9654128130 (Number Shared by Promoter in Public)
info@suncityprojects.com
https://www.suncityprojects.com
XXXX757R
U74899DL1989PTC034878
RESIDENTIAL GROUP HOUSING COLONY
SECTOR 36A ROHTAK
ROHTAK
ROHTAK
8814000152
8814000152 (Number Shared by Promoter in Public)
info@suncitypreojects.com
MANOJ KUMAR
8814000152
8814000152 (Number Shared by Promoter in Public)
manojkumar@suncityprojects.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
531804
31-07-2017
100000
ICICI
HRERA Panchkula
1371.346 (Sqr/mtrs)
19694
175
14.813 (Sqr/mtrs)
65 of 2010 dated 21.08.2010
Yes
5712 Lakhs
1149 Lakhs
3200 Lakhs
0 Lakhs
1363 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1371.346
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
1371.346
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP
No
WATER SUPPLY
HSVP
Yes
ELECTRICITY
HVPNL
Yes
SEWAGE DISPOSAL
HSVP
Yes
STORM WATER DRAINAGE
HSVP
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
62.79
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
54.28
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
25.22
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
141
SUBMITTED TO TOWN & COUNTRY PLANNING
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
37.15
SUBMITTED TO TOWN & COUNTRY PLANNING
6
STREET LIGHTING
10.72
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
0
SUBMITTED TO TOWN & COUNTRY PLANNING
8
PLAYGROUNDS AND PARKS
10.34
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO TOWN & COUNTRY PLANNING
10
SHOPPING AREA
0
SUBMITTED TO TOWN & COUNTRY PLANNING
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO TOWN & COUNTRY PLANNING
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
05-03-2015 (date)
05-03-2015 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type 1175 SQFT
0
4
0
4
2
2
APARTMENT/SHOPS/OTHER BUILDINGS Type 1250 SQFT
0
116
44
72
2
3
APARTMENT/SHOPS/OTHER BUILDINGS Type 1532 SQFT
0
60
25
35
2
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
1175 SQFT
0
TOWER T 7 COMPLETED
1250 SQFT
21
TOWER T 7 COMPLETED
1532 SQFT
9
TOWER T 7 COMPLETED
1250 SQFT
23
TOWER T 9 COMPLETED
1532 SQFT
16
TOWER T 9 COMPLETED
1175 SQFT
0
TOWER T 9 COMPLETED
06-03-2015
20-08-2020
20-08-2020
06-03-2015
100
20-08-2020
ATTACHED
ATTACHED
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
06-03-2015
100
20-08-2020
180
0
180
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
3200
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
0
0
0
0
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
17.61
Water Supply System
51.29
Sewerage treatment & garbage disposal
51.29
Electricity Supply System
145.55
Storm Water Drainage
19.35
Parks and Playgrounds
11
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (2018)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
180
Tower T 7 & Tower T 9
ii. No. of Flats/ Apartments booked
69
Tower T 7 & Tower T 9
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
2038 Lakhs
On Date of Application
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
1273 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
765 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
765 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
1149 Lakhs
Apartments
3200 Lakhs
Infrastructure
0 Lakhs
EDC/ Taxes Etc.
1363 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
50 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
0 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
1577 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
743 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
62.79
17.61
II. WATER SUPPLY SYSTEM
54.28
51.29
III. STORM WATER DRAINAGE
25.22
19.35
IV. ELECTRICITY SUPPLY SYSTEM
141
145.55
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
37.15
51.29
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
10.34
11
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
0
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
0
0
Yes
No
ICICI BANK LTD, 9A, PHELPS BUILDING, CONNAUGHT PLACE DELHI 110001
777705226009
ICIC0000007
110229002
0000007
Ankit Goel,
Suncity Business Tower, 2nd Floor, Sector - 54,
Golf Course Road,Gurgaon-122002, Haryana, India
Attached
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
12-07-2013
II. OCCUPATION CERTIFICATE
ALREADY BEEN OBTAINED
24-01-2019
Yes
Yes
Attached
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
VITRIFIED TILES -BROCHURE ATTACHED
2
WALL FINISHING DETAILS
PAINT / DAO ABOVE COUNTER IN WASH ROOM-BROCHURE ATTACHED
3
KITCHEN DETAILS
PAINT / DAO ABOVE COUNTER -*BROCHURE ATTACHED
4
BATHROOM FITTINGS
BROCHURE ATTACHED
5
WOOD WORK ETC
NO
6
DOORS AND WINDOS FRAMES
TYPICAL PLAN ATTACHED
DOOR SIZES : 1100X2100, 750X2100, 900X2100 , WINDOW SIZES : 600X900
CROME PLATTED FITTINGS SANITARY WARE IN WHITE COLOR
3 . 6
FITTING/FIXTURES
CROME PLATTED FITTINGS
4 . BED ROOMS
4 . 1
FLOOR
VITRIFIED TILES
4 . 2
WALLS
PLASTER WITH OBD PAINT
4 . 3
CEILING
PLASTER WITH OBD PAINT
4 . 4
WARDROBES
NIL
5 . TOILET
5 . 1
FLOOR
VITRIFIED TILES
5 . 2
WALLS
CERAMIC TILES UPTO 7 INCH
5 . 3
CEILING
PLASTER WITH OBD PAINT
5 . 4
COUNTERS
NIL
5 . 5
SANITARY WARE/CP FITTINGS
CROME PLATTED FITTINGS SANITARY WARE IN WHITE COLOR
5 . 6
FIXTURES
CROME PLATTED FITTINGS
6 . KITCHEN
6 . 1
FLOOR
CERAMIC /VITRIFIED TILES
6 . 2
WALLS
PAINT / DAO 2 FEET ABOVE COUNTER
6 . 3
CEILING
PAINT / OBD
6 . 4
COUNTERS
GRANITE
6 . 5
FIXTURES
STAINLESS STEEL SINK
6 . 6
KITCHEN APPLIANCES
NIL
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
CERAMIC TILE
7 . 2
WALLS & CEILING
MS GRILL
7 . 3
TOILET
X
7 . 4
BALCONY
X
8 . SIT-OUTS
8 . 1
FLOOR
X
8 . 2
WALLS & CEILING
X
8 . 3
RAILINGS
X
8 . 4
FIXTURES
X
Sr. No.
Document Description
Date of Document Upload
View Document
1