HRERA GurugramTemp Project Id : RERA-GRG-PROJ-749-2020
Submission Date : 22-09-2020 01:24:14 AM
Applicant Type : Company
Project Type: NEW




CZAR BUILDWELL PVT. LTD.
302A , GLOBAL FOYER MALL , GOLF COURSE ROAD , SECTOR 43
01244892366
8448202000 (Number Shared by Promoter in Public)
kumarprince793@gmail.com
https://www.mahirahomes.com/
XXXX381K
U45209HR2012PTC047239
 
 


 
 


 
 







MAHIRA HOMES 95
VILL. DHORKA, SUB- TEHSIL KADIPUR
GURGAON
GURUGRAM
01244892366
8448202000 (Number Shared by Promoter in Public)
INFO@MAHIRAGROUP.COM
PRINCE KUMAR
01244892366
8448202040 (Number Shared by Promoter in Public)
PRINCE.KUMAR@MAHIRAGROUP.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
11012-09-2020250000AXIS BANKHRERA Gurugram
21119-09-2020600000AXIS BANKHRERA Gurugram
31603-10-20201114056AXIS BANKHRERA Gurugram







6.05 (Acre)
2.25
2.2498
6.05 (Acre)
24 of 2020
No
Address     C-40 PREET VIHAR, EAST DELHI, 110092
Annexure-B- ANNEXURE-B-4322 DATED- 22.03.2018
YES, SHARING OF REVENUE-60 LANDOWNER, 40 DEVELOPER
Yes
4322, DATED 22.03.2018
No
Yes
Yes







19391.65 Lakhs
5570.96 Lakhs
10197.73 Lakhs
1684.60 Lakhs
1938.36 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS3736.08
3CONSTRUCTION OF ROADS4442.406
4PAVEMENTS4388.801
5PARKS AND PLAYGROUNDS4215.728
6GREEN BELTS1659
7VEHICLE PARKINGS2303
8ELECTRICITY SUB-STATION100
9CLUB HOUSE234.542
10SEWAGE AND SOLID WASTE TREATMENT FACILITY780
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER2624.171
Total24483.728




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALL READY CONNECTED-24MTR.No
WATER SUPPLYAPPLIEDNo
ELECTRICITYAPPLIEDNo
SEWAGE DISPOSALNOC (04801)Yes
STORM WATER DRAINAGENOC (3091)Yes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS215.58YET TO BE PREPARED
2WATER SUPPLY SYSTEM188.37YET TO BE PREPARED
3STORM WATER DRAINAGE23.00YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM150.70YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL135.34YET TO BE PREPARED
6STREET LIGHTING86.78YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING50.66YET TO BE PREPARED
8PLAYGROUNDS AND PARKS95.07YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE200YET TO BE PREPARED
10SHOPPING AREA24YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM140.23YET TO BE PREPARED
12SCHOOL0.00YET TO BE PREPARED
13HOSPITAL/DISPENSARY0.00YET TO BE PREPARED
14ANY OTHER16.19YET TO BE PREPARED
15PARKING120.98YET TO BE PREPARED
16STP100.00YET TO BE PREPARED
17RAIN WATER HARVESTING35.70YET TO BE PREPARED
18UNDERGROUND WATER TANK100.00YET TO BE PREPARED


10-09-2020 (date)
18-09-2020 (date)
01-12-2020
17-09-2025
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings48673.1888769
Apartment/Shops/Other Buildings985.711573





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments5
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments3010
Shops00
Plots00

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments590201890.50684
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments950400400400
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments200400382205.50
Shops400250268200
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments400350350370
Shops550150150180
Plots0000

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments200
Shops631.73
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements50
Water Supply System00
Sewerage treatment & garbage disposal00
Electricity Supply System00
Storm Water Drainage00
Parks and Playgrounds08
Clubhouse/community centres00
Shopping area00
Other00

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements105108
Water Supply System4254
Sewerage treatment & garbage disposal2123
Electricity Supply System1212
Storm Water Drainage0010
Parks and Playgrounds1510
Clubhouse/community centres1240
Shopping area0020
Other2112423

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12121212
Water Supply System107710
Sewerage treatment & garbage disposal1571015
Electricity Supply System8555
Storm Water Drainage103810
Parks and Playgrounds8406
Clubhouse/community centres108810
Shopping area2222
Other7122812

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15121215
Water Supply System15101015
Sewerage treatment & garbage disposal20202020
Electricity Supply System1581010
Storm Water Drainage12101010
Parks and Playgrounds12089
Clubhouse/community centres11151511
Shopping area0220
Other0330

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15151515
Water Supply System20151515
Sewerage treatment & garbage disposal25202325
Electricity Supply System14151818
Storm Water Drainage12121212
Parks and Playgrounds1201012
Clubhouse/community centres40202535
Shopping area5005
Other73213

ParticularsYear-2025
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.580
Water Supply System24.370
Sewerage treatment & garbage disposal300
Electricity Supply System15.700
Storm Water Drainage13.700
Parks and Playgrounds12.070
Clubhouse/community centres31.190
Shopping area00
Other18.800












Yes
No
AXIS BANK, PATEL NAGAR, OLD MG ROAD, GURGAON, HARYANA
920020064094114
UTIB0004658
110211330
4658
Mr. Sikandar Singh
ATTACHED











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. FOREST NOCALREADY BEEN OBTAINED23-12-2019
II. ZONING PLAN APPROVALALREADY BEEN OBTAINED11-09-2020
III. BUILDING PLAN APPROVALALREADY BEEN OBTAINED18-09-2020
IV. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED31-08-2020
V. LICENSE ALREADY BEEN OBTAINED10-09-2020
VI. FIRE SCHEME APPROVALAPPLIED FOR BUT YET TO RECEIVE09-09-2020
VII. ENVIRONMENT CLEARANCEAPPLIED FOR BUT YET TO RECEIVE27-07-2020
VIII. SERVICE PLAN ESTIMATESAPPLIED FOR BUT YET TO RECEIVE22-09-2020








Yes


Yes


ANNEX A COPY IN FOLDER F







MAHIRA HOMES 63A
4.98
640
0
640
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
92099209505
Cost of the apartments5810581095
Cost of the infrastructure1603160310
Others costs17961796400


0 Lakhs
15117.77 Lakhs
0 Lakhs
0 Lakhs
No
24-11-2024
30-09-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILE/ CERAMIC TILE/ IPS FLOORING
2WALL FINISHING DETAILSOIL BOND DISTEMPER / COLOR WASH
3KITCHEN DETAILSVITRIFIED TILE/CERAMIC TILE, OIL BOND DISTEMPER
4BATHROOM FITTINGSC.P. FITTING
5WOOD WORK ETCFLUSH DOOR
6DOORS AND WINDOS FRAMESALUMINIUM / MS Z SECTION / HARD WOOD
7GLASS WORKFLOAT GLASS
8ELECTRIC FITTINGSISI MARKED
9CONDUCTING AND WIRING DETAILSCOPPER/ALUMINIUM WIRE
10CUPBOARD DETAILSCOLOUR WASH
11WATER STORAGERCC OVERHEAD AND UNDERGROUND TANK
12LIFT DETAILS2 NOS LIFT PER TOWER
13EXTERNAL GLAZINGSALUMINIUM / MS Z SECTION
13.1WINDOWS/GLAZINGSALUMINIUM / MS Z SECTION
14DOORSWOOD / ALUMINIUM / MS Z SECTION
14.1MAIN DOORSWOOD / ALUMINIUM
14.2INTERNAL DOORSHARD WOOD FLUSH DOOR / MS Z
15AIR CONDITIONINGN/A
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINEN/A
18PROVISION OF WIFI AND BROADBAND FACILITYYES
19EXTERNAL FINISHING/COLOUR SCHEMEEXTERNAL TEXTURE / CEMEN PAINT
20INTERNAL FINISHINGOIL BOND DISTAMPER / COLOUR WASH / TILE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILE / IPS FLOORING
1 . 2 WALLSOIL BOND DISTAMPER / COLOUR WASH
1 . 3 CEILINGOIL BOND DISTAMPER / COLOUR WASH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILE / IPS FLOORING
2 . 2 WALLSOIL BOND DISTAMPER / COLOUR WASH
2 . 3 CEILINGOIL BOND DISTAMPER / COLOUR WASH
2 . 4 MODULAR WARDROBESN/A
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILE
3 . 2 WALLSCERAMIC TILE / COLOUR WASH
3 . 3 CEILINGOIL BOND DISTAMPER / COLOUR WASH
3 . 4 COUNTERSMARBLE/GRANITE
3 . 5 SANITARY WARE/CP FITTINGSBIS APPROVED BRAND
3 . 6 FITTING/FIXTURESVITRIFIED TILE / IPS FLOORING
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILE / IPS FLOORING
4 . 2 WALLSOIL BOND DISTAMPER / COLOUR WASH
4 . 3 CEILINGOIL BOND DISTAMPER / COLOUR WASH
4 . 4 WARDROBESWOODEN
5 . TOILET
5 . 1 FLOORCERAMIC TILE / VITRIFIED TILE
5 . 2 WALLSCERAMIC TILE / OIL BOND DISTAMPER
5 . 3 CEILINGOIL BOND DISTAMPER / COLOUR WASH
5 . 4 COUNTERSGRANITE MARBLE
5 . 5 SANITARY WARE/CP FITTINGSISI MARK STANDARD FITTINGS
5 . 6 FIXTURESISI MARK STANDARD FITTINGS
6 . KITCHEN
6 . 1 FLOORCERAMIC TILE / VITRIFIED TILE
6 . 2 WALLSTILES UPTO 2 FEET HEIGHT ABOVE COUNTER AND OIL BOND DISTAMPER / COLOUR WAS IN BALANCE AREA
6 . 3 CEILINGOIL BOND DISTAMPER / COLOUR WASH
6 . 4 COUNTERSGRANITE/ MARBLE
6 . 5 FIXTURESISI MARK STANDARD FITTINGS
6 . 6 KITCHEN APPLIANCESISI MARK STANDARD FITTINGS
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILE / VITRIFIED TILE
7 . 2 WALLS & CEILINGOIL BOND DISTAMPER / COLOUR WASH
7 . 3 TOILETISI MARK STANDARD FITTINGS
7 . 4 BALCONYCERAMIC TILE / VITRIFIED TILE
8 . SIT-OUTS
8 . 1 FLOORCERAMIC TILE / VITRIFIED TILE
8 . 2 WALLS & CEILINGOIL BOND DISTAMPER / COLOUR WASH
8 . 3 RAILINGSMS RAILINGS
8 . 4 FIXTURESISI MARK STANDARD FITTINGS












Sr. No.Document DescriptionDate of Document UploadView Document
1SERVICES PLAN 08-10-2009-10-2020 ------
2STP TREATED WATER09-10-2020 ------
3WATER SUPPLY APPLIED09-10-2020 ------
4ZONING PLAN09-10-2020 View Document
5FIRE NOC09-10-2020 ------
6NON-ENCUMBRANCE CERTIFICATE09-10-2020 ------
7SPA09-10-2020 ------
8TERRACE PLAN 5, 6 CZAR 95-1209-10-2020 ------
9SITE PLAN CZAR 95-109-10-2020 ------
10SECTION PLAN T1, T2,T3 CZAR 95-609-10-2020 ------
11FLOOR PLAN COMM 1 CZAR 95-1509-10-2020 ------
12CASH FLOW STATEMENT OF THE PROPOSED PROJECT22-09-2020 View Document
13NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT22-09-2020 View Document
14CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT22-09-2020 View Document
15A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS22-09-2020 View Document
16DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD22-09-2020 View Document
17SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN22-09-2020 View Document
18DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.22-09-2020 View Document
19IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN22-09-2020 View Document
20COPY OF LICENSE ALONG WITH SCHEDULE OF LAND22-09-2020 View Document
21IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN22-09-2020 View Document
22FOREST NOC09-10-2020 ------
23JAMABANDI09-10-2020 ------
24SEWERAGE NOC APPLIED09-10-2020 ------
25FLOOR PLAN T4, T7, T8, T9, TCZAR 95-809-10-2020 ------
26BUILDING PLAN SERVICE PLAN09-10-2020 ------
27CA CERTIFICATES CZAR09-10-2020 ------
28SECTION 4,7,8,9, CZAR 95-909-10-2020 ------
29LANDSCAPE PLAN CZAR 95-209-10-2020 ------
30AFFADAVIT09-10-2020 ------
31FLOOR PLAN COMM 3 CZAR 95-1709-10-2020 ------
32SUPERIMPOSED SITE PLAN09-10-2020 ------
33ENVIRONMENT CLEARANCE APPLIED09-10-2020 ------
34SERIVCE PLAN APPLIED09-10-2020 ------
35DEMARCATION PLAN09-10-2020 View Document
36ELEVATION 4,7,8,9, CZAR 95-1009-10-2020 ------
37LICENSE CZAR 9509-10-2020 ------
38FLOOR PLAN 5,6 CZAR 95-1109-10-2020 ------
39SECTIONS 5,6 CZAR 95-1309-10-2020 ------
40ELECTRICITY NOC APPLIED09-10-2020 ------
41FLOOR PLAN COMM2 AND COMMUNITY CZAR 95-1609-10-2020 ------
42ELEVATION 1,2,3 CZAR 95-709-10-2020 ------
43PARKING PLAN CZAR 95-309-10-2020 ------
44BASEMENT PLAN CZAR 95-409-10-2020 ------
45BANK UNDERTAKING09-10-2020 ------
46FLOOR PLAN T1, T2, T3, CZAR 95-509-10-2020 ------
47ELEVATION 5, 6, CZAR 95-1409-10-2020 ------
48BR FOR BANK09-10-2020 ------
49BR III14-10-2020 ------
50BRIII09-10-2020 ------
51DEMARACTION PLAN LETTER09-10-2020 ------
52GPA09-10-2020 ------
53SERVICE ESTAMATED PLAN APPLIED COPY09-10-2020 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 Project Registration Revoked 03-06-2024 View Document