HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1232-2022
Submission Date : 19-12-2022 02:47:12 PM
Applicant Type : Company
Project Type: NEW




SIGNATUREGLOBAL HOMES PVT. LTD.
1309, 13TH FLOOR, DR. GOPAL DAS BHAWAN, 28 BARAKHAMBA ROAD, NEW DELHI 110001
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
https://www.signatureglobal.in
XXXX888R
U70100DL2008PTC176641
 
 


 
 


 
 


 
 







SIGNATURE GLOBAL PARK-I (2)
VILLAGE DHUNELA, SECTOR 36, GURUGRAM
SOHNA
GURUGRAM
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in
RAVI AGGARWAL
01244908200
9810899381 (Number Shared by Promoter in Public)
compliance@signatureglobal.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
181830514-12-2022307384YES BANK LTD.HRERA Gurugram
281830414-12-2022116433YES BANK LTD.HRERA Gurugram







1.09 (Acre)
2.64
2.41
5.0 (Acre)
18 of 2021 Dated 16-04-2021
Yes







6717.02 Lakhs
485.31 Lakhs
5005.55 Lakhs
0 Lakhs
1226.16 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1.09
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total1.09




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEN/ANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0YET TO BE PREPARED
2WATER SUPPLY SYSTEM0YET TO BE PREPARED
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


20-04-2021 (date)
09-09-2021 (date)
01-01-2023
31-03-2025
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings89.0606416
Apartment/Shops/Other Buildings64.8607218
Apartment/Shops/Other Buildings35.20482
Apartment/Shops/Other Buildings61.54082





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
Land485.31
Other cost35

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments200.00
Shops0
Plots0
Other cost48.0

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments500.00500.00200.00300.00
Shops0000
Plots0000
Other Cost52.5058.0695.44105.15

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments400.00500.00500.000
Shops0000
Plots0000
Other Cost115.90124.97136.350

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments500.00400.00500.00
Shops000
Plots000
Other Cost106.81115.24102.27




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter (2025)
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
SBM BANK LIMITED, DLF CAPITAL POINT, BABA KHARAK SINGH MARG, CONNAUGHT PLACE, DELHI-110001
20052021001874
STCB0000065
110332002
065
Lalit Kumar Aggarwal and Pradeep Kumar Aggarwal Address-34, Road No.61, West Punjabi Bagh Delhi 110026
ATTACHED











Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO.18 OF 2021 ALREADY BEEN OBTAINED06-04-2021
II. FOREST NOC - LG1-GM0-BVMMALREADY BEEN OBTAINED13-11-2020
III. ENVIRONMENT CLEARANCE-EC21B038HR160253ALREADY BEEN OBTAINED17-12-2021
IV. FIRE NOC-FS/2021/107ALREADY BEEN OBTAINED19-10-2021








Yes


Yes









SIGNATURE GLOBAL PARK-II, REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
11.0625
0
197
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
9391.000
Cost of the apartments000
Cost of the infrastructure135.000
Others costs9256.000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
30-06-2021
30-06-2021




SIGNATURE GLOBAL PARK-III(EXT.), PHASE-1,REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
3.35
0
152
152
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
6804.9003151.62
Cost of the apartments2100.0001203.81
Cost of the infrastructure412.2030.20
Others costs4292.705993.47


5124.11 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2023
31-12-2023




SIGNATURE GLOBAL PARK-IV, REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
11.6500
540
0
538
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
24162.47019910.08
Cost of the apartments13108.60010146.77
Cost of the infrastructure1386.49095.89
Others costs9667.3809567.42


21487.52 Lakhs
6855.12 Lakhs
2250.0 Lakhs
2250.0 Lakhs
No
30-07-2022
30-07-2022




SIGNATURE GLOBAL PARK-V, REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
8.75565
292
0
290
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
13554.30011166.67
Cost of the apartments6314.6004780.08
Cost of the infrastructure1014.60252.82
Others costs6225.106133.77


11182.43 Lakhs
5847.62 Lakhs
1500.00 Lakhs
1500.00 Lakhs
No
30-07-2022
30-07-2022




SIGNATURE GLOBAL PARK-II,REVENUE ESTATE OF VILLAGE DHUNELA, TEHSIL-SOHNA, DISTRICT-GURUGRAM
8.26
368
366
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
16246.73015030.46
Cost of the apartments8497.008496.98
Cost of the infrastructure1090.94077.10
Others costs6658.7906456.38


16739.0 Lakhs
4486.14 Lakhs
2500.0 Lakhs
2500.0 Lakhs
No
31-12-2022
31-12-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED & CERAMIC TILES
2WALL FINISHING DETAILSOBD
3KITCHEN DETAILSISI MARKED
4BATHROOM FITTINGSISI MARKED
5WOOD WORK ETCISI MARKED
6DOORS AND WINDOS FRAMESWOODEN(DOOR FRAME), ALUMINIUMN/UPVC(WINDOW FRAME)
7GLASS WORKISI MARKED
8ELECTRIC FITTINGSISI MARKED
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSRCC/PVC
11WATER STORAGEISI MARKED
12LIFT DETAILSNA
13EXTERNAL GLAZINGSALUMINIUMN/UPVC
13.1WINDOWS/GLAZINGSFLUSH DOOR
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE
1 . 2 WALLSOBD
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILE
2 . 2 WALLSOBD
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILE(ANTI-SKID)
3 . 2 WALLSCERAMIC TILE
3 . 3 CEILINGGRID CEILING
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSISI MARKED
3 . 6 FITTING/FIXTURESISI MARKED
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILE
4 . 2 WALLSOBD
4 . 3 CEILINGOBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORVITRIFIED TILE
5 . 2 WALLSOBD
5 . 3 CEILINGOBD
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSISI MARKED
5 . 6 FIXTURESISI MARKED
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILE
6 . 2 WALLSOBD
6 . 3 CEILINGOBD
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESISI MARKED
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN16-12-2022 View Document
2A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS19-12-2022 View Document
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN16-12-2022 View Document
4SEWERAGE PLAN12-01-2023 ------
5ROADS AND PAVEMENT PLAN12-01-2023 ------
6CA LAND COST12-01-2023 ------
7IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN12-01-2023 View Document
8DEMARCATION PLAN12-01-2023 View Document
9WATER SUPPLY PLAN12-01-2023 ------
10NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT12-01-2023 View Document
11DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.12-01-2023 View Document
12ZONING PLAN12-01-2023 View Document
13CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT12-01-2023 View Document
14BUILDING PLAN APPROVAL TYPE A(12)12-01-2023 ------
15CASH FLOW STATEMENT OF THE PROPOSED PROJECT12-01-2023 View Document
16DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD12-01-2023 View Document
17COPY OF LICENSE ALONG WITH SCHEDULE OF LAND12-01-2023 View Document
18PROMOTER AFFIDAVITE SG PARK-I (2)12-01-2023 ------
19STORM WATER DRAINAGE PLAN12-01-2023 ------