As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
859709
09-11-2021
255719
INDUSIND BANK
HRERA Panchkula
6.31875 (Acre)
1
1
6.31875 (Acre)
License no 60 of 2021
No
Address OT-15, 3RD FLOOR, NEXT DOOR, PARKLANDS, SECTOR-76 FARIDABAD FARIDABAD HR 121004 IN
Address VILLAGE KHERI KALAN , FARIDABAD
Address OT-14, 3RD FLOOR, NEXT DOOR PARKLANDS, SECTOR-76 FARIDABAD FARIDABAD HR 121004 IN
Annexure-B- AS A COLLABORATOR.
BY VIRTUE OF COLLABORATION AGREEMENT.
Yes
THE LANDOWNER IS DESIROUS OF DEVELOPING THE LAND AND HAVE APPROACHED THE DEVELOPER TO DEVELOP THE LAND.
No
No
Yes
3011.80 Lakhs
1279.66 Lakhs
0 Lakhs
968 Lakhs
764.14 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
3.414
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
1.33875
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.486
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.022
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0.111
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.632
12
ANY OTHER
0.315
Total
6.31875
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
116
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
38
YET TO BE PREPARED
3
STORM WATER DRAINAGE
101
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
242
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
35
YET TO BE PREPARED
6
STREET LIGHTING
13
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
6
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
86
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
331
YET TO BE PREPARED
27-08-2021 (date)
NA (date)
01-12-2021
26-08-2026
Plot Area(In Square Meter)
Number of plots in the project
10533.60
90
125.40
1
198.91
2
119.73
1
245.12
2
599.61
4
1048.10
7
358.53
3
585.24
4
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.6
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
47.2
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.6
11.6
11.6
11.6
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
47.2
47.2
47.2
47.2
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.6
11.6
11.6
11.6
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
47.2
47.2
47.2
47.2
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
11.6
0
0
0
Water Supply System
0
7.6
7.6
7.7
Sewerage treatment & garbage disposal
0
7
7
7
Electricity Supply System
30.25
30.25
30.25
30.25
Storm Water Drainage
0
20.2
20.2
20.2
Parks and Playgrounds
0
0
15
15
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
47.2
47.2
47.2
47.2
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
7.6
7.6
0
0
Sewerage treatment & garbage disposal
7
7
0
0
Electricity Supply System
30.25
30.25
30.25
30.25
Storm Water Drainage
20.2
20.2
0
0
Parks and Playgrounds
15
15
15
11
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
47.2
47.2
47.2
47.2
Street Lighting
4
5
4
Security and Fire Fighting
6
Yes
No
BARAKHAMBA ROAD GOPAL DAS BHAWAN BRANCH
258181810002
INDB0000005
110234002
000005
1. Manik Malik,CFO, Address: D-2/2406, Vasant Kunj, Delhi-110070(Email:Manik.malik@bptp.com) 2. Sanjeev Loknath Agrawal, DGM (Finance and Accounts), Address: Flat No-32,Sudershan Apartments, IP Extension, New Delhi-110092 (Email: Sanjeev.agrawal@bptp.com) 3. Rakesh Agrawal, SGM(Finance and Accounts), Address: D-308,Narwama Apartment, 89, IP Extension, Patparganj, New Delhi-110092 (Email: rakesh.agrawal@bptp.com) 4. Amit Kumar Singhal, AGM(Finance and Accounts), Address: E3/28 Nand Nagri, Mandoli,North East, Delhi-110093 (Email: amit1.singhal@bptp.com
As Attached
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 60 OF 2021
ALREADY BEEN OBTAINED
27-08-2021
II. LAYOUT APPROVAL
ALREADY BEEN OBTAINED
27-08-2021
Yes
Yes
As Attached
PHASE-I, PLOTS, SECTOR-81(EDEN ESTATE)
15.12
0
168
0
163
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
3183.00
3471.30
3830.49
Cost of the apartments
0
0
0
Cost of the infrastructure
1001.00
3000.00
847.46
Others costs
440.00
471.30
2983.03
12910 Lakhs
4577 Lakhs
2000 Lakhs
1720 Lakhs
No
08-10-2018
30-06-2022
BPTP DISTRICT 1 BLOCK B
10.056
0
189
0
60
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
3657
0
1234.27
Cost of the apartments
0
0
0
Cost of the infrastructure
1453.00
0
109.36
Others costs
2204.60
0
1124.91
1938.70 Lakhs
2704.48 Lakhs
1430.00 Lakhs
1230.00 Lakhs
No
06-08-2019
01-08-2024
BPTP DISTRICT 1 BLOCK A
12.373
0
220
0
110
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
4504.39
0
1644.65
Cost of the apartments
0
0
0
Cost of the infrastructure
1786.00
0
88.43
Others costs
2718.39
0
1556.22
2527.04 Lakhs
4760.71 Lakhs
1757 Lakhs
1511 Lakhs
No
01-08-2019
29-07-2024
BPTP DISTRICT 1 BLOCK C
12.72
0
244
0
68
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
4640
0
1929.53
Cost of the apartments
0
0
0
Cost of the infrastructure
1838.00
0
498.88
Others costs
2802.11
0
1430.65
1385 Lakhs
4391 Lakhs
1809 Lakhs
1506 Lakhs
No
20-08-2019
18-08-2024
102 EDEN ESTATE
28.67
45
235
36
48
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
21082.43
0
19000.65
Cost of the apartments
0
0
0
Cost of the infrastructure
4278.5
0
2587
Others costs
16803.93
0
16413.65
91674.41 Lakhs
17173.38 Lakhs
11500 Lakhs
11500 Lakhs
Yes
01-10-2020
30-04-2024
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: