EMAAR BUSINESS DISTRICT (EBD-89 NXT)
VILLAGE-BADHA, SECTOR-89, GURUGRAM
MANESAR
GURUGRAM
01244421155
9743999521 (Number Shared by Promoter in Public)
coordination@emaar-india.com
ROLI AGGARWAL
01244421155
9743999521 (Number Shared by Promoter in Public)
coordination@emaar-india.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
917115
16-07-2021
666364
HSBC BANK, MUMBAI BRANCH
HRERA Gurugram
2
205003
08-09-2021
60600
HSBC BANK, GURGAON BRANCH
HRERA Gurugram
2.99375 (Acre)
1.5
1.5
2.99375 (Acre)
53 of 2021
No
Address EMAAR BUSINESS PARK, SIKANDERPUR SECTOR-28, GURUGRAM, HARYANA- 122001
Address EMAAR BUSINESS PARK, SIKANDERPUR SECTOR-28, GURUGRAM, HARYANA- 122001
Address EMAAR BUSINESS PARK, SIKANDERPUR SECTOR-28, GURUGRAM, HARYANA- 122001
Address EMAAR BUSINESS PARK, SIKANDERPUR SECTOR-28, GURUGRAM, HARYANA- 122001
Annexure-B- COLLABORATOR
BY VIRTUE OF COLLABORATION AGREEMENT SIGNED BEFORE GRANT OF LICENSE
Yes
THE DEVELOPER SHALL BE RESPONSIBLE FOR COMPLIANCE OF ALL TERMS & CONDITIONS OF LICENCE/CLU / PROVISIONS OF THE HARYANA DEVELOPMENT
AND REGULATIONS OF URBAN AREAS ACT,1975 & RULESTHEREOF OR THE PUNJAB SCHEDULED ROAD &CONTROLLED; AREA RESTRICTION OF
UNREGULATED DEVELOPMENT ACT,1963 & RULES THEREOF AS THE CASE MAY BE,
TILL THE GRANT OF FINAL COMPLETION CERTIFICATE TO THE COLONY OR RELIEVED OF THE RESPONSIBILITY BY THE DTCP, HARYANA OR ANY OTHER COMPETENT
AUTHORITY, WHICHEVER IS EARLIER
No
Yes
Yes
6431 Lakhs
1820.51 Lakhs
0 Lakhs
1567.44 Lakhs
3043.05 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1.04747
3
CONSTRUCTION OF ROADS
1.08998
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0.46366
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0.30888
8
ELECTRICITY SUB-STATION
0.04980
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0.02465
12
ANY OTHER
0
13
TOILET
0.00930
Total
2.99374
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
ALREADY CONNECTED
Yes
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
78.91
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
48.46
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
46.18
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
69.14
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
83.63
AS PER PROJECT REPORT
6
STREET LIGHTING
15.37
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
3.50
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
162.03
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
UG TANK
64.99
AS PER PROJECT REPORT
16
RAIN WATER HARVESTING
6.55
AS PER PROJECT REPORT
17
ELECTRICAL SUBSTATION ANCILLARY BUILDING
49.68
AS PER PROJECT REPORT
18
ELECTRICAL PANELS
109.70
AS PER PROJECT REPORT
19
SIGNAGES PLOT DEMARCATION
14.05
AS PER PROJECT REPORT
20
MISCELLANEOUS WORKS
11.78
AS PER PROJECT REPORT
21
SWITCHING STATION WORKS
483.56
AS PER PROJECT REPORT
22
OTHER COSTS CONTINGENCIES LC GST
288.62
AS PER PROJECT REPORT
23
PARKING
9.53
AS PER PROJECT REPORT
24
SEWERAGE
21.75
AS PER PROJECT REPORT
NA (date)
NA (date)
01-02-2022
17-08-2026
Plot Area(In Square Meter)
Number of plots in the project
208.688
1
1381.8
14
147.803
1
1650
11
256.1
1
594.69
4
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.39
0.79
0.39
0
Water Supply System
0
0
0
0.97
Sewerage treatment & garbage disposal
0.44
0.65
1.74
2.61
Electricity Supply System
0
0
0
1.38
Storm Water Drainage
0.92
1.39
3.69
5.54
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Other cost including Contingencies and LC and GST
0.4
0.63
1.31
2.38
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.58
7.89
10.26
14.99
Water Supply System
2.42
5.33
7.75
10.66
Sewerage treatment & garbage disposal
3.92
3.92
3.05
2.18
Electricity Supply System
3.46
7.61
11.06
15.21
Storm Water Drainage
8.31
8.31
6.46
4.62
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Switching Station Works
0
9.67
24.18
53.19
Other cost including Contingencies and LC and GST
4.44
12.87
22.01
29.95
UG Tank
0
6.24
15.21
11.31
Electrical Sub Station
0
0
0
5.96
STP
0
8.03
19.57
14.55
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
14.99
11.05
7.89
4.73
Water Supply System
9.21
6.30
3.88
1.94
Sewerage treatment & garbage disposal
1.52
1.09
0.65
0
Electricity Supply System
13.14
8.99
5.53
2.77
Storm Water Drainage
3.23
2.31
1.39
0
Parks and Playgrounds
7.94
37.43
56.55
42.13
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Other cost including Contingencies and LC and GST
36.23
48.85
61.92
45.29
Electrical Sub Station
14.41
16.89
10.93
1.49
Miscellanous Works
0
0
5.89
4.71
Rainwater Harvesting System
0
0
1.97
3.08
Street Lights
0
0
4.61
7.23
Signages and Plot Demarcation
0
0
4.22
6.61
Security and Fire Fighting
0
0
1.05
1.65
Parking
0
0
2.86
4.48
STP
10.54
11.21
11.37
7.36
UG Tank
8.19
8.71
8.84
5.72
Switching Station Works
77.37
106.38
91.88
62.86
Electrical Panels
0
5.49
54.85
43.88
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
3.95
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
17.99
Clubhouse/community centres
0
Shopping area
0
Other
0
Parking
2.19
Miscellaneous Works
0.59
STP
1.00
UG Tank
0.78
Switching Station Works
58.03
Street Lights
3.54
Rainwater Harvesting System
1.51
Electrical Panels
5.49
Electrical Sub Station
0
Sinages and Plot Demarcation
3.23
Other cost including Contingencies and LC and GST
22.36
Security and Fire Fighting
0.81
Yes
No
HSBC BANK, BARAKHAMBA ROAD, NEW DELHI
166276584921
HSBC0110002
11039002
110002
Mr. Rahul Bindle (Sr. General Manager)
E-303, Park View City 1, Sector-48, Sohna Road, Gurugram
Yes
Yes
Yes
No
Yes
No
No
No
Yes
Yes
Yes
No
Yes
Yes
Yes
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE APPROVAL
ALREADY BEEN OBTAINED
18-08-2021
II. LAYOUT PLAN APPROVAL
ALREADY BEEN OBTAINED
18-08-2021
III. FOREST NOC
ALREADY BEEN OBTAINED
15-07-2021
IV. LAYOUT APPROVAL PLAN
ALREADY BEEN OBTAINED
18-08-2021
V. ZONING PLAN APPROVAL
APPLIED FOR BUT YET TO RECEIVE
NA
Yes
Yes
Subject to Force Majeure and fulfillment by the Allottee(s) of all the
terms and conditions of this Agreement including but not limited to
timely and complete payment by the Allottee(s) of the Total Price
payable in accordance with the Payment Plan, payment of stamp duty,
registration and incidental charges and other charges in connection
thereto due, and
payable by the Allottee(s) and also subject to the
Allottee(s) having complied with all
formalities or documentation as
prescribed by the, the Developer shall offer the
possession of the Plot
to the Allottee(s) on or before the date of expiry of RERA Registration
Certificate i.e. Date of Completion Certificate of the Project.
PALM HEIGHTS, SECTOR-77, GURUGRAM
5.50
297
0
148
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
20000
20000
6272
Cost of the apartments
18143
18143
4156
Cost of the infrastructure
0
0
0
Others costs
1857
1857
1392
1615 Lakhs
14821 Lakhs
0 Lakhs
2464 Lakhs
No
31-08-2022
31-08-2022
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
NA
2
WALL FINISHING DETAILS
NA
3
KITCHEN DETAILS
NA
4
BATHROOM FITTINGS
NA
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
NA
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
NA
9
CONDUCTING AND WIRING DETAILS
NA
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
NA
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
NA
14.1
MAIN DOORS
NA
14.2
INTERNAL DOORS
NA
15
AIR CONDITIONING
NA
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
NA
1 . 2
WALLS
NA
1 . 3
CEILING
NA
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
NA
2 . 2
WALLS
NA
2 . 3
CEILING
NA
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
NA
3 . 2
WALLS
NA
3 . 3
CEILING
NA
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
NA
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
NA
4 . 2
WALLS
NA
4 . 3
CEILING
NA
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
NA
5 . 2
WALLS
NA
5 . 3
CEILING
NA
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
NA
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
NA
6 . 2
WALLS
NA
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
NA
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
NA
7 . 2
WALLS & CEILING
NA
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT