JOYVILLE SHAPOORJI HOUSING PRIVATE LIMITED
UNIT NO 1201, WING B, 12TH FLOOR, GODREJ COLISEUM, SION, MUMBAI, 400022
02243560001
9811215950 (Number Shared by Promoter in Public)
vineet.saluja@shapoorji.com
https://www.joyvillehomes.com/
XXXX800E
U70109MH2007PTC166942
JOYVILLE GURUGRAM PHASE VI
KHERKI MAJRA, SECTOR 102, GURUGRAM
GURGAON
GURUGRAM
02267490000
8750056295 (Number Shared by Promoter in Public)
vineet.saluja@shapoorji.com
VINEET SALUJA
9136047722
9136047722 (Number Shared by Promoter in Public)
vineet.saluja@shapoorji.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
438
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
139
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
114
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
0
SUBMITTED TO TOWN & COUNTRY PLANNING
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
289
SUBMITTED TO TOWN & COUNTRY PLANNING
6
STREET LIGHTING
69
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
324
SUBMITTED TO TOWN & COUNTRY PLANNING
8
PLAYGROUNDS AND PARKS
10
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO TOWN & COUNTRY PLANNING
10
SHOPPING AREA
0
SUBMITTED TO TOWN & COUNTRY PLANNING
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO TOWN & COUNTRY PLANNING
12
SCHOOL
0
SUBMITTED TO TOWN & COUNTRY PLANNING
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO TOWN & COUNTRY PLANNING
14
ANY OTHER
590
SUBMITTED TO TOWN & COUNTRY PLANNING
12-11-2018 (date)
12-11-2018 (date)
02-01-2021
31-07-2025
Plot Area(In Square Meter)
Number of plots in the project
0
0
Type
Carpet area(In Square Meter)
Number of apartments
Number of towers
Apartment/Shops/Other Buildings
36301
404
4
Apartment/Shops/Other Buildings
724.16
32
1
Apartment/Shops/Other Buildings
3697.232
1
1
Apartment/Shops/Other Buildings
808.583
1
1
Apartment/Shops/Other Buildings
683.335
1
1
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Construction Cost
7
EDC
1770
Infrastructure Development Charges
310
Land Cost
6625
Other Cost
347
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
644
717
755
471
Construction Cost
609
795
1076
1301
EDC
272
258
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
494
460
415
472
Construction Cost
1500
1331
948
1437
Loan Repayment
1100
1100
EDC
245
232
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Loan Repayment
1100
1100
1100
1100
Other Cost
617
617
563
563
Construction Cost
1606
1472
1315
1367
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Other Cost
563
500
628
711
Construction Cost
1050
781
652
525
Loan Repayment
1100
1100
85
Particulars
Year-2025
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
Shops
0
0
0
Plots
0
0
0
Construction Cost
462
476
276
Other Cost
493
893
647
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (2025)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Yes
No
INDUSIND BANK, ATLANTA BUILDING, NARIMAN POINT, MUMBAI-400021
251220010012
INDB0000006
400234004
000006
Himanshu Jani, Address: B-102, White Aarch,Hathuradas Road, Kandivali West, Near Vanja Wadi, Mumbai
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. FIRE SCHEME APPROVAL
ALREADY BEEN OBTAINED
05-03-2019
II. ZONING PLAN
ALREADY BEEN OBTAINED
15-02-2018
III. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
20-08-2018
IV. BUILDING PLAN
ALREADY BEEN OBTAINED
12-11-2018
V. SERVICE PLAN ESTIMATES APPROVAL
ALREADY BEEN OBTAINED
04-02-2019
VI. NATURAL CONSERVATION ZONE NOC
ALREADY BEEN OBTAINED
01-10-2018
VII. FOREST NOC
APPLIED FOR BUT YET TO RECEIVE
23-04-2018
Yes
Yes
JOYVILLE VIRAR
7.61
0
0
0
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
0
0
0
Cost of the apartments
0
0
0
Cost of the infrastructure
0
0
0
Others costs
0
0
0
0 Lakhs
0 Lakhs
0 Lakhs
0 Lakhs
No
01-01-2020
01-01-2021
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
CERAMIC/VITRIFIED/WOODEN LAMINATED FLOORING
2
WALL FINISHING DETAILS
OIL BOUND DISTEMPER/ACRYLIC PAINT
3
KITCHEN DETAILS
GRANITE PLATFORM WITH SINK
4
BATHROOM FITTINGS
STANDARD QUALITY CP FITTINGS
5
WOOD WORK ETC
NA
6
DOORS AND WINDOS FRAMES
HARD WOOD/ENGINEERED WOOD/ALUMINIUM/STONE
7
GLASS WORK
CLEAR/FROSTED
8
ELECTRIC FITTINGS
STANDARD SWITCHES AND SOCKETS
9
CONDUCTING AND WIRING DETAILS
DIA 20MM TO 32MM
10
CUPBOARD DETAILS
NA
11
WATER STORAGE
RCC UNDERGROUND/OVERHEAD TANKS FOR TOWERS
12
LIFT DETAILS
PASSENGER AND FIRE LIFTS
13
EXTERNAL GLAZINGS
ALUMINIUM/UPVC
13.1
WINDOWS/GLAZINGS
-
14
DOORS
-
14.1
MAIN DOORS
WOODEN FLUSH DOORS/ENGINEERED WOOD
14.2
INTERNAL DOORS
WOODEN FLUSH DOORS
15
AIR CONDITIONING
SPLIT AC
16
ELECTRICAL FITTINGS
STANDARD SWITCHES AND SOCKETS
17
CNG PIPE LINE
NA
18
PROVISION OF WIFI AND BROADBAND FACILITY
AS PER SERVICE PROVIDER
19
EXTERNAL FINISHING/COLOUR SCHEME
TEXTURE PAINT/EXTERNAL GRADE PAINT
20
INTERNAL FINISHING
-
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
VITRIFIED TILES
1 . 2
WALLS
OIL BOUND DISTEMPER/ACRYLIC PAINT
1 . 3
CEILING
OIL BOUND DISTEMPER/ACRYLIC PAINT
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
VITRIFIED/WOODEN LAMINATED
2 . 2
WALLS
OIL BOUND DISTEMPER/ACRYLIC PAINT
2 . 3
CEILING
OIL BOUND DISTEMPER/ACRYLIC PAINT
2 . 4
MODULAR WARDROBES
NA
3 . MASTER TOILET
3 . 1
FLOOR
CERAMIC/VITRIFIED TILES
3 . 2
WALLS
CERAMIC/VITRIFIED TILE DADO TILL DOOR HEIGHT
3 . 3
CEILING
FALSE CEILING
3 . 4
COUNTERS
NA
3 . 5
SANITARY WARE/CP FITTINGS
STANDARD QUALITY CP FITTINGS & SANITARY FITTINGS
3 . 6
FITTING/FIXTURES
STANDARD QUALITY CP FITTINGS & SANITARY FITTINGS
4 . BED ROOMS
4 . 1
FLOOR
VITRIFIED/WOODEN LAMINATED
4 . 2
WALLS
OIL BOUND DISTEMPER/ACRYLIC PAINT
4 . 3
CEILING
OIL BOUND DISTEMPER/ACRYLIC PAINT
4 . 4
WARDROBES
NA
5 . TOILET
5 . 1
FLOOR
CERAMIC/VITRIFIED TILES
5 . 2
WALLS
CERAMIC/VITRIFIED TILE DADO TILL DOOR HEIGHT
5 . 3
CEILING
FALSE CEILING
5 . 4
COUNTERS
NA
5 . 5
SANITARY WARE/CP FITTINGS
STANDARD QUALITY CP FITTINGS & SANITARY FITTINGS
5 . 6
FIXTURES
STANDARD QUALITY CP FITTINGS & SANITARY FITTINGS
6 . KITCHEN
6 . 1
FLOOR
VITRIFIED TILES
6 . 2
WALLS
CERAMIC/VITRIFIED TILE DADO TWO FEET ABOVE KITCHEN PLATFORM