THE ROYAL RESIDENCY, SECTOR-32, ADJOINING HOTEL NOOR MAHAL, KARNAL-132001
01842989999
8199816346 (Number Shared by Promoter in Public)
support@theroyalresidency.in
http://www.theroyalresidency.in
XXXX393J
U70100HR2010PTC041365
THE ROYAL RESIDENCY
ADJOINING HOTEL NOOR MAHAL, SECTOR-32, KARNAL-132001
KARNAL
KARNAL
01842989999
7206549999 (Number Shared by Promoter in Public)
support@theroyalresidency.in
KRISHAN TANEJA
8199816346 (Number Shared by Promoter in Public)
krishantaneja@yahoo.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
43737
26-07-2017
226000
AXIS BANK LTD
HRERA Panchkula
6.356 (Acre)
44581.111 SQM
400
6.356 (Acre)
Licence No. 46 of 2011 granted by Town and Country Planning Haryana chandigarh
Yes
7453.05 Lakhs
5.78 Lakhs
3034.07 Lakhs
4413.20 Lakhs
949.43 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
6839.91
3
CONSTRUCTION OF ROADS
6364
4
PAVEMENTS
950
5
PARKS AND PLAYGROUNDS
8074
6
GREEN BELTS
0
7
VEHICLE PARKINGS
2112
8
ELECTRICITY SUB-STATION
383
9
CLUB HOUSE
185
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
272
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
295
12
ANY OTHER
4275
Total
29749.91
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
Yes
WATER SUPPLY
HUDA
Yes
ELECTRICITY
UHBVN
Yes
SEWAGE DISPOSAL
HUDA
Yes
STORM WATER DRAINAGE
HUDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
46.85
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
8.60
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
1.70
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
143.78
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
15.61
AS PER PROJECT REPORT
6
STREET LIGHTING
9.78
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
246.5
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
17.11
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
15.5
AS PER PROJECT REPORT
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
14-05-2012 (date)
14-05-2012 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Total size of the plots/carpet area of the apartments
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type
0
0
0
0
0
0
Total
0
0
0
0
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
T2-4BHK+U
32
0
T2-6BHK P.H
4
0
T3-3BHK+U
32
0
T3-4BHK P.H
4
0
T4-3BHK
40
0
12-09-2012
11-03-2015
11-07-2017
12-09-2012
100
11-07-2017
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
12-09-2012
100
11-07-2017
0
96
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
25.4
19.68
18.33
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
7.15
9.6
3.27
Shops
0
0
0
Plots
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
2.31
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
56.75
Water Supply System
12.10
Sewerage treatment & garbage disposal
23.84
Electricity Supply System
185.76
Storm Water Drainage
4.84
Parks and Playgrounds
13.15
Clubhouse/community centres
22
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
Water Supply System
0
0
0
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
0
0
0
Storm Water Drainage
0
0
0
Parks and Playgrounds
0
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
112
ii. No. of Flats/ Apartments booked
112
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
10361.03 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
8195.85 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
2165.18 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
2165.18 Lakhs
vii. Amount invested in the project upto the date of application
8151.62 Lakhs
Land cost (If any)
5.68 Lakhs
Apartments
3313.76 Lakhs
Infrastructure
2672.75 Lakhs
EDC/ Taxes Etc.
1586.69 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
950 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
350 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT