HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1176-2022
Submission Date : 28-11-2022 02:31:10 PM
Applicant Type : Firm
Project Type: NEW


DC MANSION LLP
264, BLOCK-A, VASANT VIHAR NARWANA, DISTT. JIND - 166116
9888883250 (Number Shared by Promoter in Public)
dcmansionllp@gmail.com
ABB7323
AAUFD0030F















NARWANA GREENS
VILLAGE NARWANA, SECTOR-15, NARWANA,
NARWANA
JIND
9888883250 (Number Shared by Promoter in Public)
dcmansionllp@gmail.com
PRINCE
9888883250 (Number Shared by Promoter in Public)
dcmansionllp@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1827428-11-2022538000HDFC BANK, CHANDIGARHHRERA Panchkula







11.63125 (Acre)
0
0
11.63125 (Acre)
LICENSE NO. 191 OF 2022, DATED 22.11.2022
Yes







2270.178 Lakhs
1007.863 Lakhs
0 Lakhs
815.000 Lakhs
2270.178 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD6.035
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS2.740
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1.020
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.111
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1.200
12ANY OTHER0.056
13AREA OF UD0.0450
14COMMERCIAL AREA0.424
Total11.631




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP No
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS182.34AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM77.14AS PER PROJECT REPORT
3STORM WATER DRAINAGE64.48AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM163.87AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL100.93AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS38.10AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER12.24AS PER PROJECT REPORT
15BOUNDARY WALL GATE AND GUARD ROOM175.90AS PER PROJECT REPORT


22-11-2022 (date)
NA (date)
01-12-2022
21-11-2027
Plot Area(In Square Meter)Number of plots in the project
15095
149.8013
142.089
135.50020
134.804
129.208
122.255
101.258
140.441
148.031
150.001
143.571
149.231
127.891
140.761
94.571
149.421
1715.8671


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.26
Water Supply System8.57
Sewerage treatment & garbage disposal11.21
Electricity Supply System18.21
Storm Water Drainage7.16
Parks and Playgrounds4.23
Clubhouse/community centres0
Shopping area0
Other1.36
Boundary Wall Gate and Guard Room19.54

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.2620.2620.2620.26
Water Supply System8.578.578.578.57
Sewerage treatment & garbage disposal11.2111.2111.2111.21
Electricity Supply System18.2118.2118.2118.21
Storm Water Drainage7.167.167.167.16
Parks and Playgrounds4.234.234.234.23
Clubhouse/community centres0000
Shopping area0000
Other1.361.361.361.36
Boundary Wall Gate and Guard Room19.5419.5419.5419.54

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.2620.2620.2620.26
Water Supply System8.578.578.578.57
Sewerage treatment & garbage disposal11.2111.2111.2111.21
Electricity Supply System18.2118.2118.2118.21
Storm Water Drainage7.167.167.167.16
Parks and Playgrounds4.234.234.234.23
Clubhouse/community centres0000
Shopping area0000
Other1.361.361.361.36
Boundary Wall Gate and Guard Room19.5419.5419.5419.54












No
No
HDFC BANK INDUSTRIAL AREA PHASE 1, CHANDIGARH
59219999991717
HDFC0000873
160240020
000873
PRINCE CHHABRA C/O 264, Block A Basant ViharJind Haryana-126116
YES











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE ALREADY BEEN OBTAINED22-11-2022
II. LAYOUT PLANALREADY BEEN OBTAINED22-11-2022








Yes


Yes


FULL AGREEMENT













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1CASH FLOW STATEMENT OF THE PROPOSED PROJECT28-11-2022 View Document
2ZONING PLAN28-11-2022 View Document
3DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.28-11-2022 View Document
4IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN28-11-2022 View Document
5DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD28-11-2022 View Document
6COPY OF LICENSE ALONG WITH SCHEDULE OF LAND27-11-2022 View Document
7NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT28-11-2022 View Document
8IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN28-11-2022 View Document
9DEMARCATION PLAN28-11-2022 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 CORRIGENDUM 20-03-2024 View Document
2 CORRIGENDUM 18-06-2024 View Document
3 Supplementary RC with Performa A-H, REP-II and Revised Layout Plan 02-12-2024 View Document