HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1235-2022
Submission Date : 22-08-2023 02:12:37 PM
Applicant Type : Company
Project Type: NEW




SUNSAT EDUCATIONAL ACADEMY PVT. LTD.
ANARKALI COMPLEX, JHANDEWALA EXTENSION, NEW DELHI, DL110055
9117383838 (Number Shared by Promoter in Public)
accounts@3bhomes.in
http://3bhomes.in
XXXX733M
U80901DL2008PTC180934
 
 


 
 


 
 


 
 


 
 







3B HOMES CORNER HUB
VILLAGE- JANAULA, SECTOR-1
PATAUDI
GURUGRAM
9971953838
9971953838 (Number Shared by Promoter in Public)
accounts@3bhomes.in
NIRDESH SINGH
9971953838 (Number Shared by Promoter in Public)
accounts@3bhomes.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1184408-08-2023108000AXIS BANKHRERA Gurugram
2184508-08-202332000AXIS BANKHRERA Gurugram







0.432 (Acre)
1.5
0.83
10.9 (Acre)
16 of 2020(21-07-2020)
Yes







512 Lakhs
44.98 Lakhs
0 Lakhs
100.00 Lakhs
367.02 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD612.00
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS510.4324
4PAVEMENTS84
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS525.4040
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER16.9644
Total1748.8008




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS18.53AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM20.00AS PER PROJECT REPORT
3STORM WATER DRAINAGE10.75AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL17.36AS PER PROJECT REPORT
6STREET LIGHTING4.70AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER28.66AS PER PROJECT REPORT


03-05-2021 (date)
21-11-2022 (date)
21-08-2023
20-08-2026
Plot Area(In Square Meter)Number of plots in the project
58.504
31.5012


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements003.717.41
Water Supply System6.006.006.002.00
Sewerage treatment & garbage disposal5.215.215.211.74
Electricity Supply System0002.35
Storm Water Drainage3.233.233.231.08
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other5.735.735.735.73

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements7.41
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System2.35
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other5.73












Yes
No
DCB BANK & JHARSA ROAD, SECTOR-15 PART-II, GURUGRAM
06223900000055
DCBL0000062
110072003
062
Yashpal Yadav
Attached











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
No
No


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLANALREADY BEEN OBTAINED03-05-2021
II. ZONING PLANALREADY BEEN OBTAINED21-11-2022
III. SERVICE PLAN AND ESTIMATE APPROVALALREADY BEEN OBTAINED12-01-2022
IV. STANDARD DESIGNALREADY BEEN OBTAINED22-11-2022
V. LICENSEALREADY BEEN OBTAINED21-07-2020








Yes


Yes


As per HARERA norms







3B HOMES PATAUDI ONE, VILLAGE-JANAULA, SECTOR-1, PATAUDI, GURUGRAM
10.813
0
207
0
207
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
995.304995.304995.304
Cost of the apartments000
Cost of the infrastructure862.722862.722862.722
Others costs147.514147.514147.514


3599 Lakhs
40 Lakhs
0 Lakhs
3599 Lakhs
No
31-03-2024
31-03-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN24-12-2022 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN24-12-2022 View Document
3ZONING PLAN24-12-2022 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND24-12-2022 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN29-07-2023 View Document
6DEMARCATION PLAN07-08-2023 View Document
7A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS07-08-2023 View Document
8DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-08-2023 View Document
9NEC24-05-2024 ------
10SCO PLAN- 6, 7, 8, 9, 10, 14, 15, 16 TYPE- B24-05-2024 ------
11WATER SUPPLY NETWORK PLAN-24-05-2024 ------
12NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT24-05-2024 View Document
13ROAD LAYOUT24-05-2024 ------
14STROM WATER NETWORK PLAN24-05-2024 ------
15ELECTRICITY SUPPLY24-05-2024 ------
16SCO PLAN- 01, 03 TYPE- A24-05-2024 ------
17AKS SIJRA24-05-2024 ------
18DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD24-05-2024 View Document
19SCO PLAN 11, 1724-05-2024 ------
20CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT24-05-2024 View Document
21SEWERAGE NETWORK PLAN24-05-2024 ------
22FLOOR PLAN24-05-2024 ------
23JAMABANDI WITH LICENCE ENTRY24-05-2024 ------
24SCO PLAN- 02, 04 TYPE- A24-05-2024 ------
25SCO PLAN- 5, 12 TYPE- B24-05-2024 ------