PARK 81
SECTOR 81 FARIDABAD
FARIDABAD
FARIDABAD
01149572787
8800414400 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
VINOD KUMAR
01149572787
8800414400 (Number Shared by Promoter in Public)
rera.panchkula@bptp.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
19402
22-11-2018
2250000
AXIS BANK LIMITED
HRERA Panchkula
19.49 (Acre)
1
1
109.721 (Acre)
License no 495-521 of 2006 , 1172-1177 of 2006 and 73 of 2011
No
Address OT-14, 3RD FLOOR, NEXT DOOR PARKLANDS, SECTOR-76 FARIDABD FARIDABAD HR 121004 IN
Address OT-15, 3RD FLOOR, NEXT DOOR, PARKLANDS, SECTOR-76 FARIDABAD FARIDABAD HR 121004 IN
Address OT-16, 3RD FLOOR, NEXT DOOR, U-BLOCK, BPTP PARKLANDS, SECTOR-76 FARIDABAD FARIDABAD HR 121004 IN
Address OT-15, 3RD FLOOR, NEXT DOOR, PARKLANDS, SECTOR-76 FARIDABAD FARIDABAD HR 121004 IN
Address OT-14, 3RD FLOOR, NEXT DOOR, PARKLANDS, SECTOR-75 FARIDABAD FARIDABAD HR 121004 IN
Annexure-B- AS A PROMOTER.
ON THE BASIS OF COLLABORATION AGREEMENT BETWEEN LANDOWNER AND PROMOTERS
No
AS MENTIONED IN THE COLLABORATION AGREEMENT
Yes
No
Yes
6510.66 Lakhs
1418.81 Lakhs
0 Lakhs
1559.20 Lakhs
3532.65 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
1.268
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
8.49
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0.108
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
9.624
Total
19.49
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
No
ELECTRICITY
DHBVN
No
SEWAGE DISPOSAL
HSVP
No
STORM WATER DRAINAGE
HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
679.2
YET TO BE PREPARED
2
WATER SUPPLY SYSTEM
0
YET TO BE PREPARED
3
STORM WATER DRAINAGE
0
YET TO BE PREPARED
4
ELECTRICITY SUPPLY SYSTEM
0
YET TO BE PREPARED
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
YET TO BE PREPARED
6
STREET LIGHTING
0
YET TO BE PREPARED
7
SECURITY AND FIRE FIGHTING
0
YET TO BE PREPARED
8
PLAYGROUNDS AND PARKS
8.64
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
343.52
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
0
YET TO BE PREPARED
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
527.84
YET TO BE PREPARED
15-01-2021 (date)
15-01-2021 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type PLOTS
221.3
1
0
1
0
2
PLOT Type PLOTS
224.73
4
0
4
0
3
PLOT Type PLOTS
229.51
14
0
14
0
4
PLOT Type EWS
50
16
0
16
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
NA
01-01-2021
31-03-2025
31-03-2025
01-01-2021
45
31-03-2025
AS MENTIONED.
THE SAME HAS NOT BEE LAUNCHED YET.
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
THE SAME HAS NOT BEE LAUNCHED YET.
01-01-2021
45
31-03-2025
AS MENTIONED.
THE SAME HAS NOT BEE LAUNCHED YET.
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
30
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
2
Clubhouse/community centres
0
Shopping area
25
Other
25
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
25
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
14
Other
14
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
35
out of 35 16 plots are EWS.
ii. No. of Flats/ Apartments booked
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
4931.05 Lakhs
Land cost (If any)
1418.81 Lakhs
Apartments
0 Lakhs
Infrastructure
483.04 Lakhs
EDC/ Taxes Etc.
3029.20 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
1579.61 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
1579.61 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
165 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
503 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
679.2
271.68
II. WATER SUPPLY SYSTEM
0
0
III. STORM WATER DRAINAGE
0
0
IV. ELECTRICITY SUPPLY SYSTEM
0
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
0
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
871.36
211.36
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
8.64
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
No
BARAKHAMBA ROAD GOPAL DASS BHAWAN
250000818102
INDB0000005
110234002
000005
Account would be operated by jointly any two out of the following signatories
1. Mr. Manik Malik
Add: D-2/2406, Vasant Kunj, Delhi-110070
2. Mr. Rakesh Kumar Agrawal
Add: D-308, Narwana Apartment, 89 IP Extension, Patparganj, New Delhi-110092
3. Mr. Amit Kumar Singhal
Add: E-3/28, Nand Nagri, Mandoli, North-East Delhi-110093
4. Mr. Sanjeev Lok Nath Agrawal
Add: Flat no 32, Sudershan Apartment IP Extension, New Delhi- 110092
As attached.
Yes
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENSE NO 495 - 521 OF 2006
ALREADY BEEN OBTAINED
28-02-2006
II. RENEWAL OF LICENSE NO 495 - 521 OF 2006
ALREADY BEEN OBTAINED
31-12-2019
III. LICENSE NO 1172- 1177 OF 2006
ALREADY BEEN OBTAINED
22-09-2006
IV. RENEWAL OF LICENSE NO 1172- 1177 OF 2006
ALREADY BEEN OBTAINED
31-12-2019
V. LICENSE NO 73 OF 2011
ALREADY BEEN OBTAINED
09-08-2011
VI. ELECTRICAL LOAD APPROVAL LETTER
ALREADY BEEN OBTAINED
10-10-2011
VII. FOREST NOC
ALREADY BEEN OBTAINED
06-07-2016
VIII. RAIN WATER HARVESTING
ALREADY BEEN OBTAINED
22-11-2007
IX. ENVIRONMENTAL CLEARANCE
ALREADY BEEN OBTAINED
31-12-2012
X. APPROVAL OF REVISED LAYOUT
ALREADY BEEN OBTAINED
15-01-2021
Yes
Yes
As attached.
PHASE-I, PLOTS, SECTOR-81 (EDEN ESTATE)
15.12
0
168
0
163
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
3183.00
3471.30
3830.49
Cost of the apartments
0
0
0
Cost of the infrastructure
1001.00
3000.00
847.46
Others costs
440.00
471.30
2983.03
12910 Lakhs
4577 Lakhs
2000 Lakhs
1720 Lakhs
No
08-10-2018
31-12-2020
BPTP DISTRICT 1 BLOCK B
10.056
0
189
0
60
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
3657
0
1234.27
Cost of the apartments
0
0
0
Cost of the infrastructure
1453.00
0
109.36
Others costs
2204.60
0
1124.91
1938.70 Lakhs
2704.48 Lakhs
1430.00 Lakhs
1230.00 Lakhs
No
06-08-2019
01-08-2024
BPTP DISTRICT 1 BLOCK A
12.373
0
220
0
110
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
4504.39
0
1644.65
Cost of the apartments
0
0
0
Cost of the infrastructure
1786.00
0
88.43
Others costs
2718.39
0
1556.22
2527.04 Lakhs
4760.71 Lakhs
1757 Lakhs
1511 Lakhs
No
01-08-2019
29-07-2024
BPTP DISTRICT 1 BLOCK C
12.72
0
244
0
68
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
4640
0
1929.53
Cost of the apartments
0
0
0
Cost of the infrastructure
1838.00
0
498.88
Others costs
2802.11
0
1430.65
1385 Lakhs
4391 Lakhs
1809 Lakhs
1556 Lakhs
No
20-08-2019
18-08-2024
102 EDEN ESTATE
28.67
45
235
36
48
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
21082.43
0
19000.65
Cost of the apartments
0
0
0
Cost of the infrastructure
4278.5
0
2587
Others costs
16803.93
0
16413.65
91674.41 Lakhs
17173.38 Lakhs
11500 Lakhs
11500 Lakhs
Yes
01-10-2020
30-04-2024
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: