1309, 13TH FLOOR, DR. GOPAL DAS BHAWAN, 28 BARAKHAMBA ROAD, NEW DELHI 110001
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
https://www.signatureglobal.in
XXXX888R
U70100DL2008PTC176641
SIGNATURE GLOBAL PARK-I (2)
VILLAGE DHUNELA, SECTOR 36, GURUGRAM
SOHNA
GURUGRAM
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
RAVI AGGARWAL
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
818305
14-12-2022
307384
YES BANK LTD.
HRERA Gurugram
2
818304
14-12-2022
116433
YES BANK LTD.
HRERA Gurugram
1.09 (Acre)
2.64
2.41
5.0 (Acre)
18 of 2021 Dated 16-04-2021
Yes
6717.02 Lakhs
485.31 Lakhs
5005.55 Lakhs
0 Lakhs
1226.16 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1.09
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
1.09
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
N/A
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
0
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
0
YET TO BE PREPARED
3
STORM WATER DRAINAGE
0
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
YET TO BE PREPARED
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
20-04-2021 (date)
09-09-2021 (date)
01-01-2023
31-03-2025
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
89.060
64
16
Apartment/Shops/Other Buildings
64.860
72
18
Apartment/Shops/Other Buildings
35.204
8
2
Apartment/Shops/Other Buildings
61.540
8
2
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Land
485.31
Other cost
35
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
200.00
Shops
0
Plots
0
Other cost
48.0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
500.00
500.00
200.00
300.00
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
52.50
58.06
95.44
105.15
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
400.00
500.00
500.00
0
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
115.90
124.97
136.35
0
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
500.00
400.00
500.00
Shops
0
0
0
Plots
0
0
0
Other Cost
106.81
115.24
102.27
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (2025)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Yes
No
SBM BANK LIMITED, DLF CAPITAL POINT, BABA KHARAK SINGH MARG, CONNAUGHT PLACE, DELHI-110001
20052021001874
STCB0000065
110332002
065
Lalit Kumar Aggarwal and Pradeep Kumar Aggarwal Address-34, Road No.61, West Punjabi Bagh Delhi 110026
ATTACHED
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO.18 OF 2021
ALREADY BEEN OBTAINED
06-04-2021
II. FOREST NOC - LG1-GM0-BVMM
ALREADY BEEN OBTAINED
13-11-2020
III. ENVIRONMENT CLEARANCE-EC21B038HR160253
ALREADY BEEN OBTAINED
17-12-2021
IV. FIRE NOC-FS/2021/107
ALREADY BEEN OBTAINED
19-10-2021
Yes
Yes
SIGNATURE GLOBAL PARK-II, REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
11.0625
0
197
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
9391.0
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
135.0
0
0
Others costs
9256.0
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2021
30-06-2021
SIGNATURE GLOBAL PARK-III(EXT.), PHASE-1,REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
3.35
0
152
152
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
6804.90
0
3151.62
Cost of the apartments
2100.00
0
1203.81
Cost of the infrastructure
412.2
0
30.20
Others costs
4292.7
0
5993.47
5124.11 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2023
31-12-2023
SIGNATURE GLOBAL PARK-IV, REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
11.6500
540
0
538
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
24162.47
0
19910.08
Cost of the apartments
13108.60
0
10146.77
Cost of the infrastructure
1386.49
0
95.89
Others costs
9667.38
0
9567.42
21487.52 Lakhs
6855.12 Lakhs
2250.0 Lakhs
2250.0 Lakhs
No
30-07-2022
30-07-2022
SIGNATURE GLOBAL PARK-V, REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
8.75565
292
0
290
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
13554.30
0
11166.67
Cost of the apartments
6314.60
0
4780.08
Cost of the infrastructure
1014.6
0
252.82
Others costs
6225.1
0
6133.77
11182.43 Lakhs
5847.62 Lakhs
1500.00 Lakhs
1500.00 Lakhs
No
30-07-2022
30-07-2022
SIGNATURE GLOBAL PARK-II,REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
8.26
368
366
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
16246.73
0
15030.46
Cost of the apartments
8497.0
0
8496.98
Cost of the infrastructure
1090.94
0
77.10
Others costs
6658.79
0
6456.38
16739.0 Lakhs
4486.14 Lakhs
2500.0 Lakhs
2500.0 Lakhs
No
31-12-2022
31-12-2022
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED & CERAMIC TILES
2
WALL FINISHING DETAILS
OBD
3
KITCHEN DETAILS
ISI MARKED
4
BATHROOM FITTINGS
ISI MARKED
5
WOOD WORK ETC
ISI MARKED
6
DOORS AND WINDOS FRAMES
WOODEN(DOOR FRAME), ALUMINIUMN/UPVC(WINDOW FRAME)
7
GLASS WORK
ISI MARKED
8
ELECTRIC FITTINGS
ISI MARKED
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
RCC/PVC
11
WATER STORAGE
ISI MARKED
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
ALUMINIUMN/UPVC
13.1
WINDOWS/GLAZINGS
FLUSH DOOR
14
DOORS
FLUSH DOOR
14.1
MAIN DOORS
FLUSH DOOR
14.2
INTERNAL DOORS
FLUSH DOOR
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
ISI MARKED
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
TEXTURE PAINT
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
VITRIFIED TILE
1 . 2
WALLS
OBD
1 . 3
CEILING
OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
VITRIFIED TILE
2 . 2
WALLS
OBD
2 . 3
CEILING
OBD
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC TILE(ANTI-SKID)
3 . 2
WALLS
CERAMIC TILE
3 . 3
CEILING
GRID CEILING
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
ISI MARKED
3 . 6
FITTING/FIXTURES
ISI MARKED
4 . BED ROOMS
4 . 1
FLOOR
VITRIFIED TILE
4 . 2
WALLS
OBD
4 . 3
CEILING
OBD
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
VITRIFIED TILE
5 . 2
WALLS
OBD
5 . 3
CEILING
OBD
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
ISI MARKED
5 . 6
FIXTURES
ISI MARKED
6 . KITCHEN
6 . 1
FLOOR
VITRIFIED TILE
6 . 2
WALLS
OBD
6 . 3
CEILING
OBD
6 . 4
COUNTERS
GRANITE
6 . 5
FIXTURES
ISI MARKED
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT