Applicant Type : Registered Society or Trust or Authority
Project Type: NEW
ESTATEOFFICER,HSVP ROHTAK SECTOR-3 ROHTAK
01262279839
9812565032 (Number Shared by Promoter in Public)
eorohtakhuda2@gmail.com
http://hsvphry.org.in
XXXX087M
NA
AS PER HSVP ACT 1977
SECTOR 27,28,26,PART-I,II,III
ESTATE OFFICER, HSVP,SECTOR-3,ROHTAK
ROHTAK
ROHTAK
01262279839
9812565032 (Number Shared by Promoter in Public)
eorohtakhuda2@gmail.com
RAM PARSHAD JUNIOR ENGINEER
01262279839
9812565032 (Number Shared by Promoter in Public)
eorohtakhuda2@gmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
141.375
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
33.533
Total
300.555
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
PUBLIC HEALTH ENGINEERING DEPARTMENT
No
ELECTRICITY
UHBVNL
No
SEWAGE DISPOSAL
PUBLIC HEALTH ENGINEERING DEPARTMENT
No
STORM WATER DRAINAGE
PUBLIC HEALTH ENGINEERING DEPARTMENT
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
5565.00
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
2149.00
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
1870.00
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
1715.18
SUBMITTED TO HUDA
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
1560.00
SUBMITTED TO HUDA
6
STREET LIGHTING
9.53
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
17.30
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
181.10
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
550.00
SUBMITTED TO HUDA
10
SHOPPING AREA
570.00
SUBMITTED TO HUDA
11
RENEWABLE ENERGY SYSTEM
0.00
YET TO BE PREPARED
12
SCHOOL
50.00
SUBMITTED TO HUDA
13
HOSPITAL/DISPENSARY
500.00
SUBMITTED TO HUDA
14
ANY OTHER
0
YET TO BE PREPARED
15
POLICE POST
150.00
SUBMITTED TO HUDA
NA (date)
NA (date)
09-08-2019
31-12-2024
Plot Area(In Square Meter)
Number of plots in the project
628092.90
3053
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
5565.00
Water Supply System
2150.00
Sewerage treatment & garbage disposal
1560.00
Electricity Supply System
1715.18
Storm Water Drainage
1870.00
Parks and Playgrounds
181.10
Clubhouse/community centres
550.00
Shopping area
570.00
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0.00
0
0
0
Water Supply System
0
0
0
0
Sewerage treatment & garbage disposal
0
0
0
0
Electricity Supply System
0
0
0
0
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
600.00
600.00
500.00
760.00
Water Supply System
50.00
400.00
200.00
200.00
Sewerage treatment & garbage disposal
50.00
200.00
150.00
150.00
Electricity Supply System
0
0
0
5.17
Storm Water Drainage
50.00
300.00
200.00
300.00
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
150.00
150.00
500.00
150.00
Water Supply System
75.00
75.00
75.00
75.00
Sewerage treatment & garbage disposal
50.00
50.00
50.00
50.00
Electricity Supply System
75.00
0
0
0
Storm Water Drainage
0
75.00
50.00
50.00
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
150.00
150.00
150.00
150.00
Water Supply System
75.00
75.00
75.00
75.00
Sewerage treatment & garbage disposal
50.00
50.00
50.00
50.00
Electricity Supply System
0
0
0
50.00
Storm Water Drainage
50.00
50.00
50.00
50.00
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
50.00
100.00
100.00
100.00
Shopping area
0
50.00
50.00
100.00
Other
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
150.00
150.00
150.00
150.00
Water Supply System
50.00
50.00
50.00
50.00
Sewerage treatment & garbage disposal
50.00
50.00
50.00
50.00
Electricity Supply System
0
0
0
100.00
Storm Water Drainage
50.00
50.00
50.00
50.00
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
50.00
50.00
0
0
Shopping area
50.00
50.00
45.00
0
Other
0
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
150.00
150.00
150.00
150.00
Water Supply System
50.00
50.00
50.00
50.00
Sewerage treatment & garbage disposal
50.00
50.00
50.00
50.00
Electricity Supply System
0
0
0
0
Storm Water Drainage
50.00
50.00
50.00
50.00
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
67.90
Water Supply System
93.65
Sewerage treatment & garbage disposal
55.25
Electricity Supply System
282.88
Storm Water Drainage
78.90
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Yes
No
PNB MANIMAJRA
1183005900001699
PUNB0118300
NA
PUNB0118300
CA, HSVP, SECTOR-6, PANCHKULA
NA
Yes
Yes
Yes
Yes
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. DTP(R)1987/2018, DT. 09.08.2018
ALREADY BEEN OBTAINED
09-08-2018
Yes
No
NA
SECTOR-14 (PART-II)AND SECTOR-33 (PART-I)HISSAR
0
0
2878
0
2878
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
0
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
05-05-2013
05-03-2018
MANDITOWNSHIP KALANWALI (SIRSA)
0
0
903
0
903
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
0
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
10-03-2014
03-10-2019
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT