HRERA GurugramTemp Project Id : RERA-GRG-PROJ-811-2021
Submission Date : 08-02-2021 12:03:23 PM
Applicant Type : Company
Project Type: NEW




CONSOLIDATE REALTORS PVT. LTD.
LGF, F-22, SUSHANT SHOPPING ARCADE, SUSHANT LOK PHASE-1, GURUGRAM, HARYANA
01244732000
9711348349 (Number Shared by Promoter in Public)
consolidaterealtors@gmail.com
http://consolidaterealtors.com
XXXX796N
U70109HR2006PTC047030
 
 


 
 


 
 


 
 







ICON AT M3M MERLIN (TOWER T-11)
SECTOR-67, GURUGRAM
BADSHAHPUR ST
GURUGRAM
01244732000
9711348349 (Number Shared by Promoter in Public)
consolidaterealtors@gmail.com
RAJIV KHANNA
01244732000
9711348349 (Number Shared by Promoter in Public)
consolidaterealtors@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
151077217-08-2020385000ICICIHRERA Gurugram
226404-02-202140800ICICIHRERA Gurugram
326504-02-202120250ICICIHRERA Gurugram
451077317-08-2020182500ICICIHRERA Gurugram







1.222 (Acre)
175
210
13.344 (Acre)
53 of 2011 dated 10.06.2011
Yes







16659.1 Lakhs
4023.1 Lakhs
8382.9 Lakhs
667.5 Lakhs
3585.6 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD 0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0.212
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0.168
5PARKS AND PLAYGROUNDS 0.821
6GREEN BELTS 0
7VEHICLE PARKINGS 0.02
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 0
12ANY OTHER 0
13RAIN WAATER 0.001
Total1.222




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSGMDA/HSVPYes
WATER SUPPLYGMDA/HSVPYes
ELECTRICITYDHVBNYes
SEWAGE DISPOSALGMDA/HSVPYes
STORM WATER DRAINAGEGMDA/HSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS149.28SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM37.49SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE6.9SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM9.56SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL13.94SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING19.12SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING93.6SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS14.34SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15PARKING3.57SUBMITTED TO TOWN & COUNTRY PLANNING
16RAIN WATER4.78SUBMITTED TO TOWN & COUNTRY PLANNING
17ELECTRICAL SUB STATION314.92SUBMITTED TO TOWN & COUNTRY PLANNING


11-12-2020 (date)
11-12-2020 (date)
15-02-2021
31-01-2026
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 0 0
Total0


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings16609.3451341





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0
Land620.6

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3583.5368.1606
Shops0000
Plots0000
Others517.96115.96203.57121.81
Land1129.1

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments422318.5381.3407.5
Shops0000
Plots0000
Others214.6086.46232.49151.50

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments525.5543.7498534.8
Shops0000
Plots0000
Others238.99124.58244.42135.36

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments569.5624.1516.30371.30
Shops0000
Plots0000
Others235.84135.36201.83123.8

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments368.8392313.9317.30
Shops0000
Plots0000
Others123.8092.3982.1091.02

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments125.700
Shops000
Plots000
Land2273.4
Others111.630




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Security and Firefighting1.00

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0003.00
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage1.001.001.000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and Firefighting0.500.500.500.50

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System3.006.0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage000.500.70
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000
Security and Firefighting0.500.500.50
Electrical Sub station40.00
Security Firefighting2.50

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements20.0020.0034.1340.00
Water Supply System6.007.007.495.00
Sewerage treatment & garbage disposal04.005.004.94
Electricity Supply System03.003.002.56
Storm Water Drainage1.000.700.500.50
Parks and Playgrounds03.002.344.00
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light2.004.005.004.12
Electrical Sub station40.0050.0061.43
Security Firefighting15.0015.0020.0025.29
Parking1.001.001.00
Rain Water1.001.781.00
Electrical Sub Station50.00

ParticularsYear-2026
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements35.15
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System1.00
Storm Water Drainage0
Parks and Playgrounds5.00
Clubhouse/community centres0
Shopping area0
Other0
Parking0.57
Rain Water1.00
Street Light4.00
Security Firefighting11.31
Electrical Sub Station73.49












Yes
No
ICICI BANK LIMITED, SECTOR 54, SUNCITY, GURUGRAM
777705992020
ICIC0000399
110229060
ICICINBBCTS
Vyom Shakti Nigam D-103/3 Paras City E-3 Arera Colony Huzur Bhopal Madhya Pradesh- 462016
Yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENCEALREADY BEEN OBTAINED10-06-2011
II. ZONINGALREADY BEEN OBTAINED14-06-2011
III. BUILDING PLAN APPROVALALREADY BEEN OBTAINED15-07-2020
IV. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED04-11-2020
V. AIRPORT HEIGHTALREADY BEEN OBTAINED06-08-2019
VI. FOREST NOCALREADY BEEN OBTAINED30-12-2011
VII. ARAVALIALREADY BEEN OBTAINED12-11-2012
VIII. BUILDING PLAN APPROVAL (REVISED)ALREADY BEEN OBTAINED11-12-2020








Yes


Yes


AS PER HRERA NORMS













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEMARBLE/ WOODEN FLOORING / ANTI-SKID TILES
2WALL FINISHING DETAILSPLASTER WITH PAINT
3KITCHEN DETAILSPLASTER WITH PAINT, COUNTER TOP WITH SINK AND STANDARD CP FITTINGS
4BATHROOM FITTINGSSTANDARD CHINAWARE, CP FITTINGS, WITH/ WITHOUT WASH BASIN COUNTER
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKALUMINIUM/ UPVC FRAME SHUTTER WITH GLASS
8ELECTRIC FITTINGSALL COMMON AREAS TO BE PROVIDED WITH LED LIGHT FIXTURES. TOILETS & BALCONY OF THE FLAT ARE PROVIDED WITH LED LIGHT FIXTURE.
9CONDUCTING AND WIRING DETAILSISI APPROVED FR CONDUITS & WIRES
10CUPBOARD DETAILSNA
11WATER STORAGER.C.C COMMON TANK
12LIFT DETAILSOTIS/SCHINDLER OR EQUIVALENT
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSUPVC /POWDER COATED ALUMINIUM WINDOWS AND FRAMES
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGSPLIT AC UNITS OR ABOVE
16ELECTRICAL FITTINGSALL COMMON AREAS TO BE PROVIDED WITH LED LIGHT FIXTURES. TOILETS & BALCONY OF THE FLAT ARE PROVIDED WITH LED LIGHT FIXTURE LED LIGHT FIXTURES
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYOPTIC FIBRE OR EQUIVALENT.
19EXTERNAL FINISHING/COLOUR SCHEMEDURABLE EXTERIOR GRADE PAINT
20INTERNAL FINISHINGPLASTER WITH PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORMARBLE/ WOODEN FLOORING / ANTI-SKID TILES
1 . 2 WALLSPAINT FINISH
1 . 3 CEILINGPAINT FINISH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORWOODEN FLOORING/ ANTI- SKID TILES
2 . 2 WALLSPAINT FINISH
2 . 3 CEILINGPAINT FINISH
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORANTI-SKID TILES
3 . 2 WALLSTILES/PAINT
3 . 3 CEILINGPAINT FINISH/FALSE CEILING
3 . 4 COUNTERSWITH/ WITHOUT WASH BASIN COUNTER
3 . 5 SANITARY WARE/CP FITTINGSSTANDARD MAKE CHINAWARE & CP FITTINGS
3 . 6 FITTING/FIXTURESSTANDARD MAKE FITTING /FIXTURES
4 . BED ROOMS
4 . 1 FLOORWOODEN FLOORING/ ANTI- SKID TILES
4 . 2 WALLSPAINT FINISH
4 . 3 CEILINGPAINT FINISH
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORANTI-SKID TILES
5 . 2 WALLSTILES /PAINT
5 . 3 CEILINGPAINT FINISH/FALSE CEILING
5 . 4 COUNTERSWITH/ WITHOUT WASH BASIN COUNTER
5 . 5 SANITARY WARE/CP FITTINGSSTANDARD MAKE CHINAWARE & CP FITTINGS
5 . 6 FIXTURESSTANDARD MAKE FITTING /FIXTURES
6 . KITCHEN
6 . 1 FLOORANTI-SKID TILES
6 . 2 WALLSTILES UP TO 2 FEET ABOVE THE COUNTER AND PLASTER WITH PAINT
6 . 3 CEILINGPAINT FINISH
6 . 4 COUNTERSSTONE TOP COUNTER
6 . 5 FIXTURESSINK AND CP FITTINGS OF STANDARD MAKE & MODEL
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORANTI-SKID TILES
7 . 2 WALLS & CEILINGPAINT WITH/WITHOUT PLASTER
7 . 3 TOILETWALLS: TILES FLOOR: TILES CEILING: PAINT
7 . 4 BALCONYWALLS: EXTERNAL PAINT FLOOR: ANTI-SKID TILES CEILING: DURABLE EXTERIOR GRADE PAINT
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 05-02-2021 View Document
2 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 05-02-2021 View Document
3 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 05-02-2021 View Document
4 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 05-02-2021 View Document
5 DEMARCATION PLAN 05-02-2021 View Document
6 A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS 05-02-2021 View Document
7 ZONING PLAN 05-02-2021 View Document
8 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 05-02-2021 View Document
9 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 05-02-2021 View Document
10 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 05-02-2021 View Document
11 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 05-02-2021 View Document
12 AIRPORT HEIGHT 05-02-2021 View Document
13 FOREST 05-02-2021 View Document
14 SERVICES PLANS 05-02-2021 View Document
15 LOI 05-02-2021 View Document
16 FIRE SCHEME 05-02-2021 View Document
17 LC -IV 05-02-2021 View Document
18 BUILDING PLAN APPROVAL REVISED 05-02-2021 View Document
19 IN PRINCIPAL APPROVAL 05-02-2021 View Document
20 BANK ACCOUNT KYC 05-02-2021 View Document
21 SPE RECEIVING 05-02-2021 View Document
22 BOARD RESOLUTION 05-02-2021 View Document
23 DEMAND DRAFT 05-02-2021 View Document
24 NEC 05-02-2021 View Document
25 ELEVATION 05-02-2021 View Document
26 BASEMENT 05-02-2021 View Document
27 EWS PLAN 05-02-2021 View Document
28 PERT CHART 05-02-2021 View Document
29 SECTION PLAN 05-02-2021 View Document
30 TERRACE FLOOR 05-02-2021 View Document