HRERA GurugramTemp Project Id : RERA-GRG-PROJ-923-2021
Submission Date : 31-08-2021 04:33:56 PM
Applicant Type : Company
Project Type: ONGOING




SANTUR INFRASTRUCTURE PVT. LTD. C/O SHREE VARDHMAN INFRAHEIGHTS PVT. LTD.
302, 3RD FLOOR, INDRAZPRAKASH BUILDING, 21, BARAKHAMBA ROAD, NEW DELHI
01143605560
9811096551 (Number Shared by Promoter in Public)
victoria@shreevardhmangroup.com
http://shreevardhmangroup.com
XXXX376J
U70101DL2011PTC222557
 
 


 
 


 
 


 
 


 
 


 
 


 
 







SHREE VARDHMAN VICTORIA
SEC-70 VILLAGE BADSHAHPUR GURUGRAM HARYANA
GURGAON
GURUGRAM
01143605560
0114360556 (Number Shared by Promoter in Public)
victoria@shreevardhamgroup.com
RAMESHWAR
01143605560
9873701383 (Number Shared by Promoter in Public)
rameshwarkumar2008@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1031-08-2021ICICIHRERA Gurugram







10.9687 (Acre)
77680.196
1.7477
10.9687 (Acre)
Licence No. 103/201 Dated 30.11.2010
Yes







26185.21 Lakhs
6632.52 Lakhs
16365.98 Lakhs
0 Lakhs
3186.71 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS10.9687
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total10.9687




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNLYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS342.18SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM243.42SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE103.02SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL174.66SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING42.09SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15HORTICULTURE14.13SUBMITTED TO TOWN & COUNTRY PLANNING
16MAINTENANCE OF SERVICES531.14SUBMITTED TO TOWN & COUNTRY PLANNING


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 59200000






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
59200


12-12-2012
31-12-2020
31-08-2022
12-12-2012
85
31-08-2022
CONSTRUCTION WORK COMPLETED 85%


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
12-12-2012
85
31-08-2022


0
52
614
379
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements342.18
Water Supply System243.42
Sewerage treatment & garbage disposal174.66
Electricity Supply System0
Storm Water Drainage103.02
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Horticulture14.13
Maintenance of Services531.14
Street Lighting42.09

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Particulars Remarks, if any
i. No. of Flats/Apartments constructed592
ii. No. of Flats/ Apartments booked592
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter38844.82 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter26388.81 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter12456.01 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter31937.73 Lakhs
vii. Amount invested in the project upto the date of application26185.21 Lakhs
Land cost (If any)6632.52 Lakhs
Apartments16365.98 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.3186.71 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession0 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS00
II. WATER SUPPLY SYSTEM00
III. STORM WATER DRAINAGE00
IV. ELECTRICITY SUPPLY SYSTEM00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
No
ICICI BANK, PARLIAMENT STREET
777705226265
ICICI0006637
110229177
6637
Sandeep Jain, Sachin Jain Rishi Gupta, Vivek Aggarwal











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCE IS OBTAINED BUT RENEWAL OF LICENCE IS DUEALREADY BEEN OBTAINEDNA








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEITALIAN MARBLE/ VITRIFIED TILES
2WALL FINISHING DETAILSOIL BOUND /PLASTIC PAINT
3KITCHEN DETAILSMODULAR WITH TILES
4BATHROOM FITTINGSSTANDARD
5WOOD WORK ETCN.A
6DOORS AND WINDOS FRAMESWOOD/ UPVC/ ALUMINIUM
7GLASS WORKSANT GOVIND
8ELECTRIC FITTINGSSTANDARD
9CONDUCTING AND WIRING DETAILSSTANDARD
10CUPBOARD DETAILSNA
11WATER STORAGEO.H.W.T
12LIFT DETAILSKONE
13EXTERNAL GLAZINGSALUMINIUM /UPVC
13.1WINDOWS/GLAZINGSALUMINIUM/ UPVC
14DOORSHARD WOOD
14.1MAIN DOORSEUROPEAN STYLE FLUSH PANEL
14.2INTERNAL DOORSEUROPEAN STYLE FLUSH PANEL
15AIR CONDITIONINGSPLIT AIR CONDITIONERS
16ELECTRICAL FITTINGSSTANDARD
17CNG PIPE LINEN A
18PROVISION OF WIFI AND BROADBAND FACILITYAIR TEL
19EXTERNAL FINISHING/COLOUR SCHEMETEXTURE PAINT
20INTERNAL FINISHINGOIL BOUND/ PLASTIC PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORITALIAN MARBLE
1 . 2 WALLSOIL BOUND/PLASTIC PAINT
1 . 3 CEILINGOIL BOUND/ PLASTIC PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSOIL BOUND / PLASTIC PAINT
2 . 3 CEILINGOIL BOUND/ PLASTIC PAINT
2 . 4 MODULAR WARDROBESN A
3 . MASTER TOILET
3 . 1 FLOORANTI SKID TILES
3 . 2 WALLSTILES
3 . 3 CEILINGFALSE CEILING
3 . 4 COUNTERSN A
3 . 5 SANITARY WARE/CP FITTINGSSTANDARD
3 . 6 FITTING/FIXTURESSTANDARD
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSOIL BOUND/ PLASTIC PAINT
4 . 3 CEILINGOIL BOUND / PLASTIC PAINT
4 . 4 WARDROBESN A
5 . TOILET
5 . 1 FLOORANTI SKID TILES
5 . 2 WALLSTILES
5 . 3 CEILINGFALSE CEILING
5 . 4 COUNTERSN A
5 . 5 SANITARY WARE/CP FITTINGSSTANDARD
5 . 6 FIXTURESSTANDARD
6 . KITCHEN
6 . 1 FLOORANTI SKID TILES
6 . 2 WALLSDADO TILES/ PAINT
6 . 3 CEILINGOIL BOUND / PLASTIC PAINT
6 . 4 COUNTERSMARBLE/ GRANITE
6 . 5 FIXTURESSTANDARD
6 . 6 KITCHEN APPLIANCESCHIMNEY
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILES
7 . 2 WALLS & CEILINGOIL BOUND / PLASTIC PAINT
7 . 3 TOILETTILES
7 . 4 BALCONYTILES
8 . SIT-OUTS
8 . 1 FLOORITALIAN MARBLE
8 . 2 WALLS & CEILINGOIL BOUND / PLASTIC PAINT
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN31-08-2021 View Document
2NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT31-08-2021 View Document
3DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.31-08-2021 View Document
4IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN31-08-2021 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND31-08-2021 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Occupation Certificate 30-08-2024 View Document