5F, EVEREST, 46/C, CHOWRINGHEE ROAD, KOLKATA 70071 WEST BENGAL
01142654265
9650524421 (Number Shared by Promoter in Public)
ayush.gupta@ashianahousing.com
https://www.ashianahousing.com/
XXXX093P
L70109WB1986PLC040864
ASHIANA AMARAH PH I & IA
VILL. WAZIRPUR, SECTOR - 93
SOHNA
GURUGRAM
0124355111
9828023733 (Number Shared by Promoter in Public)
AYUSH.GUPTA@ASHIANAHOUSING.COM
MS CHAUHAN
0124355111
9599052793 (Number Shared by Promoter in Public)
ms.chauhan@ashianahousing.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
M/S UNIVERSE HEIGHTS (INDIA) PRIVATE LTD., IS THE ABSOLUTE OWNER OF AND IS SEIZED AND POSSESSED OF AND OTHERWISE WELL AND SUFFICIENTLY ENTITLED TO THE FREEHOLD PROPERTY ADMEASURING APPROXIMATELY 13.3375 ACRES SITUATED AT VILLAGE DHUNELA, SECTOR 33, TEHSIL SOHNA, DISTRICT GURGAON, HARYANA (?ENTIRE LAND?). THE DIRECTORATE OF TOWN AND COUNTRY PLANNING GRANTED LICENSE FOR THE DEVELOPMENT OF A GROUP HOUSING PROJECT OVER THE ENTIRE LAND TO UHPL VIDE LICENSE BEARING NO. 20 OF 2014 DATED 11.06.2014. THEREAFTER, UHPL ENTERED INTO A REGISTERED DEVELOPMENT AGREEMENT WITH ASHIANA HOUSING LIMITED FOR DEVELOPMENT ON ENTIRE LAND VIDE DEVELOPMENT AGREEMENT DATED 24.07.2014.
ASHIANA HOUSING LIMITED HAS ALSO BEEN GRANTED PERMISSION BY DIRECTORATE OF TOWN AND COUNTRY PLANNING, HARYANA DATED 26/11/15 FOR JOINT DEVELOPMENT RIGHTS AND MARKETING RIGHTS, WITH RESPECT TO LICENSE NO. 20 OF 2014 DATED 11.06.2014 GRANTED TO M/S UNIVERSE HEIGHTS (INDIA) PRIVATE LTD. TO DEVELOP A GROUP HOUSING COLONY ON THE ABOVE-MENTIONED LAND. ASHIANA HOUSING LIMITED HAS PROPOSED TO DEVELOP GROUP HOUSING COLONY UNDER THE NAME AND STYLE OF ASHIANA ANMOL PHASE II COMPRISING OF 180 UNITS ON A PORTION OF ENTIRE LAND ON LAND ADMEASURING 9750.00 SQ.MT. THAT ASHIANA HOUSING LIMITED IS APPLYING FOR REGISTRATION OF ASHIANA ANMOL PHASE II COMPRISING OF 180 UNITS.
No
Yes
Yes
14453.12 Lakhs
3576.87 Lakhs
4822.65 Lakhs
685.2 Lakhs
5368.4 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1576.129
3
CONSTRUCTION OF ROADS
2012.75
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
1380.38
6
GREEN BELTS
0
7
VEHICLE PARKINGS
737.5
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
2319.65
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
1723.591
Total
9750
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA -ALREADY CONNECTED
Yes
WATER SUPPLY
HUDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HUDA
Yes
STORM WATER DRAINAGE
HUDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
97.97
SUBMITTED TO HUDA
2
WATER SUPPLY SYSTEM
54.37
SUBMITTED TO HUDA
3
STORM WATER DRAINAGE
8.80
SUBMITTED TO HUDA
4
ELECTRICITY SUPPLY SYSTEM
162.69
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
8.98
SUBMITTED TO HUDA
6
STREET LIGHTING
8.13
SUBMITTED TO HUDA
7
SECURITY AND FIRE FIGHTING
92.21
SUBMITTED TO HUDA
8
PLAYGROUNDS AND PARKS
6.07
SUBMITTED TO HUDA
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
7.88
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
PARKING
41.99
AS PER PROJECT REPORT
16
UNDERGROUND WATER TANK
6.04
AS PER PROJECT REPORT
17
RAIN WATER HARVESTING
8.80
AS PER PROJECT REPORT
18
ESS
30.91
AS PER PROJECT REPORT
05-03-2021 (date)
05-03-2021 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK LARGE
109.59
30
0
30
1
2
APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK SMALL
92.54
90
0
90
2
3
APARTMENT/SHOPS/OTHER BUILDINGS Type 3BHK STAFF
117.27
30
0
30
1
4
APARTMENT/SHOPS/OTHER BUILDINGS Type 2BHK
72.45
30
0
30
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0000
0
NA
01-09-2021
30-04-2026
30-04-2026
01-09-2021
0
30-04-2026
NA
NA
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-09-2021
0
30-04-2026
NA
NA
266
0
0
59
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
312.98
Shops
0
Plots
0
EDC
1035.08
IDC
107.38
Land Cost
760.39
Other Cost
961.09
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
11.00
277.53
Shops
0
0
0
Plots
0
0
0
Land Cost
238.04
238.04
Other Cost
87.79
87.79
IDC
0
0
EDC
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
173.69
430.60
436.05
485.03
Shops
0
0
0
0
Plots
0
0
0
0
Land Cost
238.04
238.04
333.25
333.25
Other Cost
146.19
108.6
115.36
115.36
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
706.34
447.66
361.79
439.05
Shops
0
0
0
0
Plots
0
0
0
0
Land Cost
333.25
333.25
333.25
198.05
Other Cost
115.36
135.36
173.05
278.025
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
160.19
94.76
88.39
90.59
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
343.33
333.33
315.65
268.04
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
108.80
102.02
96.20
Shops
0
0
0
Plots
0
0
0
Other Cost
263.04
187.53
242.24
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0.00
Water Supply System
0.00
Sewerage treatment & garbage disposal
0.00
Electricity Supply System
0.00
Storm Water Drainage
0.00
Parks and Playgrounds
0.00
Clubhouse/community centres
0.00
Shopping area
0.00
Other
0.00
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
0
Storm Water Drainage
0
0
Parks and Playgrounds
0
1.21
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
8.82
17.64
Water Supply System
0
0
0
Sewerage treatment & garbage disposal
0
0
0
Electricity Supply System
0
0
0
Storm Water Drainage
0
1.33
2.65
Parks and Playgrounds
1.21
0
0
Clubhouse/community centres
0
0
0
Shopping area
0
0
0
Other
0
0
6.42
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
17.64
17.64
37.59
37.59
Water Supply System
0
0
0
21.75
Sewerage treatment & garbage disposal
0
0
1.7
3.40
Electricity Supply System
0
4
16.00
37.20
Storm Water Drainage
2.65
2.69
3.68
4.61
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
23.12
18.41
20.29
23.12
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
3.05
0
Water Supply System
21.75
16.91
Sewerage treatment & garbage disposal
3.40
0.48
Electricity Supply System
83.28
53.11
Storm Water Drainage
0
0
Parks and Playgrounds
2.50
1.15
Clubhouse/community centres
0
0
Shopping area
0
0
Other
6.79
10.05
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
300
ii. No. of Flats/ Apartments booked
229
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
20639.85 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
18053.04 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
2586.81 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
2586.81 Lakhs
vii. Amount invested in the project upto the date of application
25341.18 Lakhs
Land cost (If any)
7743.71 Lakhs
Apartments
6800.8 Lakhs
Infrastructure
1568.92 Lakhs
EDC/ Taxes Etc.
4631.99 Lakhs
Other 459.76
viii. Balance cost to be incurred for completion of the project and delivery of possession
32519.79 Lakhs
(a) In respect of existing allottees
2402.00 Lakhs
(b) In respect of rest of the project
30115.79 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
97.97
0
II. WATER SUPPLY SYSTEM
54.37
0
III. STORM WATER DRAINAGE
8.80
0
IV. ELECTRICITY SUPPLY SYSTEM
162.69
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
8.98
0
VI. CLUB HOUSE/COMMUNITY CENTRE
99.21
0
VII. SCHOOL
51.15
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
6.09
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
Yes
HDFC BANK LTD., GREATER KAILASH 2, NEW DELHI 110048
50200056967514
HDFC0000027
110240005
27
Vishal Gupta- Managing Director ,Address:W-177 GK II NEW DELHI
Ankur Gupta- Director, Address: C8 3rd floor Maharani Bagh Delhi
Varun Gupta- Director, Address: N-52nd floor Panchshila Park Delhi
Ashish Bansal – Manager Accounts
Uploaded
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
28-12-2015
II. FOREST NOC
ALREADY BEEN OBTAINED
12-08-2014
III. CONSENT TO ESTABLISH
ALREADY BEEN OBTAINED
16-02-2021
IV. AAI HEIGHT NOC
ALREADY BEEN OBTAINED
29-08-2019
V. BUILDING PLAN APPROVAL
ALREADY BEEN OBTAINED
05-03-2021
VI. FIRE FIGHTING SCHEME APPROVAL
APPLIED FOR BUT YET TO RECEIVE
NA
VII. SERVICE PLAN ESTIMATE APPROVAL
APPLIED FOR BUT YET TO RECEIVE
NA
Yes
Yes
Possession date as per RERA Reg. Certificate
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
PLASTIC EMULSION OF PLEASING SHADE OF A REPUTED BRAND
3
KITCHEN DETAILS
DOUBLE CHARGED VITRIFIED TILES, 600MM HIGH CERAMIC TILES DADO ABOVE PLATFROM AND PLASTIC PLASTIC EMULSION OF PLEASING SHADE. KITCHEN PLATFORM IN QUALITY QUARTZ/GRANITE STONE WITH STAINLESS STEEL SINK WITH STAINLESS, SHINK DRAIN AND PROVISION FOR HOT AND COLD WATER SUPPLY.
4
BATHROOM FITTINGS
EWC & WASH BASIN OF RAK BRAND/ROCA/JAQUAR OR EQUIVALENT GLASS CURTAIN IN MASTER TOILET, WALL MIXER & BASIN MIXER OF JAQUAR/GROHE/KOHLER OR EQUIVALENT. OTHER CP FILLINGS OR JAL/CONTINENTAL/PRAYAG OR EQUIVALENT MIRROR,TOWEL ROAD & HEALTH FAUCET.
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
FOLDED STEEL SECTION
7
GLASS WORK
NA
8
ELECTRIC FITTINGS
CONVENIENT PROVISION AND DISTRIBUTION OF LIGHTS AND POWER PLUGS ; PROVISION FOR ELECTRICAL CHIMNEY ABOVE PLATFORM, GAS PIPELINE AND WATER PURIFIER PPOINT IN KITCHEN.
9
CONDUCTING AND WIRING DETAILS
ALL ELECTRICAL WIRING IN CONCEALED CONDUITS WITH COPPER WIRES.
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
NA
12
LIFT DETAILS
TWO GEARLESS HIGH SPEED AUTOMATIC LIFTS IN EACH BLOCK WITH DG BACKUP.
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
NA
14
DOORS
35 MM LAMINATED FLUSH DOOR/SKIN DOORS WITH HANDLE
14.1
MAIN DOORS
35 MM LAMINATED FLUSH DOOR/SKIN DOORS WITH NIGHT LATCH, MAGICEYE AND HANDLE.
14.2
INTERNAL DOORS
35 MM LAMINATED FLUSH DOOR/SKIN DOORS WITH HANDLE.
15
AIR CONDITIONING
PROVISION FOR SPLIT AC IN ALL BED ROOM AND LIVING ROOM(NO AIR CONDITIONER ARE PROVIDED)
16
ELECTRICAL FITTINGS
NA
17
CNG PIPE LINE
PROVISION FOR PIPED LPG IN THE KITCHEN WILL BE PROVIDED.
18
PROVISION OF WIFI AND BROADBAND FACILITY
NA
19
EXTERNAL FINISHING/COLOUR SCHEME
NA
20
INTERNAL FINISHING
NA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
DOUBLE CHARGED VITRIFIED TILES
1 . 2
WALLS
PLEASING SHADE EMULSION PAINT (PLASTIC/ACRYLIC AS PER ARCHITECT'S RECOMMENDATION) FINISH OF APPROPRIATE QUALITY
1 . 3
CEILING
PLASTERED WITH EITHER- A) SAND-CEMENT MORTAR AND A COAT OF PLASTER OF PARIS OR B) GYPSUM
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
DOUBLE CHARGED VITRIFIED TILES
2 . 2
WALLS
PLEASING SHADE EMULSION PAINT (PLASTIC AS PER ARCHITECT'S RECOMMENDATION) FINISH OF APPROPRIATE QUALITY
2 . 3
CEILING
PLASTERED WITH EITHER- A) SAND-CEMENT MORTAR AND A COAT OF PLASTER OF PARIS OR B) GYPSUM
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC TILES
3 . 2
WALLS
CERAMIC TILES HEIGHT UP TO 2100 MM
3 . 3
CEILING
PLASTERED WITH EITHER- A) SAND-CEMENT MORTAR AND A COAT OF PLASTER OF PARIS OR B) GYPSUM
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
EWC & WASH BASIN OF RAK BRAND/ROCA/JAQUAR OR EQUIVALENT GLASS CURTAIN IN MASTER TOILET, WALL MIXER & BASIN MIXER OF JAQUAR/GROHE/KOHLER OR EQUIVALENT. OTHER CP FILLINGS OR JAL/CONTINENTAL/PRAYAG OR EQUIVALENT MIRROR,TOWEL ROAD & HEALTH FAUCET.
3 . 6
FITTING/FIXTURES
NA
4 . BED ROOMS
4 . 1
FLOOR
DOUBLE CHARGED VITRIFIED TILES
4 . 2
WALLS
PLEASING SHADE EMULSION PAINT (PLASTIC AS PER ARCHITECT'S RECOMMENDATION) FINISH OF APPROPRIATE QUALITY
4 . 3
CEILING
PLASTERED WITH EITHER- A) SAND-CEMENT MORTAR AND A COAT OF PLASTER OF PARIS OR B) GYPSUM
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
CERAMIC TILES
5 . 2
WALLS
CERAMIC TILES HEIGHT UP TO 2100 MM
5 . 3
CEILING
PLASTERED WITH EITHER- A) SAND-CEMENT MORTAR AND A COAT OF PLASTER OF PARIS OR B) GYPSUM
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
EWC & WASH BASIN OF RAK BRAND/ROCA/JAQUAR OR EQUIVALENT, WALL MIXER & BASIN MIXER OF JAQUAR/GROHE/KOHLER OR EQUIVALENT. OTHER CP FILLINGS OR JAL/CONTINENTAL/PRAYAG OR EQUIVALENT MIRROR, TOWEL ROAD & HEALTH FAUCET.
5 . 6
FIXTURES
NA
6 . KITCHEN
6 . 1
FLOOR
DOUBLE CHARGED VITRIFIED TILES
6 . 2
WALLS
600MM HIGH CERAMIC TILES DADO ABOVE PLATFORM AND PLASTIC EMULSION OF PLEASING SHADE OF REPUTED BRAND .
6 . 3
CEILING
NA
6 . 4
COUNTERS
NA
6 . 5
FIXTURES
KITCHEN PLATFROM IN QUARTZ/GRANITE STONE WITH STAINLESS STEEL SINK WITH DRAIN BOARD & PROVISION FOR HOT AND COLD WATER SUPPLY
6 . 6
KITCHEN APPLIANCES
NA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
CERAMIC TILES
7 . 2
WALLS & CEILING
ACRYLIC EMULSION WITH PLEASING SHADE OF A REPUTED BRAND AS PER ARCHITECT SUGGESTION.
7 . 3
TOILET
NA
7 . 4
BALCONY
NA
8 . SIT-OUTS
8 . 1
FLOOR
NA
8 . 2
WALLS & CEILING
NA
8 . 3
RAILINGS
NA
8 . 4
FIXTURES
NA
Sr. No.
Document Description
Date of Document Upload
View Document
1
IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN