HRERA GurugramTemp Project Id : RERA-GRG-PROJ-844-2021
Submission Date : 05-04-2021 02:34:41 PM
Applicant Type : Company
Project Type: NEW




SRV AUTOMOTIVES PVT. LTD.
PLOT NO. 146,GALI NO. 1. OPP. POLICE CHOWKI, KAPASHERA, NEW DELHI-110037
01244850000
9818008463 (Number Shared by Promoter in Public)
info@landmarkgoc.com
http://www.landmarkthehomes.com
XXXX120Q
U34300DL2005PTC134174
 
 


 
 


 
 


 
 


 
 


 
 


 
 







LANDMARK THE HOMES 81
SECTOR 81, GURUGRAM
MANESAR
GURUGRAM
0000000000
9818794949 (Number Shared by Promoter in Public)
info@landmarkgoc.com
NARENDER MALIK
0000000000
9818794949 (Number Shared by Promoter in Public)
info@landmarkgoc.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11661205-04-20211097940IDBI BANK LTD. SUSHANT LOK1, GURGAONHRERA Gurugram
21661305-04-2021471160IDBI BANK LTD. SUSHANT LOK1, GURGAONHRERA Gurugram
31700024-06-202161184IDBI BANK LTD. SUSHANT LOK1, GURGAONHRERA Gurugram







5.0 (Acre)
2.25 (Residential) 1.75 (Commercial)
2.25
5.0 (Acre)
04 of 2021 (02-03-2021)
Yes







16733.10 Lakhs
437.03 Lakhs
12829.35 Lakhs
679.18 Lakhs
2787.53 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1.1840
3CONSTRUCTION OF ROADS1.344
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1.002
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.1235
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.685
12ANY OTHER0.1767
13COMMERCIAL0.4384
14CRECHE0.0464
Total5




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP/CONNECTED WITH EXISTING REVENUE RASTA OF 9 KARAM AND PROPOSED 24 MTR. ROADNo
WATER SUPPLYGMDA- ASSURANCE LETTER MEMO NO. 153 DATED 17.03.2021No
ELECTRICITYDHBVN- ASSURANCE LETTER MEMO NO. 139/DRG-PLC DATED 03.04.2021No
SEWAGE DISPOSALHSVP- AFFIDAVIT SUBMITTEDNo
STORM WATER DRAINAGEHSVP- AFFIDAVIT SUBMITTEDNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS138.00YET TO BE PREPARED
2WATER SUPPLY SYSTEM50.00YET TO BE PREPARED
3STORM WATER DRAINAGE69.00YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM25.00YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL74.00YET TO BE PREPARED
6STREET LIGHTING20.00YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING12.00YET TO BE PREPARED
8PLAYGROUNDS AND PARKS10.00YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE33.47YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM25.00YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER32.55YET TO BE PREPARED
15PARKING10.00YET TO BE PREPARED
16STP80.00YET TO BE PREPARED
17UNDERGROUND WATER TANK45.00YET TO BE PREPARED
18RAIN WATER HARVESTING20.00YET TO BE PREPARED
19ELECTRICAL SUB STATION35.00YET TO BE PREPARED


02-06-2021 (date)
02-06-2021 (date)
01-12-2021
28-02-2026
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings59.9672908
Apartment/Shops/Other Buildings59.9091428
Apartment/Shops/Other Buildings52.0091128
Apartment/Shops/Other Buildings52.639808
Apartment/Shops/Other Buildings59.946168
Apartment/Shops/Other Buildings32.334458
Apartment/Shops/Other Buildings37.05598
Apartment/Shops/Other Buildings18363
Apartment/Shops/Other Buildings26.0423
Apartment/Shops/Other Buildings7.068103
Apartment/Shops/Other Buildings7.3573
Apartment/Shops/Other Buildings72.77713
Apartment/Shops/Other Buildings37.3823
Apartment/Shops/Other Buildings92.42913
Apartment/Shops/Other Buildings56.7623
Apartment/Shops/Other Buildings97.62113
Apartment/Shops/Other Buildings50.02813
Apartment/Shops/Other Buildings7.02223
Apartment/Shops/Other Buildings41.883103
Apartment/Shops/Other Buildings38.48563
Apartment/Shops/Other Buildings31.10113
Apartment/Shops/Other Buildings73.92113
Apartment/Shops/Other Buildings36.76823
Apartment/Shops/Other Buildings53.95613





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments517.732
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments442.3475.388246.361341.048
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments782.42806.048846.36911.048
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments764.17823.548771.36856.048
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments801.66861.05796.36866.048
Shops0000
Plots0000
Community Facilities13.2426.4726.47

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments806.36866.158971.361119.048
Shops0000
Plots0000

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments912.73
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Underground Tank4.54.5918
STP881632

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0013.820.7
Water Supply System0555
Sewerage treatment & garbage disposal07.47.47.4
Electricity Supply System2.52.52.55.0
Storm Water Drainage06.96.96.9
Parks and Playgrounds0011
Clubhouse/community centres6.6613.3113.310
Shopping area0000
Other0000
Security and Firefighting Services1.21.21.2
Parking11
Rain Water Harvesting5

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.748.334.50
Water Supply System1010150
Sewerage treatment & garbage disposal14.814.822.20
Electricity Supply System552.50
Storm Water Drainage13.813.820.70
Parks and Playgrounds0.52.550
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and Firefighting Services2.42.43.6
Street Lighting1010
Parking32.52.5
Electrical SubStation17.517.5
Rain Water Harvesting555
Renewable Energy System12.512.5
Underground Tank9
STP16

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Yes
No
SARVA HARYANA GRAMIN BANK, PLOT. NO. 36P, PRAGTI BHAWAN, SECTOR-44, GURGAON-122002
77672109942472
PUNB0HGB001
110696035
7767
Sandeep Chhillar, 9210, DLF Phase 4, Gurugram
Yes











No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE APPROVAL ALREADY BEEN OBTAINED02-03-2021
II. ZONING PLAN APPROVAL ALREADY BEEN OBTAINED04-03-2021
III. BUILDING PLAN / SITE PLAN APPROVAL ALREADY BEEN OBTAINED02-06-2021
IV. ENVIRONMENT CLEARANCE APPROVAL BASED ON LATEST APPROVED BUILDING PLANAPPLIED FOR BUT YET TO RECEIVE23-03-2021








Yes


Yes


As per norms













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED/CERAMIC TILES
2WALL FINISHING DETAILSOIL BOND/DRY DISTEMPER /WHITEWASH
3KITCHEN DETAILSMARBLE/GRANITE PLATFORM / SINGLE BOWL STAINLESS STEEL SINK / FLOORING TILES AND TILES UPTO 2 FEET HIGH ABOVE THE COUNTER AND OIL BOUND DISTEMPER IN BALANCE AREA
4BATHROOM FITTINGSCP FITTING/CHINA WARE
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESFLUSH DOORS AND UPVC/MS/ ALUMINIUM
7GLASS WORK4-6MM NORMAL GLASS/4-6MM TOUGHENED GLASS
8ELECTRIC FITTINGSISI MARKED PRODUCTS FOR WIRING, SWITCHES AND CIRCUIT.
9CONDUCTING AND WIRING DETAILSISI MARKED PRODUCTS FOR WIRING, SWITCHES AND CIRCUIT.
10CUPBOARD DETAILSN.A.
11WATER STORAGEOVERHEAD TANK AND UNDERGROUND TANK
12LIFT DETAILSSTRETCHER LIFT PER TOWER, LIFT SHAFT SIZE 1800X3000MM
13EXTERNAL GLAZINGS4-6MM NORMAL GLASS/4-6MM TOUGHENED GLASS
13.1WINDOWS/GLAZINGSUPVC/MS/ALUMINIUM
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGN.A.
16ELECTRICAL FITTINGSISI MARKED PRODUCTS FOR WIRING, SWITCHES AND CIRCUIT.
17CNG PIPE LINEN.A.
18PROVISION OF WIFI AND BROADBAND FACILITYN.A.
19EXTERNAL FINISHING/COLOUR SCHEMEOIL BOND/DRY DISTEMPER / WHITEWASH
20INTERNAL FINISHINGOIL BOND/DRY DISTEMPER / WHITEWASH
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED/CERAMIC TILES
1 . 2 WALLSOIL BOND/DRY DISTEMPER / WHITEWASH
1 . 3 CEILINGOIL BOND/DRY DISTEMPER / WHITEWASH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED/CERAMIC TILES
2 . 2 WALLSOIL BOND/DRY DISTEMPER / WHITEWASH
2 . 3 CEILINGOIL BOND/DRY DISTEMPER / WHITEWASH
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORANTISKID TILES
3 . 2 WALLSOIL BOND/DRY DISTEMPER /WHITEWASH
3 . 3 CEILINGOIL BOND/DRY DISTEMPER /WHITEWASH
3 . 4 COUNTERSN.A.
3 . 5 SANITARY WARE/CP FITTINGSCP FITTING/CHINA WARE
3 . 6 FITTING/FIXTURESCP FITTING/CHINA WARE
4 . BED ROOMS
4 . 1 FLOORVITRIFIED/CERAMIC TILES
4 . 2 WALLSOIL BOND/DRY DISTEMPER /WHITEWASH
4 . 3 CEILINGOIL BOND/DRY DISTEMPER /WHITEWASH
4 . 4 WARDROBESN.A.
5 . TOILET
5 . 1 FLOORANTISKID TILES
5 . 2 WALLSOIL BOND/DRY DISTEMPER /WHITEWASH
5 . 3 CEILINGOIL BOND/DRY DISTEMPER /WHITEWASH
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSCP FITTING/CHINA WARE
5 . 6 FIXTURESCP FITTING/CHINA WARE
6 . KITCHEN
6 . 1 FLOORVITRIFIED/CERAMIC TILES
6 . 2 WALLSOIL BOND/DRY DISTEMPER /WHITEWASH
6 . 3 CEILINGOIL BOND/DRY DISTEMPER /WHITEWASH
6 . 4 COUNTERSMARBLE/GRANITE PLATFORM / SINGLE BOWL STAINLESS STEEL SINK
6 . 5 FIXTURESCP FITTING/CHINA WARE
6 . 6 KITCHEN APPLIANCESN.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORVITRIFIED/CERAMIC TILES
7 . 2 WALLS & CEILINGOIL BOND/DRY DISTEMPER /WHITEWASH
7 . 3 TOILETN.A.
7 . 4 BALCONYVITRIFIED/CERAMIC TILES
8 . SIT-OUTS
8 . 1 FLOORN.A.
8 . 2 WALLS & CEILINGN.A.
8 . 3 RAILINGSM.S. STEEL
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND04-04-2021 View Document
2DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD04-04-2021 View Document
3ZONING PLAN04-04-2021 View Document
4CASH FLOW STATEMENT OF THE PROPOSED PROJECT04-04-2021 View Document
5NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT04-04-2021 View Document
6DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.04-04-2021 View Document
7IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN04-04-2021 View Document
8IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN04-04-2021 View Document
9DEMARCATION PLAN09-07-2021 View Document
10A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-07-2021 View Document
11CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT09-07-2021 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 The Registration Certificate has been amended due to change in bank accounts w.e.f from 12.01.2023 13-01-2023 View Document