HRERA GurugramTemp Project Id : RERA-GRG-PROJ-979-2021
Submission Date : 16-12-2021 01:54:58 PM
Applicant Type : Firm
Project Type: NEW


MRG WORLD LLP
UNIT NO. 131, VATIKA TOWER, SECTOR-54, GURUGRAM-122003
01246036000
9625935263 (Number Shared by Promoter in Public)
compliances@mrgworld.com
AAT6494
ABOFM6542L













ULTIMUS 2.0
SECTOR 90 GURUGRAM
MANESAR
GURUGRAM
01246036000
9899076262 (Number Shared by Promoter in Public)
compliances@mrgworld.com
NEERAJ MISHRA
01246036000
9899076262 (Number Shared by Promoter in Public)
neeraj.mishra@mrgworld.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1006-12-202115000AU SMALL FINANCE BANKHRERA Gurugram
2007-12-20211239117KOTAK MAHINDRA BANKHRERA Gurugram
3007-12-2021506857KOTAK MAHINDRA BANKHRERA Gurugram







5.2625 (Acre)
2.40
2.40
5.2625 (Acre)
38 of 2021
Yes







21247.66 Lakhs
3776.53 Lakhs
10269.47 Lakhs
1417.52 Lakhs
5784.14 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 3390.158
3CONSTRUCTION OF ROADS 4435.648
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 3203.36
6GREEN BELTS 0
7VEHICLE PARKINGS 6883.030
8ELECTRICITY SUB-STATION 285
9CLUB HOUSE 227.2476
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 500
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13COMMERCIAL 1266.279
Total20190.7226




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTEDNo
WATER SUPPLYYes
ELECTRICITYYes
SEWAGE DISPOSALYes
STORM WATER DRAINAGEYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS417.12YET TO BE PREPARED
2WATER SUPPLY SYSTEM307.52YET TO BE PREPARED
3STORM WATER DRAINAGE55.60YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM150YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL64.50YET TO BE PREPARED
6STREET LIGHTING20.19YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS58.12YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0.00YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0.00YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0.00YET TO BE PREPARED
14ANY OTHER244.07YET TO BE PREPARED


26-10-2021 (date)
26-10-2021 (date)
15-01-2022
14-07-2026
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings44610.4247696





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
Cost of Construction8.26
EDC62.82
Land Cost3776.52
Other Cost136.25

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Other Cost811.291091.941445.491358.96
External Development Charges62.82062.820
Internal Development Works5.915.915.9167.72
Cost of Construction436.10692.63983.37897.86

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
External Development Charges62.82062.820
Cost of Construction855.10812.35769.59769.59
Internal Development Works67.7282.55115.03129.87
Other Cost1280.061189.321241.861193.88

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Other Cost1256.701229.521268.79989.24
Cost of Construction769.59769.59769.59555.82
Internal Development Works129.87165.51141.96139.00
External Development Charges62.82062.820

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops0000
Plots0000
Other Cost949.44722.72676.44558.16
External Development Charges62.82062.8262.84
Internal Development Works139.00103.3670.8847.32
Cost of Construction453.20324.94248.32153.58




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System00023.06
Sewerage treatment & garbage disposal00011.48
Electricity Supply System0007.50
Storm Water Drainage0004.17
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light0001.51
Electrical Sub Station00011.25
Rain Water Harvesting0002.82
Underground Tank2.692.692.692.69
STP3.233.233.233.23

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements010.4320.8631.28
Water Supply System23.0623.0630.7530.75
Sewerage treatment & garbage disposal11.4811.4815.3115.31
Electricity Supply System7.507.5010.0010.00
Storm Water Drainage4.174.175.565.56
Parks and Playgrounds01.452.914.36
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting2.822.823.763.76
STP3.234.844.846.45
Street Light1.511.512.022.02
Underground Tank2.694.034.035.38
Electrical Sub Station11.2511.2515.0015.00

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements31.2862.5762.5762.57
Water Supply System30.753.7530.7523.06
Sewerage treatment & garbage disposal15.3115.3115.3111.48
Electricity Supply System10.0010.0010.007.50
Storm Water Drainage5.565.565.564.17
Parks and Playgrounds4.368.728.728.72
Clubhouse/community centres0000
Shopping area0000
Other0000
Rain Water Harvesting3.763.763.762.82
Street Light2.022.022.021.51
STP6.456.456.453.23
Underground Tank5.385.385.382.69
Electrical Sub Station15.0015.0015.0011.25

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements62.5731.2820.8620.86
Water Supply System23.0623.0615.387.69
Sewerage treatment & garbage disposal11.4811.487.663.83
Electricity Supply System7.507.505.002.50
Storm Water Drainage4.174.172.781.39
Parks and Playgrounds8.724.362.912.91
Clubhouse/community centres0000
Shopping area0000
Other0000
STP3.233.233.231.61
Street Light1.511.511.010.50
Electrical Sub Station11.2511.257.503.75
Rain Water Harvesting2.822.821.880.94
Underground Tank2.692.692.691.34












Yes
No
HDFC BANK LIMITED, GROUND FLOOR, JEHANGR BUILDING , M G ROAD, FORT MUMBAI, MAHARASHTRA-400001
57500000833706
HDFC0000060
400240015
60
Mr. Ashok Kumar











Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. BUILDING APPROVALSALREADY BEEN OBTAINED26-10-2021








Yes


No















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEBEDROOMS, KITCHEN- VITRIFIED TILES 2X2 (AMBANI, ORIENT BELL, VERMORA) TOILETS, BALCONY - CERAMIC TILES (AMBANI, ORIENT BELL, VERMORA) STAIRCASE - GRANITE, CHIMA PINK
2WALL FINISHING DETAILSEXTERNAL WALLS - TEXTURE PAINTS (ASIAN, BURGER, NEROLAC) INTERNAL WALLS - OBD (ASIAN, BURGER, NEROLAC)
3KITCHEN DETAILSWALLS - OBD (ASIAN, BURGER, NEROLAC) FLOORING - VITRIFIES TILES
4BATHROOM FITTINGSSTANDARD WASHBASIN - HINDWARE, WOLGA STANDARD TAPS - HINDWARE, WOLGA WC-WESTERN - PARKASH, WOLGA
5WOOD WORK ETCMAIN DOOR - FLUSHDOOR WITH LAMINATE (ALPRO, NAYUR, BUTTAN TUFF-DOOR) INTERNAL DOORS - FLUSHDOOR (ALPRO, NAYUR, BUTTAN TUFF-DOOR)
6DOORS AND WINDOS FRAMESMAIN AND INTERNAL DOORS- RED MERENDI (ALPRO, NAYUR, BUTTAN TUFF-DOOR)
7GLASS WORKWINDOW SHUTTER - 5 MM CLEAR GLASS (SAINT GOBAIN, MODIGAURD, ASHAI) VENTILATOR SHUTTER - 5 MM CLEAR GLASS (SAINT GOBAIN, MODIGAURD, ASHAI)
8ELECTRIC FITTINGSSWITCHES - MODULAR SWITCH (ABB, PROKON, ANCHOR)
9CONDUCTING AND WIRING DETAILSCONDUIT - 25MM HEAVY AND MEDIUM (POLYPACK, AKG, JP OR EQUIVALENT) WIRE - 1.5 MM, 2.5 MM, 4 MM (PROKON, ANCHOR, POLYCAB)
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSOTIS/KONE/ECE
13EXTERNAL GLAZINGSEXTERNAL DOOR WINDOWS- ALUMINUM (JINDAL, UMALCO) WINDOW SHUTTER - 5 MM CLEAR GLASS (SAINT GOBAIN, MODIGAURD, ASHAI)
13.1WINDOWS/GLAZINGSEXTERNAL DOOR WINDOWS- ALUMINUM (JINDAL, UMALCO) WINDOW SHUTTER - 5 MM CLEAR GLASS (SAINT GOBAIN, MODIGAURD, ASHAI)
14DOORSMAIN DOOR - FLUSHDOOR WITH LAMINATE (ALPRO, NAYUR, BUTTAN TUFF-DOOR) INTERNAL DOORS - FLUSHDOOR (ALPRO, NAYUR, BUTTAN TUFF-DOOR) EXTERNAL DOOR WINDOWS- ALUMINUM (JINDAL, UMALCO)
14.1MAIN DOORSFLUSHDOOR WITH LAMINATE (ALPRO, NAYUR, BUTTAN TUFF-DOOR)
14.2INTERNAL DOORSFLUSHDOOR (ALPRO, NAYUR, BUTTAN TUFF-DOOR)
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSSWITCHES - MODULAR SWITCH (ABB, PROKON, ANCHOR) SOCKETS - MODULAR SOCKETS (ABB, PROKON, ANCHOR) SWITCH BOARDS - MODULAR SWITCHBOARDS (ABB, PROKON, ANCHOR)
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT (ASIAN, BURGER, NEROLAC)
20INTERNAL FINISHINGOBD (ASIAN, BURGER, NEROLAC)
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES 2X2 (AMBANI, ORIENT BELL, VERMORA)
1 . 2 WALLSOBD (ASIAN, BURGER, NEROLAC)
1 . 3 CEILINGOBD (ASIAN, BURGER, NEROLAC)
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES 2X2 (AMBANI, ORIENT BELL, VERMORA)
2 . 2 WALLSOBD (ASIAN, BURGER, NEROLAC)
2 . 3 CEILINGOBD (ASIAN, BURGER, NEROLAC)
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
3 . 2 WALLSGLAZED CERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
3 . 3 CEILINGGRID CEILING
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSWC-WESTERN (PARKASH, WOLGA)
3 . 6 FITTING/FIXTURESSTANDARD WASHBASIN (HINDWARE, WOLGA) STANDARD TAPS (HINDWARE, WOLGA)
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES 2X2 (AMBANI, ORIENT BELL, VERMORA)
4 . 2 WALLSOBD (ASIAN, BURGER, NEROLAC)
4 . 3 CEILINGOBD (ASIAN, BURGER, NEROLAC)
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORCERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
5 . 2 WALLSGLAZED CERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
5 . 3 CEILINGGRID CEILING
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSWC-WESTERN (PARKASH, WOLGA)
5 . 6 FIXTURESSTANDARD WASHBASIN (HINDWARE, WOLGA) STANDARD TAPS (HINDWARE, WOLGA)
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES 2X2 (AMBANI, ORIENT BELL, VERMORA)
6 . 2 WALLSGLAZED CERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
6 . 3 CEILINGOBD (ASIAN, BURGER, NEROLAC)
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESSINK SINGLE BOWL (HINDWARE, WOLGA) STANDARD TAPS (HINDWARE, WOLGA)
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
7 . 2 WALLS & CEILINGTEXTURE PAINT (ASIAN, BURGER, NEROLAC)
7 . 3 TOILETNA
7 . 4 BALCONYCERAMIC TILES (AMBANI, ORIENT BELL, VERMORA)
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 07-12-2021 View Document
2 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 07-12-2021 View Document
3 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 07-12-2021 View Document
4 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 16-12-2021 View Document
5 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 16-12-2021 View Document
6 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 16-12-2021 View Document
7 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 16-12-2021 View Document
8 SITE PLAN-WATER SUPPLY LAYOUT 17-01-2022 ------
9 BASEMENT AREA DIAGRAM 17-01-2022 ------
10 BASEMENT LAYOUT 17-01-2022 ------
11 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 17-01-2022 View Document
12 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 17-01-2022 View Document
13 COMMERCIAL ELEVATIONS AND SECTIONS 17-01-2022 ------
14 COMMERCIAL LAYOUT AND AREA STATEMENT 2 17-01-2022 ------
15 COMMERCIAL LAYOUT AND AREA STATEMENT 17-01-2022 ------
16 COMMUNITY HALL CRECHE CUM ANGANWADI LAYOUTS 17-01-2022 ------
17 DEMARCATION PLAN 17-01-2022 View Document
18 LAYOUT TOWER A1 17-01-2022 ------
19 LAYOUT TOWER A3 17-01-2022 ------
20 MASTER PLAN FOR HUDA SERVICE ESTIMATE-FIRE LAYOUT 17-01-2022 ------
21 MASTER PLAN FOR HUDA SERVICE ESTIMATE-IRRIGATION LAYOUT 17-01-2022 ------
22 MASTER PLAN FOR HUDA SERVICE ESTIMATE-SEWER LAYOUT 17-01-2022 ------
23 SITE PLAN-IRRIGATION LAYOUT 17-01-2022 ------
24 TOWER A1 AND A2 ELEVATION 17-01-2022 ------
25 TOWER A1 AND A2 SECTIONS 17-01-2022 ------
26 MASTER PLAN FOR HUDA SERVICE ESTIMATE-STORM WATER LAYOUT 17-01-2022 ------
27 MASTER PLAN FOR HUDA SERVICE ESTIMATE-WATER SUPPLY LAYOUT 17-01-2022 ------
28 SERVICE ESTIMATES DTCP COMMUNICATION 17-01-2022 ------
29 SITE LAYOUT- GREEN AREA AND PARKING 17-01-2022 ------
30 SITE PLAN 17-01-2022 ------
31 SITE PLAN-FIRE LAYOUT 17-01-2022 ------
32 SITE PLAN-SEWER LAYOUT 17-01-2022 ------
33 TOWER 1-12 CARPET AREA 17-01-2022 ------
34 SITE PLAN-STP 17-01-2022 ------
35 SITE PLAN-STROM WATER LAYOUT 17-01-2022 ------
36 TOWER A1 AREA DIAGRAM 17-01-2022 ------
37 TOWER A3 A4 A5 ELEVATIONS 17-01-2022 ------
38 TOWER A3 A4 A5 SECTIONS 17-01-2022 ------
39 TOWER B1 AREA SHEET 17-01-2022 ------
40 TOWER B1 ELEVATIONS 17-01-2022 ------
41 TOWER B1 LAYOUT 17-01-2022 ------
42 TOWER B1 SECTION 17-01-2022 ------
43 TOWERS A3 AND A5 AREA DIAGRAMS 17-01-2022 ------
44 WATER SUPPLY NETWORKING PLAN 17-01-2022 ------
45 ZONING PLAN 17-01-2022 View Document