9810253077 (Number Shared by Promoter in Public)
sumitagarwal@emperiumrealty.com
https://www.emperiumrealty.com/
XXXX163A
U45200DL2015PTC278647
EMPERIUM CITY
VILLAGE TARAF RAJPUTAN & TARAF INSAR, SECTOR-1A
PANIPAT
PANIPAT
9810253077 (Number Shared by Promoter in Public)
sumitagarwal@emperiumrealty.com
SUMIT AGARWAL
9810253077 (Number Shared by Promoter in Public)
sumitagarwal@emperiumrealty.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
503856
20-09-2021
450000
ICICI BANK
HRERA Panchkula
9.28 (Acre)
1
1
9.28 (Acre)
65 of 2021 dated 04.09.2021
Yes
4105.00 Lakhs
1219.00 Lakhs
0.00 Lakhs
1951.00 Lakhs
935.00 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
4.763
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
2.294
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.781
6
GREEN BELTS
0.307
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
13
COMMERCIAL
0.207
14
COMMUNITY
0.928
Total
9.28
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
No
WATER SUPPLY
HUDA
No
ELECTRICITY
UHBVNL
No
SEWAGE DISPOSAL
HUDA
No
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
164.82
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
170.00
YET TO BE PREPARED
3
STORM WATER DRAINAGE
85.61
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
38.00
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
256.22
YET TO BE PREPARED
6
STREET LIGHTING
14.24
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
15.39
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
MAINTENANCE OF SERVICES
185.43
YET TO BE PREPARED
08-09-2021 (date)
NA (date)
15-10-2021
03-09-2026
Plot Area(In Square Meter)
Number of plots in the project
137.445
74
99.5625
83
149.82
4
149.7125
1
92.9475
1
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.25
Water Supply System
9.00
Sewerage treatment & garbage disposal
14.00
Electricity Supply System
0
Storm Water Drainage
4.30
Parks and Playgrounds
0.77
Clubhouse/community centres
0
Shopping area
0
Other
0
Street Lighting
0.70
Maintenance
0.00
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.82
9.85
9.00
9.00
Water Supply System
8.65
8.65
8.60
8.60
Sewerage treatment & garbage disposal
14.00
14.00
15.00
15.00
Electricity Supply System
0
0
0
0
Storm Water Drainage
4.35
4.35
4.35
4.30
Parks and Playgrounds
0.85
0.85
0.77
0.77
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Maintenance
0
9.27
9.27
9.27
Street Lighting
0.70
0.70
0.80
0.80
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
9.15
9.15
8.25
8.25
Water Supply System
8.50
8.50
8.40
8.40
Sewerage treatment & garbage disposal
16.00
16.00
14.00
14.00
Electricity Supply System
0
0
0
0
Storm Water Drainage
4.25
4.25
4.35
4.35
Parks and Playgrounds
0.77
0.70
0.70
0.70
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Maintenance
10.30
10.30
10.30
10.30
Street Lighting
0.90
0.90
0.90
0.90
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
8.55
8.55
8.50
8.50
Water Supply System
8.35
8.35
8.40
8.40
Sewerage treatment & garbage disposal
13.00
13.00
12.50
12.50
Electricity Supply System
0
0
0
0
Storm Water Drainage
4.35
4.35
4.30
4.30
Parks and Playgrounds
0.85
0.85
0.85
0.85
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Maintenance
9.27
9.27
9.27
9.27
Street Lighting
0.85
0.85
0.85
0.85
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
7.50
7.50
7.25
7.25
Water Supply System
8.35
8.35
8.50
8.50
Sewerage treatment & garbage disposal
12.00
12.00
11.00
10.20
Electricity Supply System
0
0
0
0
Storm Water Drainage
4.15
4.15
4.20
4.20
Parks and Playgrounds
0.73
0.73
0.73
0.73
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Street Lighting
0.54
0.50
0.50
0.50
Maintenance
11.59
11.59
11.59
11.59
Particulars
Year-2026
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
6.50
6.50
6.50
Water Supply System
8.50
8.50
8.50
Sewerage treatment & garbage disposal
9.34
9.34
9.34
Electricity Supply System
0
0
0
Storm Water Drainage
4.25
4.25
4.26
Parks and Playgrounds
0.73
0.73
0.73
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
0
Street Lighting
0.50
0.50
0.50
Maintenance
10.30
10.30
12.36
Yes
No
ICICI BANK, MODEL TOWN, PANIPAT, HARYANA-132103
661905601511
ICIC0006619
132229003
6619
RAVINDER SAUND/ HARDEEP SINGH
YES
Yes
No
No
No
No
No
No
No
Yes
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 65 OF 2021
ALREADY BEEN OBTAINED
04-09-2021
No
No
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT