HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-978-2021
Submission Date : 15-11-2021 05:33:44 PM
Applicant Type : Firm
Project Type: ONGOING


HL RESIDENCY (PROPRIETORSHIP FIRM)
SHOP NO 8 COMMERCIAL COMPLEX HL CITY SECTOR 37 BAHADURGARH DISTT JHAJJAR HARYANA
01276297888
9958488889 (Number Shared by Promoter in Public)
HLRESIDENCYAFFORDABLE@GMAIL.COM
HR07E0002157
BCSPS5048B











HL RESIDENCY AFFORDABLE GROUP HOUSING
VILLAGE NUNA MAJRA SECTOR 37 HL CITY
BAHADURGARH
JHAJJAR
01276297888
9466626999 (Number Shared by Promoter in Public)
HLRESIDENCYAFFORDABLE@GMAIL.COM
SACHIN DAHIYA
01276297888
9466626999 (Number Shared by Promoter in Public)
HLRESIDENCY@GMAIL.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
12335426-10-201926900AXIS BANK BAHADURGARHHRERA Panchkula
22335526-10-2019414200AXIS BANK BAHADURGARHHRERA Panchkula
3667104-11-2019546285AXIS BANK PANCHKULAHRERA Panchkula
485982405409-11-2021771000ONLINE PAYMENT-AXIS BANKHRERA Panchkula







45987.9178 (Sqr/mtrs)
106675.202
231.96
45783.3495 (Sqr/mtrs)
75 of 2019 dated 23.07.2019 and 31 of 2021 dated 30.06.2021.
Yes







21758.42 Lakhs
1663.42 Lakhs
16000 Lakhs
2895 Lakhs
1200 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS11604.472
3CONSTRUCTION OF ROADS11079.103
4PAVEMENTS0
5PARKS AND PLAYGROUNDS9548.87
6GREEN BELTS2333.862
7VEHICLE PARKINGS5272.231
8ELECTRICITY SUB-STATION600
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY900
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER3900
13CRECHE374.69
14COMMUNITY374.69
Total45987.918




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSH L RESIDENCY PVT LTDNo
WATER SUPPLYHDRANo
ELECTRICITYUHBVNNo
SEWAGE DISPOSALH L RESIDENCY PVT LTD/ HDRANo
STORM WATER DRAINAGEH L RESIDENCY PVT LTD/ HDRANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS690YET TO BE PREPARED
2WATER SUPPLY SYSTEM420YET TO BE PREPARED
3STORM WATER DRAINAGE50YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM695YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL300YET TO BE PREPARED
6STREET LIGHTING100YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING250YET TO BE PREPARED
8PLAYGROUNDS AND PARKS150YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE30YET TO BE PREPARED
10SHOPPING AREA10YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER200YET TO BE PREPARED


NA (date)
31-10-2021 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-1 3BHK59.9973471272205
2APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-1A-3BHK59.931351842675
3APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-1B 3BHK59.9979123684
4APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-1C 3BHK59.9319139524
5APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-2 2BHK59.641130103272
6APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-2A 2BHK59.68613094362
7APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-3 1BHK28.994426983283
8APARTMENT/SHOPS/OTHER BUILDINGS Type UNIT-4 2BHK59.559200201
9APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE 1-GF208.65872021
10APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE 2-GF210.902021
11APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE 3-GF123.0565051
12APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE 4-FF166.962021
13APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE 5-FF1652021
14APARTMENT/SHOPS/OTHER BUILDINGS Type COMMERCIAL TYPE 6-FF92.4265051






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
00


09-06-2020
09-06-2023
29-06-2026
09-06-2020
0
29-06-2026
ATTACHED
ANNEXURE C ATTACHED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT0NA
09-06-2020
0
29-06-2026


679
310
0
229
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments1645
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1645700
Shops00
Plots00

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments700135013501350
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments13501516650650
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments650650650650
Shops0000
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments6507007890
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments000
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements305
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements3050
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other00
Street Lighting0

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements003838
Water Supply System004242
Sewerage treatment & garbage disposal003030
Electricity Supply System007070
Storm Water Drainage0055
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Lightning2020
Security and Fire Fighting5050

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements38383838
Water Supply System42424242
Sewerage treatment & garbage disposal30303030
Electricity Supply System70707070
Storm Water Drainage5555
Parks and Playgrounds0151515
Clubhouse/community centres0200
Shopping area0100
Other0202020
Street Lightning0000
Security and Fire Fighting0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements38383843
Water Supply System42424242
Sewerage treatment & garbage disposal30303030
Electricity Supply System70707065
Storm Water Drainage5555
Parks and Playgrounds15151515
Clubhouse/community centres0000
Shopping area0000
Other20202020
Security and Fire Fighting0000
Street Lightning002020

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds1515150
Clubhouse/community centres1010100
Shopping area00100
Other2020200
Street Lightning20000
Security and Fire Fighting50500
Security and Fire fighting50

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System000
Sewerage treatment & garbage disposal000
Electricity Supply System000
Storm Water Drainage000
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000
Street Lightning00
Security and Fire Fighting00












Particulars Remarks, if any
i. No. of Flats/Apartments constructed0
ii. No. of Flats/ Apartments booked568
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter12279.30 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter6580.87 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter5698.43 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 Lakhs
vii. Amount invested in the project upto the date of application0 Lakhs
Land cost (If any)1663.42 Lakhs
Apartments1645 Lakhs
Infrastructure305 Lakhs
EDC/ Taxes Etc.588.64 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession17556.36 Lakhs
(a) In respect of existing allottees5632.15 Lakhs
(b) In respect of rest of the project11924.21 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS690305
II. WATER SUPPLY SYSTEM4200
III. STORM WATER DRAINAGE500
IV. ELECTRICITY SUPPLY SYSTEM6950
V. SEWAGE TREATMENT & GARBAGE DISPOSAL3000
VI. CLUB HOUSE/COMMUNITY CENTRE300
VII. SCHOOL00
VIII. ANY OTHER2000
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING100
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.1500
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM2500
XVII. OTHER FACILITIES AS PER PROJECT REPORT1000









Yes
Yes
THE JHAJJAR CENTRAL CO-OPERATIVE BANK LIMITED
000735030100005
UTIB0JCCB01
0007
SHAILAJA
ATTACHED











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE GRANTED BY DTCP LICENSE NO 75ALREADY BEEN OBTAINED23-07-2019
II. ZONING PLANALREADY BEEN OBTAINED06-09-2021
III. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED04-11-2019
IV. LICENSE GRANTED BY DTCP-LICENSE NO 31ALREADY BEEN OBTAINED30-06-2021
V. SANCTIONED BUILDING PLANALREADY BEEN OBTAINED24-10-2021








Yes


Yes


ATTACHED













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
2WALL FINISHING DETAILSWALL PUTTY WITH OBD
3KITCHEN DETAILSONE SINK WITHOUT DRAIN BOARD
4BATHROOM FITTINGSONE WASH BASIN ONE ENGLISH SEAT WITH CP FITTING
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESMILD STEEL PRESSED STEEL FRAME
7GLASS WORKON EXTERNAL WINDOW
8ELECTRIC FITTINGSISI MARK SWITCH SOCKET
9CONDUCTING AND WIRING DETAILSIN PVC CONDUITS WITH COPPER WIRING
10CUPBOARD DETAILSNA
11WATER STORAGEA COMMON TANK IN RCC FORM HALF DAY CAPACITY PROVIDED
12LIFT DETAILSTOWER F 6 NOS TOWER C 3 NOS
13EXTERNAL GLAZINGSONLY MS WINDOW IN FLAT PROVIDED
13.1WINDOWS/GLAZINGS4MM GLASS
14DOORSFLUSH DOOR SHUTTER
14.1MAIN DOORSFLUSH DOOR SHUTTER
14.2INTERNAL DOORSFLUSH DOOR SHUTTER
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGOBD
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSWALL PUTTY WITH OBD
1 . 3 CEILINGPUTTY WITH OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSWALL PUTTY WITH OBD
2 . 3 CEILINGPUTTY WITH OBD
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNON SKID TILES
3 . 2 WALLSGLAZED TILES
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSONE WASH BASIN ONE ENGLISH SEAT WITH CP FITTING
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSWALL PUTTY WITH OBD
4 . 3 CEILINGPUTTY WITH OBD
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNON SKID CERAMIC TILES
5 . 2 WALLSGLAZED TILES
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSONE WASH BASIN ONE ENGLISH SEAT WITH CP FITTING
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSGLAZED TILES 2 FEET ABOVE COUNTER
6 . 3 CEILINGPUTTY WITH OBD
6 . 4 COUNTERSGRANITE STONE ON RCC SLAB
6 . 5 FIXTURESSTAINLESS STEEL SINK WITHOUT DRAIN BOARD
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNON SKID TILES
7 . 2 WALLS & CEILINGWALL PUTTY WITH OBD
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNON SKID TILES
8 . 2 WALLS & CEILINGWALL PUTTY WITH OBD
8 . 3 RAILINGSMS RAILING
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN30-10-2021 View Document
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND30-10-2021 View Document
3SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN30-10-2021 View Document
4DEMARCATION PLAN30-10-2021 View Document
5IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN30-10-2021 View Document
6ZONING PLAN30-10-2021 View Document
7A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS30-10-2021 View Document
8DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.30-10-2021 View Document
9DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD30-10-2021 View Document
10CASH FLOW STATEMENT OF THE PROPOSED PROJECT30-10-2021 View Document
11EXPLANATORY STATEMENT15-11-2021 ------
12CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT15-11-2021 View Document
13NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT15-11-2021 View Document