9729870009 (Number Shared by Promoter in Public)
info@bestcityindia.com
http://www.bestcityindia.com
XXXX789G
U74899DL2005PTC142999
GULMOHAR CITY (PHASE-3)
VILLAGE SHERGARH AND PATTI GAADAR, SECTOR-29, KAITHAL
KAITHAL
KAITHAL
9588559717 (Number Shared by Promoter in Public)
info@bestcityindia.com
SAMEER BASSI
9588559717 (Number Shared by Promoter in Public)
info@bestcityindia.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
639
23-08-2017
704000
AXIS BANK
HRERA Panchkula
31.038 (Acre)
2
2
77.699 (Acre)
89 of 2008 and 05 of 2011
Yes
3146 Lakhs
0 Lakhs
0 Lakhs
1456 Lakhs
1690 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
60498
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
42225
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
22888
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
125611
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA
Yes
WATER SUPPLY
HUDA
Yes
ELECTRICITY
UHBVN
No
SEWAGE DISPOSAL
HUDA
No
STORM WATER DRAINAGE
HUDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
357
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
196
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
70.72
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
0
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
0
AS PER PROJECT REPORT
6
STREET LIGHTING
166.40
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
0
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
83.20
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
17-01-2012 (date)
17-01-2012 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
PLOT Type TYPE-A
420
10
0
10
0
2
PLOT Type TYPE-A
293.75
36
0
36
0
3
PLOT Type TYPE-A
250
63
0
63
0
4
PLOT Type TYPE-A
209
51
0
51
0
5
PLOT Type TYPE-A
166.50
116
0
116
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
N/A
N/A
N/A
01-04-2016
95
31-03-2021
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-04-2016
95
31-03-2021
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
250
Water Supply System
196
Sewerage treatment & garbage disposal
64.40
Electricity Supply System
450
Storm Water Drainage
70.72
Parks and Playgrounds
83.20
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter ()
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
276
ii. No. of Flats/ Apartments booked
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
0 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
0 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
0 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
0 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
0 Lakhs
Apartments
0 Lakhs
Infrastructure
664.32 Lakhs
EDC/ Taxes Etc.
169 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
0 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
557 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
357
250
II. WATER SUPPLY SYSTEM
196
196
III. STORM WATER DRAINAGE
70.72
70.72
IV. ELECTRICITY SUPPLY SYSTEM
450
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
64.40
64.40
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
No
AXIS BANK LTD MATAK MAJRI, KARNAL 132041
912020041608830
UTIB0002211
13221106
002211
Dinesh Gupta
Enclosed
Yes
Yes
Yes
No
Yes
No
No
No
No
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LAYOUT PLAN ALREADY BEEN OBTAINED DATED 17.01.2012
ALREADY BEEN OBTAINED
17-01-2012
Yes
Yes
Annexure Folder F-3
SPECIFICATION OF CONSTRUCTION