HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-967-2021
Submission Date : 25-09-2021 01:46:55 PM
Applicant Type : Firm
Project Type: NEW


RHYTHM BUILDTECH
H.NO. - 1868, SECTOR- 04, REWARI, HARYANA - 123401
9991933997 (Number Shared by Promoter in Public)
rhythmcity21@gmail.com
00006
ABCFR1793G













RHYTHM CITY
VILLAGE MAHESHWARI, TEHSIL DHARUHERA & DISTRICT REWARI, HARYANA
DHARUHERA ST
REWARI
9991933997 (Number Shared by Promoter in Public)
rhythmcity21@gmail.com
HITESH MISHRA
9991933997 (Number Shared by Promoter in Public)
rhythmcity21@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
160677723-09-2021505000INDIAN BANKHRERA Panchkula







10.90625 (Acre)
0
0
10.90625 (Acre)
59 of 2021 dated 27.08.2021
No
Address     306-308, SQUARE ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Address     306-308, SQUARE ONE, C-2, DISTRICT CENTRE, SAKET, NEW DELHI-110017
Annexure-B- COLLABORATION AGREEMENTS AND POWER OF ATTORNEY
COLLABORATION AGREEMENTS AND POWER OF ATTORNEY BEFORE GRANT OF LICENCE AND ALL DOCUMENT ARE IMPORTANT
Yes
FULL DOCUMENT IS IMPORTANT
No
Yes
Yes







1360.86 Lakhs
121.00 Lakhs
0 Lakhs
421.89 Lakhs
817.97 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD5.412
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS2.8225
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0.8195
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.1033
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.11455
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES1.0909
12ANY OTHER0.05305
13COMMERCIAL0.43426
14UNDER0.0494
15MILK0.00679
Total10.90625




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDANo
WATER SUPPLYHUDANo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHUDANo
STORM WATER DRAINAGEHUDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS173.29AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM79.12AS PER PROJECT REPORT
3STORM WATER DRAINAGE63.61AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM185.46AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL97.26AS PER PROJECT REPORT
6STREET LIGHTING0AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS32.72AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER15.00AS PER PROJECT REPORT
15BOUNDARY WALL GATE AND GUARD ROOM171.52AS PER PROJECT REPORT


31-08-2021 (date)
NA (date)
01-10-2021
26-08-2026
Plot Area(In Square Meter)Number of plots in the project
108.8069
136.602
117.441
97.5010
120.254
107.251
91.501
117.003
97.501
98.2523
102.644
107.649
91.3815
138.777
95.3536
138.3618
1757.281


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.75
Water Supply System7.19
Sewerage treatment & garbage disposal8.84
Electricity Supply System16.86
Storm Water Drainage5.78
Parks and Playgrounds2.97
Clubhouse/community centres0
Shopping area0
Other1.36
Boundary Wall and Gate and Guard Room15.59

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.7515.7515.7515.75
Water Supply System7.197.197.197.19
Sewerage treatment & garbage disposal8.848.848.848.84
Electricity Supply System16.8616.8616.8616.86
Storm Water Drainage5.785.785.785.78
Parks and Playgrounds2.972.972.972.97
Clubhouse/community centres0000
Shopping area0000
Other1.361.361.361.36
Boundary Wall and Gate and Guard Room15.5915.5915.5915.59

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.7515.7515.7515.75
Water Supply System7.197.197.197.19
Sewerage treatment & garbage disposal8.848.848.848.84
Electricity Supply System16.8616.8616.8616.86
Storm Water Drainage5.785.785.785.78
Parks and Playgrounds2.972.972.972.97
Clubhouse/community centres0000
Shopping area0000
Other1.361.361.361.36
Boundary Wall and Gate and Guard Room15.5915.5915.5915.59

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.7515.75
Water Supply System7.197.19
Sewerage treatment & garbage disposal8.848.84
Electricity Supply System16.8616.86
Storm Water Drainage5.785.78
Parks and Playgrounds2.972.97
Clubhouse/community centres00
Shopping area00
Other1.361.36
Boundary Wall and Gate and Guard Room15.5915.59












No
No
INDIAN BANK, DSS 145-146, SECTOR-4, HUDA MARKET, REWARI, HARYANA.
7029419735
IDIB000R634
123019004
6417
SH. HITESH MISHRA R/O H.NO.- 6611, BASS SITAAB RAI, WARD NO. - 15, NEAR BHARAWAS GATE, REWARI, HARYANA - 123401
YES











Yes
No
No
No
No
No
No
No
No
No


No
No
No
No
No
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSEALREADY BEEN OBTAINED27-08-2021
II. LAYOUT PLANALREADY BEEN OBTAINED31-08-2021








Yes


Yes


FULL AGREEMENT













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND18-09-2021 View Document
2IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN18-09-2021 View Document
3A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS18-09-2021 View Document
4CASH FLOW STATEMENT OF THE PROPOSED PROJECT18-09-2021 View Document
5IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN18-09-2021 View Document
6NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT25-09-2021 View Document
7DEMARCATION PLAN25-09-2021 View Document
8ZONING PLAN25-09-2021 View Document
9DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.25-09-2021 View Document