HRERA GurugramTemp Project Id : RERA-GRG-PROJ-665-2020
Submission Date : 18-03-2020 06:59:55 PM
Applicant Type : Company
Project Type: ONGOING




ST PATRICKS REALTY PVT LTD
TOWER-D, 3RD FLOOR, GLOBAL BUSINESS PARK, M.G ROAD, GURGAON, GURGAON, HARYANA, 122002
01244107050
9871474655 (Number Shared by Promoter in Public)
tarun.juneja@centralpark.in
https://www.centralpark.in
XXXX877J
U45200HR2008PTC037964
 
 


 
 


 
 







CENTRAL PARK FLOWER VALLEY
SECTOR 29, 30, 32 & 33, SOHNA, DIST GURUGRAM
SOHNA
GURUGRAM
01244107050
9871474655 (Number Shared by Promoter in Public)
tarun.juneja@centralpark.in
TARUN DEEP JUNEJA
01244107050
9871474655 (Number Shared by Promoter in Public)
tarun.juneja@centralpark.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1007-03-2020HRERA Gurugram







148.6833 (Acre)
0
0
148.6833 (Acre)
54 of 2014 (19-06-2024), 28 of 2016 (22-12-2021), 07 of 2020 (28-01-2025)
Yes







120233.80 Lakhs
8276.03 Lakhs
26802.55 Lakhs
13519.14 Lakhs
71636.08 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD55.69
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS14.11
3CONSTRUCTION OF ROADS20.67
4PAVEMENTS20.67
5PARKS AND PLAYGROUNDS11.665
6GREEN BELTS7.146
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.47
9CLUB HOUSE2
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.63
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER3.52
13COMMERCIAL4.11
14COMMUNITY6.45
15UNDETERMINED1.552
Total148.683




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSNo
WATER SUPPLYNo
ELECTRICITYNo
SEWAGE DISPOSALNo
STORM WATER DRAINAGENo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS1157AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM567AS PER PROJECT REPORT
3STORM WATER DRAINAGE324AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM1736AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL463AS PER PROJECT REPORT
6STREET LIGHTING174AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING23AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS694AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE1500AS PER PROJECT REPORT
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM25AS PER PROJECT REPORT
12SCHOOL3476AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY1509AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT


13-12-2019 (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1PLOT Type BLOCK A0419110
2PLOT Type BLOCK B0301820
3PLOT Type BLOCK C01155480
4PLOT Type BLOCK D01767510
5PLOT Type BLOCK E0158000
6PLOT Type BLOCK F020750120
7PLOT Type BLOCK G010546580
8PLOT Type BLOCK H0480480
9PLOT Type BLOCK I010401040
10PLOT Type BLOCK J01030600
11PLOT Type BLOCK K0620240






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
FLAMINGO FLOORS563STRUCTURE & PLASTER DONE, FLOORING & FINISHING IN PROGRESS
CERISE FLOOR139SUPERSTRUCTURE NEARING COMPLETION
CLOVER FLOORS12STRUCTURE IN PROGRESS
FLEUR VILLAS61STRUCTURE, PLASTER AND FLOORING DONE, FINISHING IN PROGRESS


01-08-2014
31-07-2022
31-12-2024
01-08-2014
47
31-12-2024


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT252LEVELING AND DEMARCATION DONE, SEWERAGE, DRAINAGE AND ELECTRIFICATION WORK IN PROGRESS
01-08-2014
47
31-12-2024


0
482
0
709
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments11282.76
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments922.03910.12890.63850.30
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1269.011269.011269.011269.01
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments888.84888.84888.84888.84
Shops0000
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments1113.591113.59543.93543.93
Shops0000
Plots0000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements534
Water Supply System285
Sewerage treatment & garbage disposal191
Electricity Supply System519
Storm Water Drainage232
Parks and Playgrounds559
Clubhouse/community centres495
Shopping area0
Other764

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.7218.7218.7218.72
Water Supply System8.468.468.468.46
Sewerage treatment & garbage disposal3.983.983.983.98
Electricity Supply System36.5336.5336.5336.53
Storm Water Drainage6.926.926.926.92
Parks and Playgrounds4.064.064.064.06
Clubhouse/community centres62.8162.8162.8162.81
Shopping area0000
Other26.9126.9126.9126.91

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements18.7231.1931.1931.19
Water Supply System8.4614.1014.1014.10
Sewerage treatment & garbage disposal3.986.646.646.64
Electricity Supply System36.5360.8860.8860.88
Storm Water Drainage6.9211.5311.5311.53
Parks and Playgrounds4.066.776.776.77
Clubhouse/community centres62.8162.8161.8162.81
Shopping area0000
Other26.9144.8544.8544.85

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements31.1931.1962.3862.38
Water Supply System14.1014.1028.1928.19
Sewerage treatment & garbage disposal6.646.6413.2813.28
Electricity Supply System60.8860.88121.76121.76
Storm Water Drainage11.5311.5323.0523.05
Parks and Playgrounds6.776.7713.5513.55
Clubhouse/community centres62.8162.8162.8162.81
Shopping area0000
Other44.8544.8589.7089.70

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements62.3862.3831.1931.19
Water Supply System28.1928.1914.1014.10
Sewerage treatment & garbage disposal13.2813.286.646.64
Electricity Supply System121.76121.7660.8860.88
Storm Water Drainage23.0523.0511.5311.53
Parks and Playgrounds13.5513.556.676.77
Clubhouse/community centres62.8162.8162.8162.81
Shopping area0000
Other89.7089.7044.8544.85

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.6015.6015.6015.60
Water Supply System7.057.057.057.05
Sewerage treatment & garbage disposal3.323.323.323.32
Electricity Supply System30.4430.4430.4430.44
Storm Water Drainage5.765.765.765.76
Parks and Playgrounds3.393.393.393.39
Clubhouse/community centres0000
Shopping area0000
Other22.4222.4222.4222.42












Particulars Remarks, if any
i. No. of Flats/Apartments constructed2057Including Plots & Builtup units
ii. No. of Flats/ Apartments booked1027Plots & Builtup units
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter108266 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter41378 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter66888 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter6082 Lakhs
vii. Amount invested in the project upto the date of application53181 Lakhs
Land cost (If any)11474 Lakhs
Apartments11283 Lakhs
Infrastructure3084 Lakhs
EDC/ Taxes Etc.3399 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession67052 Lakhs
(a) In respect of existing allottees45357 Lakhs
(b) In respect of rest of the project21695 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
12000 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 175 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS1157534
II. WATER SUPPLY SYSTEM567285
III. STORM WATER DRAINAGE463232
IV. ELECTRICITY SUPPLY SYSTEM1736519
V. SEWAGE TREATMENT & GARBAGE DISPOSAL324191
VI. CLUB HOUSE/COMMUNITY CENTRE1500495
VII. SCHOOL32980
VIII. ANY OTHER00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.694559
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM2310
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
ICICI BANK. SOLITAIRE PLAZA, M. G ROAD, GURGAON-122002
002105023530
ICIC0000021
110229003
000021
Neeraj Dhawan
Yes











Yes
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
No
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. FOREST AND ARAVALI NOCALREADY BEEN OBTAINEDNA
II. LAYOUT APPROVALALREADY BEEN OBTAINEDNA
III. BUILTUP BUILDING PLANSALREADY BEEN OBTAINEDNA
IV. LICENSE ALREADY BEEN OBTAINEDNA
V. ENVIRONMENTAL APPROVALAPPLIED FOR BUT YET TO RECEIVENA
VI. DEMARCATION & ZONINGAPPLIED FOR BUT YET TO RECEIVENA
VII. SERVICE PLAN ESTIMATESAPPLIED FOR BUT YET TO RECEIVENA








Yes


Yes









CENTRAL PARK RESORTS, SEC 48, GURUGRAM
47.418
2441
0
1840
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
388028388028258772
Cost of the apartments213335213335162242
Cost of the infrastructure184511845114032
Others costs15624215624282498


212690 Lakhs
5979 Lakhs
37500 Lakhs
32500 Lakhs
Yes
24-05-2016
31-08-2024










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEFOR FLAMINGO FLOORS: VITRIFIED TILES, LAMINATED WOODEN, CERAMIC
2WALL FINISHING DETAILSPLASTIC PAINT, CERAMIC TILES
3KITCHEN DETAILSTILES ON WALL 2 FT ABOVE KITCHEN COUNTER
4BATHROOM FITTINGSJAGUAR OR EQUIVALENT
5WOOD WORK ETCAS PER DESIGN
6DOORS AND WINDOS FRAMESUPVC
7GLASS WORKAS PER DESIGN
8ELECTRIC FITTINGSMODULAR SWITCHES & SOCKETS OF REPUTED MAKE
9CONDUCTING AND WIRING DETAILSAS PER DESIGN
10CUPBOARD DETAILSLAMINATED WARDROBE
11WATER STORAGEAS PER NBC
12LIFT DETAILSNA
13EXTERNAL GLAZINGSUPVC FRAMES WITH 5 MM THICK GLASS
13.1WINDOWS/GLAZINGSUPVC FRAMES WITH 5 MM THICK GLASS
14DOORSFLUSH DOOR
14.1MAIN DOORSFLUSH DOOR
14.2INTERNAL DOORSFLUSH DOOR
15AIR CONDITIONINGSPLIT
16ELECTRICAL FITTINGSMODULAR SWITCHES & SOCKETS OF REPUTED MAKE
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEAS PER DESIGN
20INTERNAL FINISHINGAS PER DRAWING
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSPLASTIC PAINT
1 . 3 CEILINGOBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSPLASTIC PAINT
2 . 3 CEILINGOBD
2 . 4 MODULAR WARDROBESLAMINATED WARDROBES
3 . MASTER TOILET
3 . 1 FLOORANTI SKID CERAMIC TILES
3 . 2 WALLSCERAMIC TILES
3 . 3 CEILINGOBD
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSJAGUAR OR EQUIVALENT
3 . 6 FITTING/FIXTURESJAGUAR OR EQUIVALENT
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSPLASTIC PAINT
4 . 3 CEILINGOBD
4 . 4 WARDROBESPARTICLE BOARD/MDF CARCASS WITH LAMINATED MDF PARTICLE BOARD SHUTTERS
5 . TOILET
5 . 1 FLOORANTI SKID CERAMIC TILES
5 . 2 WALLSCERAMIC TILES
5 . 3 CEILINGOBD
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSJAGUAR OR EQUIVALENT
5 . 6 FIXTURESJAGUAR OR EQUIVALENT
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSTILES ON WALL 2 FT ABOVE KITCHEN COUNTER
6 . 3 CEILINGOBD
6 . 4 COUNTERSGRANITE COUNTER
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND18-03-2020 View Document
2A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS18-03-2020 View Document
3NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT18-03-2020 View Document
4CASH FLOW STATEMENT OF THE PROPOSED PROJECT18-03-2020 View Document
5DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.18-03-2020 View Document
6DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD18-03-2020 View Document
7CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT18-03-2020 View Document
8IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN18-03-2020 View Document
9SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN18-03-2020 View Document
10IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN18-03-2020 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 PROJECT CONTINUATION- RC/REP/HARERA/GGM/150 of 2017/7(3)/34/2023/11 DATED 17.04.2023 12-05-2023 View Document