HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-866-2020
Submission Date : 15-09-2020 10:28:14 PM
Applicant Type : Company
Project Type: NEW




GODREJ PROPERTIES LIMITED
3RD FLOOR UM HOUSE SECTOR 22 GURUGRAM
01244956150
1244956150 (Number Shared by Promoter in Public)
ho_rera@godrejproperties.com
http://www.godrejproperties.com
XXXX995M
L74120MH1985PLC035308
 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 


 
 







GODREJ RETREAT VIBE
SECTOR 83
FARIDABAD
FARIDABAD
2261698888
2261698888 (Number Shared by Promoter in Public)
ho_rera@godrejproperties.com
ROHIT SANTOSH
2261698888
2261698888 (Number Shared by Promoter in Public)
ho_rera@godrejproperties.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150104603-09-2020380608HDFC HRERA Panchkula







7.494 (Acre)
Plotted development with FAR of 2 on plots
2
7.806 (Acre)
79 of 2019(29-07-2024)
Yes







6127 Lakhs
3818 Lakhs
0 Lakhs
699 Lakhs
1610 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD4.547
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS1.50
4PAVEMENTS0.17
5PARKS AND PLAYGROUNDS0.585
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.021
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.025
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.781
12ANY OTHER0
Total7.629




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS84YET TO BE PREPARED
2WATER SUPPLY SYSTEM9YET TO BE PREPARED
3STORM WATER DRAINAGE80YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM163YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL39YET TO BE PREPARED
6STREET LIGHTING20YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS33YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER270YET TO BE PREPARED


23-07-2019 (date)
NA (date)
10-09-2020
30-09-2022
Plot Area(In Square Meter)Number of plots in the project
87.104
101.531
106.371
109.3410
112.1535
120.829
123.936
128.514
132.241
133.321
134.411
135.501
136.621
137.741
138.831
139.911
140.531
141.001
144.156
147.421
149.452
150.0052


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0
Street lighting0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.23.515.7
Water Supply System1.30.41.7
Sewerage treatment & garbage disposal5.61.67.2
Electricity Supply System23.76.830.5
Storm Water Drainage11.63.314.9
Parks and Playgrounds16.6016.6
Clubhouse/community centres000
Shopping area000
Other27.512.640.1
Street lighting2.90.83.8

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements7.814.310.79.7
Water Supply System0.81.51.11.0
Sewerage treatment & garbage disposal3.66.54.94.5
Electricity Supply System15.227.620.618.8
Storm Water Drainage7.413.510.19.2
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other28.251.438.435.0
Street lighting1.93.42.62.3

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements06.14.2
Water Supply System00.70.5
Sewerage treatment & garbage disposal02.81.9
Electricity Supply System011.88.2
Storm Water Drainage05.84.0
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other022.015.2
Street lighting01.51.0












Yes
No
AXIS BANK, DLF STAR TOWER, STS 25 & 45 SECTOR 30, GURGAON -122002
920020002280151
UTIB0003622
110211230
3622
Sandeep Somani, 3rd Floor UM House Sector 22 Gurugram











Yes
No
Yes
No
No
No
No
No
No
No


No
Yes
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LOIALREADY BEEN OBTAINED21-02-2019
II. LAYOUT PLANALREADY BEEN OBTAINED23-07-2019
III. LICENCE NO. 79 OF 2019ALREADY BEEN OBTAINED30-07-2019
IV. FOREST NOCALREADY BEEN OBTAINED26-06-2020
V. CONSENT TO ESTABLISH (CTE)ALREADY BEEN OBTAINED05-07-2020
VI. TRANSFER OF LICENCEALREADY BEEN OBTAINED28-08-2020
VII. APPROVAL OF ZONING PLANALREADY BEEN OBTAINED07-09-2020








Yes


Yes


Agreement will be executed between the Promoter and the Allottee







GODREJ HABITAT, SECTOR 3
7.46875
384
0
222
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
42400424007925.89
Cost of the apartments18300183001161.59
Cost of the infrastructure250025007.76
Others costs11500115006756.54


5370.62 Lakhs
17658.00 Lakhs
0 Lakhs
0 Lakhs
Yes
25-02-2023
25-02-2023










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1CONSENT TO ESTABLISH (CTE)06-08-2020 ------
2COPY OF LICENSE ALONG WITH SCHEDULE OF LAND05-08-2020 View Document
3LETTER OF INTENT (LOI)05-08-2020 ------
4FOREST NOC06-08-2020 ------
5IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN05-08-2020 View Document
6ZONING PLAN10-09-2020 View Document
7MOM AND AOA14-09-2020 ------
8NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT01-09-2020 View Document
9AUDITED FINANCIAL 19-2015-09-2020 ------
10AUDITED FINANCIALS 16-1701-09-2020 ------
11AUDITED FINANCIALS 17-1801-09-2020 ------
12AUDITED FINANCIALS 18-1901-09-2020 ------
13DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.15-09-2020 View Document
14ORDER FOR TRANSFER OF LICENCE07-09-2020 ------
15APPROVAL OF ZONING PLAN10-09-2020 ------
16SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN10-09-2020 View Document
17IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN10-09-2020 View Document
18CASH FLOW STATEMENT OF THE PROPOSED PROJECT15-09-2020 View Document
19SALE DEED14-09-2020 ------