HRERA GurugramTemp Project Id : RERA-GRG-PROJ-613-2020
Submission Date : 04-02-2020 05:39:30 AM
Applicant Type : Company
Project Type: ONGOING




EMAAR MGF LAND LIMITED
EMAAR BUSINESS PARK, SIKANDERPUR SECTOR-28, GURUGRAM, HARYANA 122001
1244421155
1244421155 (Number Shared by Promoter in Public)
coordination@emaar-india.com
http://www.emaar-india.com/
XXXX308B
U45201DL2005PLC133161
 
 


 
 


 
 







IMPERIAL GARDENS PHASE-I
SECTOR 102
GURGAON
GURUGRAM
1244421155
9743999521 (Number Shared by Promoter in Public)
coordination@emaar-india.com
DEEPAK JAIN
1244421155
9560404126 (Number Shared by Promoter in Public)
Deepak.Jain@Emaar-India.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
195853511-07-20172063987HDFCHRERA Gurugram
260394507-07-2017485623HDFCHRERA Gurugram







7.43 (Acre)
175
174.705
12 (Acre)
107 of 2012
No
Address     306-308, SQUARE ONE, C2, DISTRICT CENTER, SAKET, NEW DELHI-110017
Annexure-B- AS COLLABORATOR
BY VIRTUE OF A COLLABORATION AGREEMENT
No
THE OWNER SHALL BE ENTITLED TO RETAIN SUCH PORTION OF THE REVENUE AS IS EQUIVALENT TO (A) THE COST OF THE LAND AND PERCENTAGE(ONE PERCENT) MARK UP ON THE COST OF LAND OR (B) THE CIRCLE RATE AS APPLICABLE TO THE STATE OR (C) RS 25000 PER ACRE WHICHEVER IS LOWER, AS CONSIDERATION IN RESPECT OF THE RIGHTS ASSIGNED TO THE DEVELOPER FOR DEVELOPMENT OF THE PROJECT WHICH SHALL BECAME PAYABLE AS AND WHEN THE REVENUE IS RECOGNIZED BY THE DEVELOPER IN RESPECT OF SUCH LAND.
No
Yes
Yes







31695 Lakhs
1103 Lakhs
21592 Lakhs
2811 Lakhs
6189 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.70
3CONSTRUCTION OF ROADS2.46
4PAVEMENTS0
5PARKS AND PLAYGROUNDS3.01
6GREEN BELTS0
7VEHICLE PARKINGS1.11
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0.15
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total7.43




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSALREADY CONNECTEDYes
WATER SUPPLYGMDAYes
ELECTRICITYDHBVNYes
SEWAGE DISPOSALGMDAYes
STORM WATER DRAINAGEGMDAYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS254.32SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM50.73SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE80.24SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM496.05SUBMITTED TO TOWN & COUNTRY PLANNING
5SEWAGE TREATMENT & GARBAGE DISPOSAL44.27SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING18.4SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING69.16SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS429.90SUBMITTED TO TOWN & COUNTRY PLANNING
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM14.05SUBMITTED TO TOWN & COUNTRY PLANNING
12SCHOOL44.58SUBMITTED TO TOWN & COUNTRY PLANNING
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED
15UG TANK46.34SUBMITTED TO TOWN & COUNTRY PLANNING
16STP39.70SUBMITTED TO TOWN & COUNTRY PLANNING
17RAINWATER HARVESTING29.84SUBMITTED TO TOWN & COUNTRY PLANNING
18PARKING1212SUBMITTED TO TOWN & COUNTRY PLANNING


26-02-2013 (date)
26-02-2013 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - D(T3) , ( 3BHK )116.66585801
2APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - C2(T4) , ( 3BHK )116.66373431
3APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - C2(T4) , ( 3BHK )114.1373341
4APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - C1(T5) , ( 3BHK )116.66373701
5APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - C1(T5) , ( 3BHK )114.1373611
6APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - B1(T6) , ( 3BHK )116.66353411
7APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - B1(T6) , ( 3BHK )114.1353321
8APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - B2(T7) , ( 3BHK )116.66343311
9APARTMENT/SHOPS/OTHER BUILDINGS Type TOWER - B2(T7) , ( 3BHK )114.1353321






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
3 BHK-116.66197COMPLETED AND OC RECEIVED
3 BHK-114.1137COMPLETED AND OC RECEIVED
3 BHK-114.1137COMPLETED AND OC RECEIVED


01-10-2013
31-12-2018
31-12-2019
01-10-2013
100
31-12-2019
COMPLETED


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
01-10-2013
100
31-12-2019


549
180
0
141
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments21592
Shops0
Plots0
Land Cost1103
Other Cost including EDC IDC and Taxes6189

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements254.32
Water Supply System50.73
Sewerage treatment & garbage disposal44.27
Electricity Supply System496.05
Storm Water Drainage80.24
Parks and Playgrounds429.90
Clubhouse/community centres0
Shopping area0
Other0
Parking1211.98
Rain Water Harvesting29.84
Renewable energy14.05
School44.58
Security and Fire Fighting69.16
Solid Waste Collection and Management System39.70
UG Tank46.34

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0












Particulars Remarks, if any
i. No. of Flats/Apartments constructed345OC Received
ii. No. of Flats/ Apartments booked334OC Received
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter45357 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter37742 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter7615 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter1496 Lakhs
vii. Amount invested in the project upto the date of application29519 Lakhs
Land cost (If any)1103 Lakhs
Apartments19835 Lakhs
Infrastructure2674 Lakhs
EDC/ Taxes Etc.5906 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession2176 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project2176 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS254.32236.93
II. WATER SUPPLY SYSTEM50.7338.31
III. STORM WATER DRAINAGE80.2460.96
IV. ELECTRICITY SUPPLY SYSTEM496.05449.05
V. SEWAGE TREATMENT & GARBAGE DISPOSAL44.2731.13
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL44.5844.58
VIII. ANY OTHER46.3439.73
IX. SOLID WASTE COLLECTION & MGMT SYSTEM39.7035.63
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.429.90421.63
XIII. COVERED PARKING1211.981211.98
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM69.1660.18
XVII. OTHER FACILITIES AS PER PROJECT REPORT43.8943.89









Yes
No
MASTER ACCOUNT- HSBC BANK, BARAKHAMBA ROAD
051504181985
HSBC0110002
110039002
110002
Rahul Bindle, Address: 306-308, SQUARE ONE, C2, DISTRICT CENTRE SAKET, NEW DELHI- 110017
Yes











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE 107 OF 2012ALREADY BEEN OBTAINED10-10-2012
II. LOIALREADY BEEN OBTAINED30-12-2011
III. AIRPORT HEIGHT CLEARANCEALREADY BEEN OBTAINED08-02-2013
IV. FIRE SCHEME APPROVALALREADY BEEN OBTAINED25-10-2013
V. SERVICE PLAN ESTIMATEALREADY BEEN OBTAINED24-03-2014
VI. BUILDING PLANALREADY BEEN OBTAINED26-02-2013
VII. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED06-09-2013
VIII. FIRE NOCALREADY BEEN OBTAINED30-05-2019
IX. OCCUPATION CERTIFICATEALREADY BEEN OBTAINED17-10-2019








Yes


Yes


Within 60 (sixty) days from the date of issuance of Occupancy Certificate by the concerned Authorities, the company shall offer the possession of the unit to the Allottee







PALM HEIGHTS, SECTOR 77, GURUGRAM
5.50
297
0
148
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
20000200005548
Cost of the apartments18143181434156
Cost of the infrastructure000
Others costs185718571392


1615 Lakhs
14821 Lakhs
0 Lakhs
2464 Lakhs
Yes
31-08-2022
31-08-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES / LAMINATED WOODEN FLOORING / CERAMIC TILE
2WALL FINISHING DETAILSACRYLIC EMULSION / OIL BOUND DISTEMPER / DRY DISTEMPER
3KITCHEN DETAILSMODULAR
4BATHROOM FITTINGSSTANDARDE CHINAWARE & CP FITTINGS
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESSEASONED HARDWOOD FRAME / UPVC
7GLASS WORKNA
8ELECTRIC FITTINGSMODULAR SWITCHES
9CONDUCTING AND WIRING DETAILSPVC CONDUITS AND FRLS WIRING
10CUPBOARD DETAILSNA
11WATER STORAGEUNDER GROUND AND OVER HEAD WATER TANK
12LIFT DETAILSPROVIDED
13EXTERNAL GLAZINGSUPVC
13.1WINDOWS/GLAZINGSUPVC
14DOORSUPVC ( EXTERIOR )
14.1MAIN DOORSHARDWOOD FRAME WITH POLISHED HARDWOOD DOOR
14.2INTERNAL DOORSHARDWOOD FRAME WITH PAINTED FLUSH SHUTTER
15AIR CONDITIONINGSPLIT AC ( LIVING / DINING / BED ROOMS )
16ELECTRICAL FITTINGSMODULAR SWITCHES
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEWEATHER PROOF PAINT / TEXTURE PAINT
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSACRYLIC EMULSION
1 . 3 CEILINGACRYLIC EMULSION
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOORING
2 . 2 WALLSACRYLIC EMULSION
2 . 3 CEILINGACRYLIC EMULSION
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORVITRIFIED TILES
3 . 2 WALLSCOMBINATION OF CERAMIC TILES & ACRYLIC EMULSION
3 . 3 CEILINGACRYLIC EMULSION
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSSTANDARDE CHINAWARE & CP FITTINGS
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOORING
4 . 2 WALLSACRYLIC EMULSION
4 . 3 CEILINGACRYLIC EMULSION
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORVITRIFIED TILES
5 . 2 WALLSCOMBINATION OF CERAMIC TILES & ACRYLIC EMULSION
5 . 3 CEILINGACRYLIC EMULSION
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSSTANDARDE CHINAWARE & CP FITTINGS
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSCOMBINATION OF CERAMIC TILES & ACRYLIC EMULSION
6 . 3 CEILINGACRYLIC EMULSION
6 . 4 COUNTERSGRANITE COUNTER TOP
6 . 5 FIXTURESSATINLESS STEEL SINGLE DRAIN BOARD SINK
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGDRY DISTEMPER
7 . 3 TOILETNA
7 . 4 BALCONYANTI SKID TILES
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1EC-IMPERIAL GARDEN02-03-2020 ------
2FIRE SCHEME APPROVAL02-03-2020 ------
3BBA02-03-2020 ------
4BR-III FOR 12 ACRES02-03-2020 ------
5AAI NOC02-03-2020 ------
6IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN02-03-2020 View Document
7FIRE NOC IG02-03-2020 ------
8NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT02-03-2020 View Document
9DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.02-03-2020 View Document
10IMPERIAL GARDENS (12 ACRES)- NEC02-03-2020 ------
11LC-IV & BILATERAL AGREEMENT 12 ACRES02-03-2020 ------
12LICENSE MERGED02-03-2020 ------
13NOC AAI 12.0 ACRES02-03-2020 ------
14LOI 12.0 AC GH02-03-2020 ------
15SPE APPROVAL02-03-2020 ------
16SUPERIMPOSED SITE PLAN10-07-2020 ------
17DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD10-07-2020 View Document
18BOARD RESOLUTION FOR OPERATING BANK ACCOUNTS10-07-2020 ------
19CASH FLOW STATEMENT OF THE PROPOSED PROJECT10-07-2020 View Document
20CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT10-07-2020 View Document
21ANNUAL REPORT 2017-1804-02-2020 ------
22COPY OF LICENSE ALONG WITH SCHEDULE OF LAND04-02-2020 View Document
23ANNUAL REPORT 2016-1704-02-2020 ------
24IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN04-02-2020 View Document
25ANNUAL REPORT 2018-1904-02-2020 ------












Sr. No.Document DescriptionDate of Document UploadView Document
1 Extension No. 03 of 2019 DATED: 02.08.2019 30-05-2020 View Document
2 OC uploaded 08-08-2023 View Document
3 OC uploaded 08-08-2023 View Document
4 OC uploaded 08-08-2023 View Document
5 OC uploaded 08-08-2023 View Document