HRERA GurugramTemp Project Id : RERA-GRG-PROJ-1160-2022
Submission Date : 22-09-2022 01:09:51 PM
Applicant Type : Company
Project Type: NEW




BETTERCHOICE REALTORS PVT LTD
G 79, GROUND FLOOR, VIJAY CHOWK LAXMI NAGAR, DELHI-110092
01248130099
8130099253 (Number Shared by Promoter in Public)
dhiraj.goyal@bettercoicerealty.in
XXXX476M
U45201DL2006PTC144377
 
 


 
 


 
 


 
 







VANYA CITY
SECTOR 99A
KADIPUR ST
GURUGRAM
8130099253 (Number Shared by Promoter in Public)
dhiraj.goyal@betterchoicerealty.in
PRAVAL JAIN
9873583533 (Number Shared by Promoter in Public)
dhiraj.goyal@betterchoicerealty.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11498221-09-2022888468IDBI BANK, SIKANDARPUR BRANCH GURUGRAMHRERA Gurugram
21334707-10-20225714IDBI BANK, SIKANDARPUR BRANCH GURUGRAMHRERA Gurugram







10.83125 (Acre)
0
0
10.83125 (Acre)
LICENSE NO 141 OF 2022 DATED 16-09-2022
No
Address     G-79, GROUND FLOOR, VIJAY CHOWK, LAXMI NAGAR, DELHI-110092
Address     NEW DELHI
Address     NEW DELHI
Address     NEW DELHI
Address     NEW DELHI
Annexure-B- COLLABORATOR
YES
Yes
YES
No
Yes
Yes







22929.94 Lakhs
12335.26 Lakhs
0 Lakhs
2914.68 Lakhs
7680.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD6.3520
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS2.1158
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.840
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.0420
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.112
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1.084
12ANY OTHER0
13MILKBOOTH0.0066
14COMMERCIAL0.2920
15UD0.14085
Total10.98525




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDANo
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNNo
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS307.35AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM187AS PER PROJECT REPORT
3STORM WATER DRAINAGE68.30AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM90AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL109.45AS PER PROJECT REPORT
6STREET LIGHTING24.92AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS6.5AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


16-09-2022 (date)
NA (date)
03-10-2022
31-10-2025
Plot Area(In Square Meter)Number of plots in the project
95.09511
126.79144
130.47531
146.9679
140.3637
146.80081
105.008


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.44
Water Supply System7.78
Sewerage treatment & garbage disposal2.58
Electricity Supply System0
Storm Water Drainage3.25
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Construction of Boundary Wall and Gate11.43

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements27.6627.6627.6632.27
Water Supply System17.5420.4821.3222.07
Sewerage treatment & garbage disposal8.068.9011.4431.30
Electricity Supply System2.7013.0518.2626.06
Storm Water Drainage5.456.016.839.29
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Construction of Boundary Wall and Gate16.5127.9433.0224.13

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements32.2746.1046.1018.44
Water Supply System25.2522.9121.9917.39
Sewerage treatment & garbage disposal15.8912.4811.986.82
Electricity Supply System20.389.5600
Storm Water Drainage11.959.227.385.93
Parks and Playgrounds01.392.552.01
Clubhouse/community centres0000
Shopping area0000
Other0000
Construction of Boundary Wall and Gate11.432.54
Street Lighting8.72

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.4412.29
Water Supply System8.421.87
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage2.990
Parks and Playgrounds0.550
Clubhouse/community centres00
Shopping area00
Other00
Street Lighting16.20












Yes
No
HDFC BANK, E143, SAKET NEW DELHI,DELHI110017
50200072722012
HDFC0000043
110240007
0043
NAYAN NAVEEN RAHEJA
YES











Yes
No
No
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO 141 OF 2022 DATED 16-09-2022ALREADY BEEN OBTAINED16-09-2022
II. LAYOUT PLANALREADY BEEN OBTAINED16-09-2022
III. ZONING PLANALREADY BEEN OBTAINED03-11-2022








Yes


Yes


YES













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND17-09-2022 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN17-09-2022 View Document
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN17-09-2022 View Document
4A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS17-09-2022 View Document
5CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT22-09-2022 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.22-09-2022 View Document
7CASH FLOW STATEMENT OF THE PROPOSED PROJECT22-09-2022 View Document
8NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT10-10-2022 View Document
9DOMESTIC WATER SUPPLY LAYOUT10-10-2022 ------
10IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN10-10-2022 View Document
11LOI DDJAY 99A10-10-2022 ------
12PERT CHART AND CASH FLOW FOR SERVICES- VANYA CITY10-10-2022 ------
13FLUSHING WATER LAYOUT10-10-2022 ------
14SEWERAGE LAYOUT10-10-2022 ------
15STORM WATER LAYOUT10-10-2022 ------
16DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD10-10-2022 View Document
17ROAD LAYOUT10-10-2022 ------
18SERVICE ESTIMATE (10.83125 ACRES)10-10-2022 ------
19UNDERTAKINGS 10PERCENT LAND10-10-2022 ------
20DEMARCATION PLAN16-11-2022 View Document
21ZONING PLAN16-11-2022 View Document