8-D, HANSALYA, 15, BARAKHAMBHA ROAD, NEW DELHI - 110001
9891500335 (Number Shared by Promoter in Public)
udit@onecity.in
https://onecity.in/
XXXX529B
U70101DL2005PTC137209
ONE CITY
SECTOR-42, BAHADURGARH
BAHADURGARH
JHAJJAR
9540968345 (Number Shared by Promoter in Public)
sales@onecity.in
UDIT JAIN
9540968345 (Number Shared by Promoter in Public)
sales@onecity.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
334326
04-08-2022
115000
BANK OF BARODA
HRERA Panchkula
5.18125 (Acre)
NIL
0
5.18125 (Acre)
118 of 2022 (10-08-2022)
Yes
1477.63583 Lakhs
531 Lakhs
0 Lakhs
458.52583 Lakhs
488.11 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
2.6788
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1.060497
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.39118
6
GREEN BELTS
0.332
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.518163
12
ANY OTHER
0
13
COMMERCIAL
0.20061
Total
5.18125
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
NA
No
WATER SUPPLY
NA
No
ELECTRICITY
NA
No
SEWAGE DISPOSAL
NA
No
STORM WATER DRAINAGE
NA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
78.00839
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
192.77394
YET TO BE PREPARED
3
STORM WATER DRAINAGE
28.08595
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
81.26721
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
44.49380
YET TO BE PREPARED
6
STREET LIGHTING
6.46074
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
7.11901
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
20.31680
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
10-08-2022 (date)
NA (date)
17-08-2022
09-08-2027
Plot Area(In Square Meter)
Number of plots in the project
117.64
18
111.21
14
149.98
5
115.60
32
106.48
1
104.56
2
130.68
7
61.02
1
76.92
1
100.75
1
115.87
5
64.35
1
120.879
5
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.75105
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
9.75105
9.75105
9.75105
Water Supply System
0
24.09674
24.09674
24.09674
Sewerage treatment & garbage disposal
8.89876
4.44938
4.44938
4.44938
Electricity Supply System
0
8.12672
8.12672
8.12672
Storm Water Drainage
7.02149
7.02149
0
7.02149
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.75105
9.75105
9.75105
0
Water Supply System
24.09674
24.09674
24.09674
12.04837
Sewerage treatment & garbage disposal
4.44938
8.89876
4.44938
4.44938
Electricity Supply System
8.12672
0
0
8.12672
Storm Water Drainage
0
7.02149
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.75105
0
0
0
Water Supply System
12.04837
12.4837
12.04837
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
8.12672
8.12672
8.12672
16.25344
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
2.37300
2.37300
2.37300
Clubhouse/community centres
0
0
0
0
Shopping area
0
6.77227
6.77227
6.77227
Other
0
0
0
0
Street Lighting
3.23037
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Street Lighting
3.23037
Yes
No
HDFC BANK, 6 BLOCK NO. 90, 104 BAIRD ROAD, GOLE MARKET, NEW DELHI, DELHI-110001
50200072896920
HDFC0000584
110240085
000584
Udit Jain, C-479, Defence Colony, New Delhi-110024
No Default
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE
ALREADY BEEN OBTAINED
10-08-2022
Yes
Yes
1. 10% of the sale price to be paid as the booking amount by the allottee.
2. Name and particulars of the allottee along with contact details.
3. Area, location and price of the plot. Also, states the external electrification, sewer connection and water connection charges and IFMS to be paid by the allottee.
4. Ownership details of project land.
5. Possession of the plot unit will be given on complete payment by the allottee when sale deed is registered in the name of the allottee.
6. Payment Plan clearly mentions the timeline of payment to be made by the allottee.
7. The agreement will be registered with Sub-Registrar office, Tehsil Bahadurgarh and will be binding on both parties.
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT