9996000262 (Number Shared by Promoter in Public)
singhy_2480@yahoo.com
00059
AAHFU0877C
ULTIMA GLOBAL SQUARE
VILLAGE RATHDHANA, SECTOR- 35
SONIPAT
SONIPAT
9996000262 (Number Shared by Promoter in Public)
singhy_2480@yahoo.com
SURENDER SINGH
9996000262 (Number Shared by Promoter in Public)
singhy_2480@yahoo.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
942741
20-07-2022
567000
UNION BANK
HRERA Panchkula
3.373 (Acre)
138.31
138.31
3.373 (Acre)
The License No. 71 of 2009, dated 26.11.2009 and License No. 24 of 2014, dated 11.06.2014 had granted in favour M/s. Jindal Realty Limited and M/s. Jindal Realty Limited had sold the land measuring 3.373 acres, vide conveyance deed no. 13977 dated 31.03.2022 in favour of ULTIMA REALTY. Further ULTIMA REALTY is promoter of the Said Project.
Yes
2333 Lakhs
1042.5 Lakhs
0 Lakhs
150 Lakhs
1140.5 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
0.385
4
PAVEMENTS
0.138
5
PARKS AND PLAYGROUNDS
0.523
6
GREEN BELTS
0
7
VEHICLE PARKINGS
1.047
8
ELECTRICITY SUB-STATION
0.050
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.050
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
COMMERCIAL
1.180
Total
3.373
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
HUDA
No
ELECTRICITY
UHBVNL
No
SEWAGE DISPOSAL
HUDA
No
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
50.66
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
10.85
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
8.64
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
20.00
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
AS PER PROJECT REPORT
6
STREET LIGHTING
15.15
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
7.31
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
BOUNDARY WALL GATE AND GUARD ROOM
37.43
AS PER PROJECT REPORT
NA (date)
07-06-2022 (date)
01-08-2022
05-04-2027
Plot Area(In Square Meter)
Number of plots in the project
71.76
72
400
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
4.61
4.61
Water Supply System
0.99
0.99
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
1.82
1.82
Storm Water Drainage
0.79
0.79
Parks and Playgrounds
0.66
0.66
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
STREET LIGHTING
1.38
1.38
Boundary Wall Gate and Guard Room
3.40
3.40
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
4.61
4.61
4.61
4.61
Water Supply System
0.99
0.99
0.99
0.99
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
1.82
1.82
1.82
1.82
Storm Water Drainage
0.79
0.79
0.79
0.79
Parks and Playgrounds
0.66
0.66
0.66
0.66
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Boundary Wall Gate and Guard Room
3.40
3.40
3.40
3.40
STREET LIGHTING
1.38
1.38
1.38
1.38
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
4.61
4.61
4.61
4.61
Water Supply System
0.99
0.99
0.99
0.99
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
1.82
1.82
1.82
1.82
Storm Water Drainage
0.79
0.79
0.79
0.79
Parks and Playgrounds
0.66
0.66
0.66
0.66
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Boundary Wall Gate and Guard Room
3.40
3.40
3.40
3.40
STREET LIGHTING
1.38
1.38
1.38
1.38
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
4.61
Water Supply System
0.99
Sewerage treatment & garbage disposal
0
Electricity Supply System
1.82
Storm Water Drainage
0.79
Parks and Playgrounds
0.66
Clubhouse/community centres
0
Shopping area
0
Other
0
Boundary Wall Gate and Guard Room
3.40
STREET LIGHTING
1.38
No
No
ICICI BANK, RAI SONIPAT, HARYANA
140505500453
ICIC0001405
110229163
001405
SURENDER SINGH
r/O HO. NO. 677/30 MEHLANA ROAD GALI NO. 2 MALVIYA CITY SONIPAT HARYANA 131001
YES
No
No
Yes
No
Yes
No
No
No
Yes
Yes
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. THE SAID COMMERCIAL IS PART OF THE LICENSE NO. 71 OF 2009, DATED 26.11.2009 AND LICENSE NO. 24 OF 2014, DATED 11.06.2014.
ALREADY BEEN OBTAINED
11-06-2014
II. STANDARD DESIGNS OF COMMERCIAL SITE
ALREADY BEEN OBTAINED
07-06-2022
Yes
Yes
FULL AGREEMENT
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: