HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1211-2022
Submission Date : 14-12-2022 06:16:46 PM
Applicant Type : Company
Project Type: NEW




BST DEVELOPERS INDIA PVT LTD
308, ILD TRADE TOWER, SECTOR 47,MAIN SOHNA ROAD, GURUGRAM 122001
01244280032
9540400032 (Number Shared by Promoter in Public)
info@bstdevelopers.com
https://bstdevelopers.com
XXXX948N
U45200HR2013PTC049176
 
 


 
 


 
 







GREEN BHOOMI
SECTOR 99A, VILLAGE GOPALPUR, TEHSIL HARSARU
HARSARU ST
GURUGRAM
9582245696 (Number Shared by Promoter in Public)
info@bstdevelopers.com
PANKAJ GUPTA
9582245696 (Number Shared by Promoter in Public)
info@bstdevelopers.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150151809-12-2022460865ICICI BANK HRERA Gurugram
299508905-01-20234561ICICI BANK HRERA Gurugram







5.6375 (Acre)
1
1
5.6375 (Acre)
170 of 2022(22.10.2022)
No
Address     VILLAGE GOPALPUR, TEHSIL HARSARU, GURUGRAM
Annexure-B- DEVELOPER
YES
Yes
JOINT DEVELOPMENT AGREEMENT WHEREIN LAND OWNER AND DEVELOPER SHALL SHARE THE AREA OF COLONY
No
Yes
No







4915.78 Lakhs
2868.51 Lakhs
0.0 Lakhs
760.20 Lakhs
1287.07 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD11636.518
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.00
3CONSTRUCTION OF ROADS6129.369
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1711.210
6GREEN BELTS0.00
7VEHICLE PARKINGS0.00
8ELECTRICITY SUB-STATION150
9CLUB HOUSE0.00
10SEWAGE AND SOLID WASTE TREATMENT FACILITY450.00
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES2281.523
12ANY OTHER0
13COMMERCIAL456.342
Total22814.962




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYHSVPNo
ELECTRICITYHSVPNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS146.27SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM162.64SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE96.32SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM21.63SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL150.41SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS2.91SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


27-10-2022 (date)
NA (date)
26-01-2022
25-01-2027
Plot Area(In Square Meter)Number of plots in the project
127.56822
116.61633
128.26710
161.2452
121.21010
100.95412
144.5371
141.7351
138.9401
136.1391
133.3441
130.5431
127.7481


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
Land1700.00

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other39.10
Collaboration Advance557.96
Statutory Approvals296.10

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements29.2514.6314.6314.63
Water Supply System0081.3281.32
Sewerage treatment & garbage disposal0075.2175.21
Electricity Supply System0000
Storm Water Drainage0048.1648.16
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
STP816.016.0
Underground Water Tank15.539.5
Rainwater Harvesting16.04.0

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0014.6314.63
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System025.0050.000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Electrical sub station20.0070.0010.00
Street Light7.2114.42

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements14.6314.6314.63
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds2.9100
Clubhouse/community centres000
Shopping area000
Other000
Construction of Road14.706.30
Commercial Development20.005.00












Yes
No
ICICI BANK LTD 559/1-A GF DAYANAND COLONY, NEW RAILWAY ROAD, GURUGRAM 122001
424405000847
ICIC0004244
110229288
4244
Yoginder Tanwar, Address-So Satbir Singh Silani 207 Gurugram 122103











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
No
Yes
Yes
Yes
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE ALREADY BEEN OBTAINED27-10-2022
II. LAYOUT PLAN ALREADY BEEN OBTAINED27-10-2022
III. SERVICE PLAN ESTIMATES FROM GMDA ALREADY BEEN OBTAINED23-11-2022








Yes


Yes


As per RERA norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD01-12-2022 View Document
2A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS01-12-2022 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN01-12-2022 View Document
4COPY OF LICENSE ALONG WITH SCHEDULE OF LAND01-12-2022 View Document
5SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN01-12-2022 View Document
6IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN01-12-2022 View Document
7DEMARCATION PLAN14-12-2022 View Document
8ZONING PLAN14-12-2022 View Document
9NO LOAN CERTIFICATE18-08-2023 ------
10SIZRA18-08-2023 ------
11DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.18-08-2023 View Document
12NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT18-08-2023 View Document
13CASH FLOW STATEMENT OF THE PROPOSED PROJECT18-08-2023 View Document
14CA CERTIFICATE LAND COST ANNEXURE-518-08-2023 ------
15ELECTRICAL LOAD INTIMATION LETTER18-08-2023 ------
16JAMABANDI 18-08-2023 ------
17LAYOUT PLAN18-08-2023 ------
18PL-DDJAY BST EXTERNAL SITE PLAN-R1 SEWER LINE18-08-2023 ------
19PL-UNDER GROUND WATER TANK DETAIL FOR APPROVAL -18-03-2023-MODEL18-08-2023 ------
20PL-DDJAY BST EXTERNAL SITE PLAN-R1 STORM LINE18-08-2023 ------
21PL-UNDER GROUND WATER TANK STRU.DETAIL18-08-2023 ------
22PROMOTER AFFIDAVIT REGARDING BANK ACCOUNT18-08-2023 ------
23CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT18-08-2023 View Document