HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-1116-2022
Submission Date : 11-12-2022 12:48:30 PM
Applicant Type : Company
Project Type: ONGOING




VARDHMAN BUILDTECH PRIVATE LIMITED
SECTOR-3, DHARUHERA, REWARI
9871395694 (Number Shared by Promoter in Public)
akaseema@gmail.com
XXXX445M
U45400DL2007PTC169313
 
 


 
 


 
 







VARDHMAN SPRINGDALES
SECTOR-3, DHARUHERA
REWARI
REWARI
7982578090 (Number Shared by Promoter in Public)
SPRINGDALES.VARDHMAN@GMAIL.COM
VIJESH GOEL
7982578090 (Number Shared by Promoter in Public)
SPRINGDALES.VARDHMAN@GMAIL.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
171910409-12-2022287000UNION BANK OF INDIAHRERA Panchkula







8.1 (Acre)
1.75
1.75
8.1 (Acre)
142 OF 2008
No
Address     WZ 22, SECOND FLOOR, VASHISTA PARK, PANKHA ROAD, NEW DELHI 110046
Annexure-B- THE APPLICANT IS APPLYING FOR REGISTRATION IN THE CAPACITY OF DEVELOPER IN RESPECT OF JOINT DEVELOPMENT AGREEMENT EXECUTED BETWEEN THE OWNER AND THE APPLICANT
JOINT DEVELOPMENT AGREEMENT WAS MADE AFTER THE GRANT OF THE LICENSE
No
SUMMARY OF COLLABORATION AGREEMENTS IS ATTACHED AS ANNEXURE
No
Yes
Yes







16000 Lakhs
1500 Lakhs
14500 Lakhs
0 Lakhs
0 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5539.31
3CONSTRUCTION OF ROADS6019.305
4PAVEMENTS6718.513
5PARKS AND PLAYGROUNDS0
6GREEN BELTS6565.229
7VEHICLE PARKINGS7223.1
8ELECTRICITY SUB-STATION0
9CLUB HOUSE180
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
13NURSERY232.34
14SWIMMING138.5
15SHOPPING163.188
Total32779.485




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSTO BE DONENo
WATER SUPPLYTO BE DONENo
ELECTRICITYTO BE DONENo
SEWAGE DISPOSALTO BE DONENo
STORM WATER DRAINAGETO BE DONENo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS0YET TO BE PREPARED
2WATER SUPPLY SYSTEM0YET TO BE PREPARED
3STORM WATER DRAINAGE0YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL0YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


29-04-2011 (date)
29-04-2011 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type APPARTMENTS1175204165390
2APARTMENT/SHOPS/OTHER BUILDINGS Type APPARTMENTS1240534850
3APARTMENT/SHOPS/OTHER BUILDINGS Type APPARTMENTS1350166141250
4APARTMENT/SHOPS/OTHER BUILDINGS Type APPARTMENTS16406629370
5APARTMENT/SHOPS/OTHER BUILDINGS Type APPARTMENTS18506621450
6APARTMENT/SHOPS/OTHER BUILDINGS Type EWS APPARTMENTS200989800






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
APPARTMENTS502APPROX. 90% DEVELOPMENT IS COMPLETED FOR TOWER A, B, C, D, E, F AND EWS TOWER. DEVELOPMENT FOR TOWER H IS COMPLETED UPTO APPROX. 70% AND FOR TOWER G, I AND J, DEVELOPMENT IS COMPLETED APPROX 40%.,


01-04-2012
31-12-2015
31-12-2026
31-01-2023
0
31-12-2026


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
31-12-2023
0
31-12-2024
NOT APPLICABLE
NOT APPLICABLE


541
116
0
290
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments9400
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Particulars Remarks, if any
i. No. of Flats/Apartments constructed0No appartment is fully developed
ii. No. of Flats/ Apartments booked502Total appartments booked are inclusive of 98 Units of EWS
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter11630.5 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter10031.43 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter1599.09 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter1599.09 Lakhs
vii. Amount invested in the project upto the date of application9400 Lakhs
Land cost (If any)0 Lakhs
Apartments9400 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.0 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession5100 Lakhs
(a) In respect of existing allottees3100 Lakhs
(b) In respect of rest of the project2000 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS00
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
No
UNION BANK OF INDIA, JANAKPURI, NEW DELHI
532801010320212
UBIN0905224
110026070
JANAKPURI
MANISH GUPTA











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. AIRPORT APPROVALALREADY BEEN OBTAINED28-11-2011
II. ZONAL PLAN APPROVALALREADY BEEN OBTAINED08-04-2011
III. CERTIFICATE OF LAND NOT FALLING IN ARAVALI RANGEALREADY BEEN OBTAINED21-09-2012
IV. BUILDING APPROVALALREADY BEEN OBTAINED28-10-2011
V. BUILDING AND OTHER CONSTRUCTION WORKSALREADY BEEN OBTAINED05-11-2012
VI. ELECTRICITY SANCTION LOADALREADY BEEN OBTAINED28-08-2012
VII. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED20-01-2012
VIII. FIRE NOCALREADY BEEN OBTAINED13-12-2011
IX. POLLUTION NOCALREADY BEEN OBTAINED14-12-2012
X. TEMORARY SITE APPROVALALREADY BEEN OBTAINED12-05-2011








Yes


No


As per Agreement













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT10-12-2022 View Document
2SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN10-12-2022 View Document
3DRAFT BBA10-12-2022 ------
4IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN11-12-2022 View Document
5DEMARCATION PLAN10-12-2022 View Document
6COPY OF LICENSE ALONG WITH SCHEDULE OF LAND10-12-2022 View Document
7IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN10-12-2022 View Document
8DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD10-12-2022 View Document
9ZONING PLAN10-12-2022 View Document
10A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS10-12-2022 View Document
11BALANCE SHEET FY 2020-2110-12-2022 ------
12BALANCE SHEET FY 2019-2010-12-2022 ------
13BALANCE SHEET FY 2018-1910-12-2022 ------
14CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT10-12-2022 View Document
15DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.10-12-2022 View Document
16CASH FLOW STATEMENT OF THE PROPOSED PROJECT11-12-2022 View Document