.0846800
Sewerage treatment & garbage disposal0030.63750
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other16.544216.544216.544216.5442












No
No
HDFC BANK LTD, SHOP NO. 1&2, NEAR RAJPUT DHARAMSHALA, AGROHA, DISTRICT - HISAR
50200072068069
HDFC0003209
125240061
3209
Ravi Beniwal R/o. Village - Mirpur, Agroha, Tehsil & District - Hisar
Attached











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLANALREADY BEEN OBTAINED22-11-2022








Yes


Yes


Copy Attached













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN24-12-2022 View Document
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT24-12-2022 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN24-12-2022 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND24-12-2022 View Document
5DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.24-12-2022 View Document