KRISHNA RESIDENCY
VILLAGE DABUA, SECTOR-49
BADKHAL
FARIDABAD
9312930435 (Number Shared by Promoter in Public)
trishulresidency@yahoo.com
HARISH CHANDRA
9312930435 (Number Shared by Promoter in Public)
trishulresidency@yahoo.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
393913
19-08-2022
280000
PNB DELHI
HRERA Panchkula
6.0125 (Acre)
0
0
6.0125 (Acre)
LICENSE NO. 116 OF 2022, DATED 12.08.2022
Yes
4070.99 Lakhs
982.41 Lakhs
0 Lakhs
1515.15 Lakhs
1573.43 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.3077
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1.3467
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.4545
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.0549
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.6015
12
ANY OTHER
0
13
MILK AND VEG BOOTH
0.0068
14
CONSTRUCTION OF COMMERCIAL SHOPS
0.2404
Total
6.0125
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
265.42
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
165.47
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
139.18
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
340.85
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
185.12
AS PER PROJECT REPORT
6
STREET LIGHTING
65.45
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
65.86
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
75.46
AS PER PROJECT REPORT
15
BOUNDARY WALL GATE AND GUARD ROOM
212.34
AS PER PROJECT REPORT
12-08-2022 (date)
NA (date)
01-09-2022
11-08-2027
Plot Area(In Square Meter)
Number of plots in the project
116.72
19
115.30
8
120.98
16
148.38
7
149.87
34
113.47
9
144.31
8
973.05
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
24.13
24.13
Water Supply System
15.04
15.04
Sewerage treatment & garbage disposal
16.83
16.83
Electricity Supply System
30.99
30.99
Storm Water Drainage
12.65
12.65
Parks and Playgrounds
5.99
5.99
Clubhouse/community centres
0
0
Shopping area
0
0
Other
6.86
6.86
STREET LIGHTING
5.95
5.95
Boundary Wall Gate and Guard Room
19.30
19.30
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
24.13
24.13
24.13
24.13
Water Supply System
15.04
15.04
15.04
15.04
Sewerage treatment & garbage disposal
16.83
16.83
16.83
16.83
Electricity Supply System
30.99
30.99
30.99
30.99
Storm Water Drainage
12.65
12.65
12.65
12.65
Parks and Playgrounds
5.99
5.99
5.99
5.99
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
6.86
6.86
6.86
6.86
Boundary Wall Gate and Guard Room
19.30
19.30
19.30
19.30
STREET LIGHTING
5.95
5.95
5.95
5.95
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
24.13
24.13
24.13
24.13
Water Supply System
15.04
15.04
15.04
15.04
Sewerage treatment & garbage disposal
16.83
16.83
16.83
16.83
Electricity Supply System
30.99
30.99
30.99
30.99
Storm Water Drainage
12.65
12.65
12.65
12.65
Parks and Playgrounds
5.99
5.99
5.99
5.99
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
6.86
6.86
6.86
6.86
Boundary Wall Gate and Guard Room
19.30
19.30
19.30
19.30
STREET LIGHTING
5.95
5.95
5.95
5.95
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
24.13
Water Supply System
15.04
Sewerage treatment & garbage disposal
16.83
Electricity Supply System
30.99
Storm Water Drainage
12.65
Parks and Playgrounds
5.99
Clubhouse/community centres
0
Shopping area
0
Other
6.86
Boundary Wall Gate and Guard Room
19.30
STREET LIGHTING
5.95
Yes
No
ICICI BANK C-82, MALVIYA NAGAR, NEW DELHI- 110017
113605002201
ICIC0001136
110229120
001136
HARISH CHANDRA R/O B-40, SHIV PARK, KHANPUR, NEW DELHI-110062
YES
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Yes
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE
ALREADY BEEN OBTAINED
12-08-2022
II. LAYOUT PLAN
ALREADY BEEN OBTAINED
12-08-2022
Yes
Yes
FULL AGREEMENT
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: