HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1223-2022
Submission Date : 21-12-2022 02:58:11 PM
Applicant Type : Company
Project Type: NEW




DLF LIMITED
3RD FLOOR, DLFSHOPPING MALL,ARJUN MARG, DLF CITYPHASE I, GURUGRAM -122002
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
https://www.dlf.in
XXXX494N
L7010HR1963PLC002484
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







INDEPENDENT FLOORS AT DLF GARDENCITY ENCLAVE PHASE 2
SECTOR 93
HARSARU ST
GURUGRAM
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in
YUDHVEER SINGH
01244769000
9711080232 (Number Shared by Promoter in Public)
haryanarera@dlf.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
152150016-12-20221949000.00ICICIHRERA Gurugram







20277 (Sqr/mtrs)
2.64
2.64
108936.11 (Sqr/mtrs)
94 of 2021 Dated 12.11.2021
No
Address     1ST FLOOR,SHOPPING MALLCOMPLEX, ARJUNMARG, DLF PHASE-I,DLF CITY, GURUGRAMHR 122002 IN
Address     1ST FLOOR,SHOPPING MALL COMPLEX, ARJUN MARG, DLF PHASE-I,DLF CITY, GURUGRAMHR 122002
Address     1ST FLOOR,SHOPPING MALLCOMPLEX, ARJUNMARG, DLF PHASE-I,DLF CITY, GURUGRAMHR 122002 IN
Address     1ST FLOOR,DLF GATEWAY TOWER, R BLOCK,DLF CITY,PHASE-III GURUGRAM HR122002
Address     3RD FLOOR,DLF SHOPPING MALL,ARJUN MARG, DLFCITY PHASE I,GURUGRAM - 122002
Annexure-B- COLLABORATOR
YES
Yes
AS PER ANNEXURE
No
Yes
Yes







49568 Lakhs
8962 Lakhs
30890 Lakhs
3002 Lakhs
6714 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS20277
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total20277




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTEDYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS319AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM156AS PER PROJECT REPORT
3STORM WATER DRAINAGE151AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM547AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL209AS PER PROJECT REPORT
6STREET LIGHTING65AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING82AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS690AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT
15EARTH WORKS158AS PER PROJECT REPORT
16STP158AS PER PROJECT REPORT
17UGT143AS PER PROJECT REPORT
18RAINWATER HARVESTING114AS PER PROJECT REPORT
19CONSTRUCTION OF CIRCULATION ROADS117AS PER PROJECT REPORT
20PARKING90AS PER PROJECT REPORT


NA (date)
NA (date)
01-10-2023
31-10-2028
Plot Area(In Square Meter)Number of plots in the project
150.00124
134.007
144.8101
143.9101
149.9942
150.001


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings80.042496124
Apartment/Shops/Other Buildings69.089287
Apartment/Shops/Other Buildings77.27141
Apartment/Shops/Other Buildings79.79441
Apartment/Shops/Other Buildings80.03882
Apartment/Shops/Other Buildings80.04241





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments633
Shops0
Plots0

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments633154515452178
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments2811308930893089
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3089154515451228
Shops0000
Plots0000

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments122812281228595
Shops0000
Plots0000

ParticularsYear-2028
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments595
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System38.9638.9638.96
Sewerage treatment & garbage disposal52.2952.2952.29
Electricity Supply System0136.76136.76
Storm Water Drainage37.8637.8637.86
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
Earth works79.2079.20
STP39.6039.6039.60
UGT35.6435.6235.64
Construction of circulation road11.72
Parking9.0113.5122.51
RWH39.9239.92
Street Lighting16.3616.36
Construction of circular roads17.58
Construction of circulation roads29.31

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements63.90127.80127.800
Water Supply System38.96000
Sewerage treatment & garbage disposal52.29000
Electricity Supply System136.76136.7600
Storm Water Drainage37.86000
Parks and Playgrounds000345.23
Clubhouse/community centres0000
Shopping area0000
Other0000
Construction of circulation roads29.3117.5811.72
Street Lighting16.3616.36
Parking22.5113.519.01
Security and fire fighting32.95
STP39.60
UGT35.64
RWH34.22

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds345.23
Clubhouse/community centres0
Shopping area0
Other0
Security and fire fighting49.92












Yes
No
ICICI BANK LTD., GROUND FLOOR, GOPAL DAS BHAWAN, CONNAUGHT PLACE, NEW DELHI, 110001
000705053860
ICIC0001352
110229137
1352
01. Mr. Vivek Anand (E1001, Palm Springs, Golf Course Road, opposite IBIS Hotel, Sector 54,Gurgaon, Haryana 122002) 02. Mr. Puneet Rakheja (H.No. 386, Sector 31, Faridabad, Haryana 121003)03. Mr. Pankaj Jain (C701, Apex Acacia Valley, Sector 3, Ghaziabad, Uttar Pradesh 201010) 04. Mr.Saurabh Kumar Gupta (1116, Vikas Kunj, Vikaspuri, Delhi 110018) 05. Mr. Gaurav Arora (A-33, NearMehfil Banquet Hall, Mahendru Enclave, GT Karnal Road, Delhi 110009) 06. Ms. Sandhya Singla(Neelanchal Apartments, Plot No. 3, Sector 4, Dwarka, Delhi 110075) 07. Mr. Ashok Nanda (A255, SuryaNagar, Chander Nagar, Ghaziabad, Uttar Pradesh 201011) 08. Mr. Rajeev Singhal (Flat No. 14, TowerNo. 4, Raj Nagar Extension, Signature Homes, Ghaziabad, Uttar Pradesh 201001) 09. Mr. Sujeet KumarSinha (C-061, DLF New Town Heights, IMT Manesar, Sector 91, Gurgaon, Haryana 122505) 10. Mr.Pankaj Kumar (A3, Rajcottage 1/18, Rajendra Nagar, Ghaziabad, Uttar Pradesh 201005)
Uploaded











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No


Yes
No
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. SERVICE PLAN ESTIMATESALREADY BEEN OBTAINED24-01-2022
II. ELECTRICAL LOAD AVAILABILITYALREADY BEEN OBTAINED22-10-2021
III. STORM WATER DRAINAGEALREADY BEEN OBTAINED28-12-2021
IV. SEWAGE DISPOSALALREADY BEEN OBTAINED29-12-2021
V. WATER SUPPLYALREADY BEEN OBTAINED19-10-2021
VI. LAYOUT PLANALREADY BEEN OBTAINED21-02-2022
VII. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED28-04-2022
VIII. LICENSEALREADY BEEN OBTAINED12-11-2021








Yes


Yes


As per RERA Act







INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
0.969
72
18
72
18
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
484754732936
Cost of the apartments411347992396
Cost of the infrastructure000
Others costs442674540


1715 Lakhs
6964 Lakhs
0 Lakhs
1083 Lakhs
No
20-06-2024
31-10-2023




INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
1.096
52
13
52
13
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
613361372522
Cost of the apartments453547301133
Cost of the infrastructure000
Others costs42214071389


4030 Lakhs
6142 Lakhs
0 Lakhs
2243 Lakhs
No
19-11-2024
24-11-2024




INDEPENDENT FLOORS AT DLF GARDENCITY ENCLAVE, GURGAON
6.83
388
97
388
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
23468242922521
Cost of the apartments18345209901982
Cost of the infrastructure136700
Others costs30453302539


4401 Lakhs
46459 Lakhs
0 Lakhs
0 Lakhs
No
19-08-2027
19-08-2027




DLF GARDENCITY, GURGAON
16.25
0
109
0
109
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
14392040402
Cost of the apartments000
Cost of the infrastructure14192010384
Others costs203018


87 Lakhs
160 Lakhs
0 Lakhs
0 Lakhs
No
27-06-2023
27-06-2023




INDEPENDENT FLOORS AT DLF GARDENCITY SECTOR 91/92
2.246
124
31
124
31
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
12800127504155
Cost of the apartments10000100981921
Cost of the infrastructure000
Others costs280026522234


6143 Lakhs
17243 Lakhs
0 Lakhs
3266 Lakhs
No
31-03-2025
31-03-2025




GARDENCITY ARCADE, GURGAON
1.42
99
1
99
1
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
630863822066
Cost of the apartments41624409814
Cost of the infrastructure000
Others costs214619731252


334 Lakhs
8131 Lakhs
0 Lakhs
140 Lakhs
No
29-04-2025
29-04-2025




DLF GARDENCITY ENCLAVE, GURGAON
19
0
270
0
270
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
10943134303232
Cost of the apartments000
Cost of the infrastructure595084370
Others costs301430141253


693 Lakhs
9193 Lakhs
0 Lakhs
0 Lakhs
No
29-03-2024
29-03-2024




SUMMIT PLAZA SECTOR-54, GURUGRAM, HARYANA
2.65
311
0
45
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
24956278826814
Cost of the apartments18530249205514
Cost of the infrastructure000
Others costs642629621300


3175 Lakhs
7449 Lakhs
0 Lakhs
2374 Lakhs
No
01-06-2026
01-06-2026




THE GROVE DLF 5, SECTOR-54, GURUGRAM, HARYANA
5.3073
292
73
52
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
48115602946168
Cost of the apartments39176478044174
Cost of the infrastructure000
Others costs8939124901994


2075 Lakhs
30509 Lakhs
0 Lakhs
0 Lakhs
No
01-12-2025
01-12-2025




SIRIS ESTATE DLF CITY PHASE-III, SECTOR 24, GURUGRAM, HARYANA
1.243
48
12
48
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
629368963350
Cost of the apartments516758092488
Cost of the infrastructure000
Others costs11261087862


7944 Lakhs
9238 Lakhs
0 Lakhs
2545 Lakhs
No
01-10-2024
01-10-2024




INDEPENDENT FLOORS AT DLF CITY PHASE – III DLF CITY PHASE-III, SECTOR 24, GURUGRAM, HARYANA
1.243
48
12
48
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
628068803168
Cost of the apartments524458352230
Cost of the infrastructure000
Others costs10361045938


7850 Lakhs
10776 Lakhs
0 Lakhs
3102 Lakhs
No
01-12-2024
01-12-2024




INDEPENDENT FLOORS AT DLF CITY PHASE – I DLF CITY PHASE-I, GURUGRAM, HARYANA
0.621
28
7
28
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
383340151462
Cost of the apartments313134921035
Cost of the infrastructure000
Others costs702523427


3851 Lakhs
8526 Lakhs
0 Lakhs
1784 Lakhs
No
01-02-2024
01-02-2024




INDEPENDENT FLOORS AT DLF CITY PHASE - IV DLF CITY PHASE - IV SECTOR-27, GURUGRAM, HARYANA
1.625
60
15
60
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
822793271130
Cost of the apartments64447333441
Cost of the infrastructure000
Others costs17831994689


5555 Lakhs
23281 Lakhs
0 Lakhs
720 Lakhs
No
01-05-2025
01-05-2025










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEIPS FLOORING / TILES / GRANITE
2WALL FINISHING DETAILSWHITE WASH / OBD
3KITCHEN DETAILSWHITE WASH / OBD
4BATHROOM FITTINGSNA
5WOOD WORK ETCNIL
6DOORS AND WINDOS FRAMESWOODEN FRAMES FOR DOORS UPVC/AL/MS FRAMES FOR WINDOWS
7GLASS WORKPLAIN GLASS
8ELECTRIC FITTINGSMODULAR FITTINGS
9CONDUCTING AND WIRING DETAILSPVC CONDUITS, FRLS WIRING
10CUPBOARD DETAILSNIL
11WATER STORAGEOHT WATER TANKS
12LIFT DETAILSBRANDED MAKE
13EXTERNAL GLAZINGSSINGLE GLASS UNIT WITH CLEAR GLASS UPVC/AL FRAMES AND SHUTTERS INHABITABLE ROOMS. CLEAR/FROSTED GLASS IN TOILETS
13.1WINDOWS/GLAZINGSSINGLE GLASS UNIT WITH CLEAR GLASS UPVC/AL FRAMES AND SHUTTERS INHABITABLE ROOMS. CLEAR/FROSTED GLASS IN TOILETS
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGLIVING, DINING & BEDROOMS
16ELECTRICAL FITTINGSMODULAR FITTINGS
17CNG PIPE LINENIL
18PROVISION OF WIFI AND BROADBAND FACILITYNIL
19EXTERNAL FINISHING/COLOUR SCHEMEWEATHER SHIELD PAINT ON EXTERNAL SURFACES, OBD IN STILTS.
20INTERNAL FINISHINGWHITE WASH / OBD
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORINDIAN MARBLE
1 . 2 WALLSACRYLIC EMULSION / OBD
1 . 3 CEILINGACRYLIC EMULSION / OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN
2 . 2 WALLSACRYLIC EMULSION / OBD
2 . 3 CEILINGACRYLIC EMULSION / OBD
2 . 4 MODULAR WARDROBESNIL
3 . MASTER TOILET
3 . 1 FLOORANTI-SKID TILES
3 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSION PAINT & MIRRO
3 . 3 CEILINGACRYLIC EMULSION PAINT / OBD
3 . 4 COUNTERSGRANITE / SYNTHETIC STONE
3 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, FLOOR MOUNTED / WALL-HUNG WC
3 . 6 FITTING/FIXTURESEXHAUST FAN, TOWEL RAIL / RING, GEYSER
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION PAINT / OBD
4 . 3 CEILINGACRYLIC EMULSION PAINT / OBD
4 . 4 WARDROBESNIL
5 . TOILET
5 . 1 FLOORIPS FLOORING / TILES
5 . 2 WALLSCOMBINATION OF TILES, ACRYLIC EMULSION PAINT & MIRROR
5 . 3 CEILINGWHITEWASH / OBD
5 . 4 COUNTERSGRANITE / SYNTHETIC STONE
5 . 5 SANITARY WARE/CP FITTINGSCP FITTINGS, WASH BASIN, FLOOR MOUNTED / WALL-HUNG WC
5 . 6 FIXTURESEXHAUST FAN, TOWEL RAIL / RING, GEYSER
6 . KITCHEN
6 . 1 FLOORANTI-SKID TILES
6 . 2 WALLSTILES UP-TO 2’ ABOVE COUNTER & OBD / ACRYLIC EMULSION PAINT IN BALANCE AREA
6 . 3 CEILINGOBD / ACRYLIC EMULSION PAINT
6 . 4 COUNTERSGRANITE /SYNTHETIC STONE
6 . 5 FIXTURESCP FITTINGS, SS SINK, EXHAUST FAN
6 . 6 KITCHEN APPLIANCESNIL
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORIPS / TILES
7 . 2 WALLS & CEILINGWHITEWASH
7 . 3 TOILETTILE FLOORING & CLADDING, CONVENTIONAL CP FITTINGS, CHINAWARE
7 . 4 BALCONYIPS / TILES
8 . SIT-OUTS
8 . 1 FLOORIPS / TILES
8 . 2 WALLS & CEILINGOBD
8 . 3 RAILINGSMS RAILINGS
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DEMARCATION PLAN16-12-2022 View Document
2CASH FLOW STATEMENT OF THE PROPOSED PROJECT20-12-2022 View Document
3DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.16-12-2022 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND16-12-2022 View Document
5ZONING PLAN16-12-2022 View Document
6SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN16-12-2022 View Document
7CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT20-12-2022 View Document
8DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD16-12-2022 View Document
9IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN16-12-2022 View Document
10IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN16-12-2022 View Document
11A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS20-12-2022 View Document
12NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT20-12-2022 View Document
13BUILDING PLAN TYPICAL (7.5 X 20, 150SQ. MTR)20-12-2022 ------