HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1165-2022
Submission Date : 15-11-2022 04:51:16 PM
Applicant Type : Company
Project Type: NEW




JAYANT BUILDHOME PRIVATE LIMITED
J-221, SARITA VIHAR, NEW DELHI-110076
9711012419 (Number Shared by Promoter in Public)
jayantbuildhome@gmail.com
http://jayantbuildhome.com
XXXX855E
U45200DL2008PTC176421
 
 


 
 


 
 


 
 







FLOWER VALLEY
VILLAGE- JARAUDA, SECTOR-25, JAGADHARI, YAMUNA NAGAR, HARYANA
JAGADHRI
YAMUNANAGAR
9728905241 (Number Shared by Promoter in Public)
jayantbuildhome@gmail.com
PRADEEP KHANNA
9728905241 (Number Shared by Promoter in Public)
jayantbuildhome@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1357514-11-2022125000HDFC BANKHRERA Panchkula







5.66875 (Acre)
2.0
2.0
5.66875 (Acre)
176 OF 2022 DATED 03.11.2022
Yes







1499.595 Lakhs
585 Lakhs
0 Lakhs
566.875 Lakhs
347.720 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD3.364
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS1.12845
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.424
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.0483
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.565
12ANY OTHER0
13COMMERCIAL0.123
14UGT0.0160
Total5.66875




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSEXISTING ROAD VILLAGENo
WATER SUPPLYCGWANo
ELECTRICITYUHBVNNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS100YET TO BE PREPARED
2WATER SUPPLY SYSTEM60YET TO BE PREPARED
3STORM WATER DRAINAGE60YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM60YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL50YET TO BE PREPARED
6STREET LIGHTING25YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS30YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15MAINTENANCE30YET TO BE PREPARED
16BOUNDARY WALL91.875YET TO BE PREPARED
17EARTH FILLING60YET TO BE PREPARED


03-11-2022 (date)
NA (date)
01-12-2022
02-11-2027
Plot Area(In Square Meter)Number of plots in the project
14865
12810
108.503


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.00
Water Supply System2.00
Sewerage treatment & garbage disposal2.00
Electricity Supply System2.00
Storm Water Drainage2.00
Parks and Playgrounds1.25
Clubhouse/community centres0
Shopping area0
Other0
EARTH FILLING2.00
BOUNDARY WALL4.00
MAINTENANCE1.25
STREET LIGHTING1.00

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.764.764.764.76
Water Supply System2.922.922.922.92
Sewerage treatment & garbage disposal2.382.382.382.38
Electricity Supply System2.922.922.922.92
Storm Water Drainage2.922.922.922.92
Parks and Playgrounds1.421.421.421.42
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING1.192.921.191.19
MAINTENANCE1.421.421.421.42
BOUNDARY WALL4.3754.3754.3754.375
EARTH FILLING2.922.922.922.92

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.764.764.764.76
Water Supply System2.922.922.922.92
Sewerage treatment & garbage disposal2.382.382.382.92
Electricity Supply System2.922.922.922.92
Storm Water Drainage2.922.922.922.92
Parks and Playgrounds1.421.421.421.42
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING1.191.191.191.19
MAINTENANCE1.421.421.421.42
EARTH FILLING2.922.922.922.92
BOUNDARY WALL4.3754.3754.3754.375

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.764.764.764.76
Water Supply System2.922.922.922.92
Sewerage treatment & garbage disposal2.382.382.382.38
Electricity Supply System2.922.922.922.92
Storm Water Drainage2.922.922.922.92
Parks and Playgrounds1.421.421.421.42
Clubhouse/community centres0000
Shopping area0000
Other0000
BOUNDARY WALL4.3754.3754.3754.375
STREET LIGHTING1.191.191.191.19
MAINTENANCE1.421.421.421.42
EARTH FILLING2.922.922.922.92

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.764.764.764.76
Water Supply System2.922.922.922.92
Sewerage treatment & garbage disposal2.382.382.382.38
Electricity Supply System2.922.922.922.92
Storm Water Drainage2.922.922.922.92
Parks and Playgrounds1.421.421.421.42
Clubhouse/community centres0000
Shopping area0000
Other0000
BOUNDARY WALL4.3754.3754.3754.375
STREET LIGHTING1.191.191.191.19
MAINTENANCE1.421.421.421.42
EARTH FILLING2.922.922.922.92

ParticularsYear-2027
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements4.764.764.765.56
Water Supply System2.922.922.922.52
Sewerage treatment & garbage disposal2.382.382.382.78
Electricity Supply System2.922.922.922.52
Storm Water Drainage2.922.922.922.52
Parks and Playgrounds1.421.421.421.77
Clubhouse/community centres0000
Shopping area0000
Other0000
STREET LIGHTING1.191.191.191.39
EARTH FILLING2.922.922.922.52
BOUNDARY WALL4.3754.3754.3754.75
MAINTENANCE1.421.421.421.77












Yes
No
HDFC BANK
50200065423252
HDFC0000480
110240072
480
PRINCE CHHABRA ADITYA GARG SANDEEP MANGLA
CA CERTIFICATE ATTACHED











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED03-11-2022
II. LAYOUT PLANALREADY BEEN OBTAINED03-11-2022








Yes


Yes


ATTACHED







FLOWER VALLEY AT VILLAGE- HALUWALA , SECTOR-25, JAGADHARI, YAMUNA NAGAR, HARYANA
15.85
0
282
0
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
385000
Cost of the apartments50000
Cost of the infrastructure175000
Others costs60000


0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
23-12-2026
23-12-2026










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1LC-IV AND LC-IV-B BILATERAL AGREEMENT15-11-2022 ------
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT15-11-2022 View Document
3DD15-11-2022 ------
4MUTATION15-11-2022 ------
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND12-11-2022 View Document
6IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN15-11-2022 View Document
7LETTER OF INTENT 15-11-2022 ------
8DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD15-11-2022 View Document
9JAMABANDI15-11-2022 ------
10ALLOTMENT15-11-2022 ------
11APPLICATION15-11-2022 ------
12SUMMARY OF AGREEMENT TO SALE15-11-2022 ------
13AGREEMENT15-11-2022 ------
14IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN15-11-2022 View Document
15DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.15-11-2022 View Document