As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
Annexure-B- COLLABORATION AGREEMENT AND GPA ENCLOSED WITH THE APPLICATION.
YES THE AGREEMENTS HAVE BEEN REGISTERED.
Yes
THE LAND OWNER HAS IS NOT FULLY EQUIPPED TO EXECUTE AND COMPLETE THE WORK OF DEVELOPMENT OF THE COLONY AND HAS REQEUSTED TO DEVELOPER COMPANY TO ARRANGE TECHNICAL RESOURCES FOR ALL SANCTIONS FOR ESTABLISHMENT OF THE PROJECT.
No
Yes
Yes
3890.98 Lakhs
3396.871 Lakhs
0.00 Lakhs
221.42 Lakhs
272.69 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
9.72128
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
4.91483
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1.45086
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
1.85257
12
ANY OTHER
0
13
COMMERCIAL
0.50421
Total
18.44375
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
UHBVNL
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
59.78
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
22.14
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
22.14
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
55.36
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
22.14
AS PER PROJECT REPORT
6
STREET LIGHTING
13.29
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
26.57
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
16-08-2022 (date)
NA (date)
05-10-2022
15-08-2027
Plot Area(In Square Meter)
Number of plots in the project
134.522
8
149.851
2
140.394
1
117.584
1
149.933
4
141.342
2
127.019
2
137.434
5
135.991
31
100.451
1
112.861
1
117.00
13
121.207
9
113.342
1
114.01
9
90.617
9
102.787
1
110.420
1
90.617
10
99.146
5
126.836
27
126.110
1
118.577
1
128.969
23
147.145
1
140.463
1
110.632
25
125.911
1
148.335
1
107.097
9
105.643
10
107.097
9
135.068
1
134.053
2
107.097
9
105.643
10
107.097
9
134.053
2
130.249
1
117.00
13
133.929
1
101.150
1
117.00
14
108.518
1
120.923
1
121.576
4
139.957
1
145.283
1
103.950
7
90.461
1
103.692
1
117.686
1
122.130
3
113.750
4
118.993
6
120.708
13
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.99
Water Supply System
1.11
Sewerage treatment & garbage disposal
1.11
Electricity Supply System
2.77
Storm Water Drainage
1.11
Parks and Playgrounds
1.33
Clubhouse/community centres
0
Shopping area
0
Other
0.66
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.99
2.99
2.99
2.99
Water Supply System
1.11
1.11
1.11
1.11
Sewerage treatment & garbage disposal
1.11
1.11
1.11
1.11
Electricity Supply System
2.77
2.77
2.77
2.77
Storm Water Drainage
1.11
1.11
1.11
1.11
Parks and Playgrounds
1.33
1.33
1.33
1.33
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0.66
0.66
0.66
0.66
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.99
2.99
2.99
2.99
Water Supply System
1.11
1.11
1.11
1.11
Sewerage treatment & garbage disposal
1.11
1.11
1.11
1.11
Electricity Supply System
2.77
2.77
2.77
2.77
Storm Water Drainage
1.11
1.11
1.11
1.11
Parks and Playgrounds
1.33
1.33
1.33
1.33
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0.66
0.66
0.66
0.66
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.99
2.99
2.99
2.99
Water Supply System
1.11
1.11
1.11
1.11
Sewerage treatment & garbage disposal
1.11
1.11
1.11
1.11
Electricity Supply System
2.77
2.77
2.77
2.77
Storm Water Drainage
1.11
1.11
1.11
1.11
Parks and Playgrounds
1.33
1.33
1.33
1.33
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0.66
0.66
0.66
0.66
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.99
2.99
2.99
2.99
Water Supply System
1.11
1.11
1.11
1.11
Sewerage treatment & garbage disposal
1.11
1.11
1.11
1.11
Electricity Supply System
2.77
2.77
2.77
2.77
Storm Water Drainage
1.11
1.11
1.11
1.11
Parks and Playgrounds
1.33
1.33
1.33
1.33
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0.66
0.66
0.66
0.66
Particulars
Year-2027
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
2.99
2.99
2.99
Water Supply System
1.11
1.11
1.11
Sewerage treatment & garbage disposal
1.11
1.11
1.11
Electricity Supply System
2.77
2.77
2.77
Storm Water Drainage
1.11
1.11
1.11
Parks and Playgrounds
1.33
1.33
1.33
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0.66
0.66
0.66
Yes
No
UNION BANK OF INDIA, D-2, PANCHWATI COMMERCIAL CENTRE,AZADPUR, NEW DELHI
35810101421254
UBIN0535818
110026021
0535818
Raman Goyal
R/o Shivaji Apartments A-7-2 Sector-14 Rohini Rajapur Kalan Sector 7 North West Delhi-110085
Uploaded in Upload Section.
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO. 119 OF 2022
ALREADY BEEN OBTAINED
16-08-2022
Yes
Yes
The RERA Provisions have been added into the Draft Agreements.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: