HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-995-2021
Submission Date : 19-01-2022 06:32:13 PM
Applicant Type : Company
Project Type: NEW




ELITE HOMES PRIVATE LIMITED
SHOP NO. 30, M2K MALL, 16, MANGALAM PLACE, DIST. CENTRE, SECTOR-3, ROHINI WEST DELHI- 110085
01244525000
9818199908 (Number Shared by Promoter in Public)
M2KHARMONY2@M2KINDIA.COM
http://www.m2kindia.com
XXXX378F
U45201DL2005PTC133721
 
 


 
 


 
 


 
 







M2K HARMONY-2
SECTOR-5, 7A & 21, DHARUHERA
DHARUHERA ST
REWARI
9818199908
9818199908 (Number Shared by Promoter in Public)
M2KHARMONY2@M2KINDIA.COM
BHAGIRATH NANDU
9818199908
9818199908 (Number Shared by Promoter in Public)
M2KHARMONY2@M2KINDIA.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1149317-12-2021122000AXIS BANK LIMITEDHRERA Panchkula







5.30625 (Acre)
N.A.
0
5.30625 (Acre)
22 of 2020
Yes







1126.04 Lakhs
169.99 Lakhs
0.00 Lakhs
407.95 Lakhs
548.10 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD12333.018
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS4444.822
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1611.401
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY100.444
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES2040.322
12ANY OTHER0
13SCOPLOTSINCOMMERCIALBLOCK285.425
14OPENAREAINCLUDINGPARKINGPUBLICAMENITIESSERVICESINCOMMERCIALBLOCK530.585
15UGT100.081
16MILK27.50
Total21473.598




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP/ DTCPNo
WATER SUPPLYHSVP/ DTCPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVP/ DTCPNo
STORM WATER DRAINAGEHSVP/ DTCPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS52.76SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM104.15SUBMITTED TO HUDA
3STORM WATER DRAINAGE59.85SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM73.15AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL80.77SUBMITTED TO HUDA
6STREET LIGHTING20.37SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING0.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS1.72SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0.00AS PER PROJECT REPORT
10SHOPPING AREA0.00AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0.00AS PER PROJECT REPORT
12SCHOOL0.00AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0.00AS PER PROJECT REPORT
14ANY OTHER0.00AS PER PROJECT REPORT
15MISC CIVIL STRUCTURE15.18AS PER PROJECT REPORT


03-09-2020 (date)
NA (date)
01-12-2021
30-08-2025
Plot Area(In Square Meter)Number of plots in the project
147.7702
141.3911
117.6191
149.9201
134.6104
139.44011
149.1071
132.9511
137.5502
136.71032
122.6041
94.2321
93.63531
92.1001
92.8681
146.5848
147.2321
27.5001
85.5051
49.9804


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots550.22

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0006




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System15.46
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0.90
Clubhouse/community centres0
Shopping area0
Other0
Miscellaneous Civil Structure1.09
Street Lighting0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0003.30
Water Supply System0000
Sewerage treatment & garbage disposal0005.05
Electricity Supply System0000
Storm Water Drainage0003.74
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Miscellaneous Civil Structure0000
Street Lighting0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements9.899.8913.199.89
Water Supply System5.5427.7227.7222.17
Sewerage treatment & garbage disposal15.1420.1925.2415.15
Electricity Supply System04.5722.8622.86
Storm Water Drainage11.2214.9618.7011.23
Parks and Playgrounds0.050.150.150.31
Clubhouse/community centres0000
Shopping area0000
Other0000
Miscellaneous Civil Structure02.855.693.80
Street Lighting00011.46

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.60
Water Supply System5.54
Sewerage treatment & garbage disposal0
Electricity Supply System22.86
Storm Water Drainage0
Parks and Playgrounds0.16
Clubhouse/community centres0
Shopping area0
Other0
Street Lighting8.91
Miscellaneous Civil Structure1.75












Yes
No
1. TF-23,SIDDHI VINAYAK, MODULE-16,ABHAY KHAND-3, INDIRAPURAM, SHIPRA SUNCITY, GHAZIABAD, UP-201014, 2. 50, GALI NO 12, GANDHI NAGAR, GURUGRAM, HARYANA-122001
0169102000026929
IBKL0000169
110259016
000169
1. MR. MUKESH SHARMA 2. MR. VIKASH AGARWAL
YES











Yes
Yes
No
No
No
No
No
No
No
No


Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LAYOUT PLANALREADY BEEN OBTAINED03-09-2020
II. NOC FROM FOREST DEPARTMENTALREADY BEEN OBTAINED11-03-2015
III. LICENSE UNDER DDJAY-2016ALREADY BEEN OBTAINED31-08-2020
IV. DEMARCATION PLANALREADY BEEN OBTAINED31-12-2021
V. NOC FROM HARYANA POLLUTION CONTROL BOARDALREADY BEEN OBTAINED29-04-2021
VI. APPROVAL OF ELECTRIFICATION PLAN FROM DHBVNAPPLIED FOR BUT YET TO RECEIVE11-08-2021








Yes


Yes









M2K GALLERIA, SEC 5 AND 7A, DHARUHERA, REWARI, HARYANA
1.399
0
38
0
26
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
876.82876.82649.75
Cost of the apartments000
Cost of the infrastructure156.78156.78155.88
Others costs720.04720.04493.87


249.56 Lakhs
578.85 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2022
31-03-2022




M2K HARMONY, SEC 5, DHARUHERA, REWARI, HARYANA
5.16875
0
108
0
45
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
723.45723.45315.86
Cost of the apartments000
Cost of the infrastructure310.16310.1669.21
Others costs413.29413.29246.65


231.49 Lakhs
1386.38 Lakhs
0 Lakhs
0 Lakhs
No
31-03-2023
31-03-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEN.A.
2WALL FINISHING DETAILSN.A.
3KITCHEN DETAILSN.A.
4BATHROOM FITTINGSN.A.
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESN.A.
7GLASS WORKN.A.
8ELECTRIC FITTINGSN.A.
9CONDUCTING AND WIRING DETAILSN.A.
10CUPBOARD DETAILSN.A.
11WATER STORAGEN.A.
12LIFT DETAILSN.A.
13EXTERNAL GLAZINGSN.A.
13.1WINDOWS/GLAZINGSN.A.
14DOORSN.A.
14.1MAIN DOORSN.A.
14.2INTERNAL DOORSN.A.
15AIR CONDITIONINGN.A.
16ELECTRICAL FITTINGSN.A.
17CNG PIPE LINEN.A.
18PROVISION OF WIFI AND BROADBAND FACILITYN.A.
19EXTERNAL FINISHING/COLOUR SCHEMEN.A.
20INTERNAL FINISHINGN.A.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN.A.
1 . 2 WALLSN.A.
1 . 3 CEILINGN.A.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN.A.
2 . 2 WALLSN.A.
2 . 3 CEILINGN.A.
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORN.A.
3 . 2 WALLSN.A.
3 . 3 CEILINGN.A.
3 . 4 COUNTERSN.A.
3 . 5 SANITARY WARE/CP FITTINGSN.A.
3 . 6 FITTING/FIXTURESN.A.
4 . BED ROOMS
4 . 1 FLOORN.A.
4 . 2 WALLSN.A.
4 . 3 CEILINGN.A.
4 . 4 WARDROBESN.A.
5 . TOILET
5 . 1 FLOORN.A.
5 . 2 WALLSN.A.
5 . 3 CEILINGN.A.
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSN.A.
5 . 6 FIXTURESN.A.
6 . KITCHEN
6 . 1 FLOORN.A.
6 . 2 WALLSN.A.
6 . 3 CEILINGN.A.
6 . 4 COUNTERSN.A.
6 . 5 FIXTURESN.A.
6 . 6 KITCHEN APPLIANCESN.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A.
7 . 2 WALLS & CEILINGN.A.
7 . 3 TOILETN.A.
7 . 4 BALCONYN.A.
8 . SIT-OUTS
8 . 1 FLOORN.A.
8 . 2 WALLS & CEILINGN.A.
8 . 3 RAILINGSN.A.
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT16-12-2021 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND16-12-2021 View Document
3IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN17-12-2021 View Document
4DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD17-12-2021 View Document
5IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN22-12-2021 View Document
6ELECTRICTY SUPPLY PLAN22-12-2021 ------
7SEWERAGE AND GARBAGE DISPOSAL PLAN22-12-2021 ------
8ROAD AND PAVEMENT PLAN22-12-2021 ------
9STORM WATER DRAINAGE PLAN22-12-2021 ------
10STREET LIGHTING PLAN22-12-2021 ------
11FLUSHING LAYOUT PLAN22-12-2021 ------
1210% LAND TO BE TRANSFERRED TO THE GOVT.FOR COMMUNITY FACILITY22-12-2021 ------
13DEMARCATION PLAN13-01-2022 View Document
14ZONING PLAN14-01-2022 View Document
15SCO PLAN18-01-2022 ------
16CASH FLOW STATEMENT OF THE PROPOSED PROJECT18-01-2022 View Document
17DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.19-01-2022 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Corrigendum of registration of project . 28-10-2022 View Document
2 Corrigendum 04-09-2023 View Document