HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1173-2022
Submission Date : 20-10-2022 05:58:37 PM
Applicant Type : Company
Project Type: NEW




WINGS REALTORS PRIVATE LIMITED
746-P, SECTOR 38, GURUGRAM, HARYANA
9716013600 (Number Shared by Promoter in Public)
akarunswami@gmail.com
http://www.wingsrealtors.com/
XXXX546M
U70100HR2011PTC041996
 
 


 
 


 
 


 
 







NKV GOLDEN AVENUE
VILLAGE SOHNA, SECTOR 35, SOHNA, GURUGRAM
SOHNA
GURUGRAM
9716013600 (Number Shared by Promoter in Public)
wingsrealtors01@gmail.com
ARUN KUMAR
9716013600 (Number Shared by Promoter in Public)
akarunswami@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150767107-10-2022415000ICICI BANKHRERA Gurugram







5.0125 (Acre)
1
1
5.0125 (Acre)
87 of 2021(27-10-2021)
Yes







2692.71 Lakhs
1072 Lakhs
0 Lakhs
386.5 Lakhs
456.18 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD2.5869
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS1.13675
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.3816
6GREEN BELTS0.236
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.1112
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.50125
12ANY OTHER0.131
13COMMERCIAL0.1935
14MILKBOOTH0.0068
Total5.285




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNHAIYes
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS100.02AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM138.80AS PER PROJECT REPORT
3STORM WATER DRAINAGE55.22AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM0AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL70.14AS PER PROJECT REPORT
6STREET LIGHTING19.23AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS3.09AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER127.18AS PER PROJECT REPORT


31-10-2022 (date)
NA (date)
15-09-2022
26-09-2026
Plot Area(In Square Meter)Number of plots in the project
116.2626
124.96140
125.69824
127.69515
136.51974
136.5771
139.310212
184.9161
598.1081


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots10

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots10101010

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots51055

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots5555

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots1010100




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal33.44
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements031.67347.509520.8375
Water Supply System00131.866.94
Sewerage treatment & garbage disposal33.44000
Electricity Supply System0000
Storm Water Drainage31.475420.983602.761
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lighting0013.971348.08867

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6666
Water Supply System8888
Sewerage treatment & garbage disposal6.926.926.926.92
Electricity Supply System0000
Storm Water Drainage2.82.82.82.8
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6120
Water Supply System8160
Sewerage treatment & garbage disposal6.92130
Electricity Supply System000
Storm Water Drainage2.85.60
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000












No
No
WRPL NKV GOLDEN AVENUE
165105002544
ICIC0001651
110229194
001651
Arun Kumar R/o 746P, Sector 38, Gurugram, Haryana
yes











Yes
No
Yes
No
No
No
No
No
No
No


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED27-10-2021
II. LAYOUT PLANALREADY BEEN OBTAINED01-04-2022
III. ZONING PLANALREADY BEEN OBTAINED12-10-2022
IV. SERVICE PLANS AND ESTIMATESALREADY BEEN OBTAINED19-07-2022








No


No















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN13-10-2022 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND13-10-2022 View Document
3ZONING PLAN20-10-2022 View Document
4IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN20-10-2022 View Document
5LAYOUT EXT WATER SUPPLY22-11-2022 ------
6LAYOUT EXT ROAD PLAN22-11-2022 ------
7LAYOUT EXT SEWAGE22-11-2022 ------
8ELECTRICAL LAYOUT22-11-2022 ------
9DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.22-11-2022 View Document
10NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT22-11-2022 View Document
11CASH FLOW STATEMENT OF THE PROPOSED PROJECT22-11-2022 View Document
12DEMARCATION PLAN22-11-2022 View Document
13DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD22-11-2022 View Document
14LAYOUT EXT DRAINAGE22-11-2022 ------