HRERA GurugramTemp Project Id : RERA-GRG-PROJ-604-2020
Submission Date : 12-02-2020 05:53:09 AM
Applicant Type : Company
Project Type: ONGOING




MARTIAL BUILDCON PVT. LTD. M3M INDIA PVT. LTD.
CABIN 2, OFFICE NO. 1221 A, DEVIKA TOWER, 12TH FLOOR, 6, NEHRU PLACE, NEW DELHI 110019
01244732000
9319843320 (Number Shared by Promoter in Public)
martialbuildcon65@gmail.com
http://martialbuildcon.com
XXXX226L
U45400DL2007PTC170267
 
 


 
 


 
 


 
 







M3M URBANA PREMIUM
SECTOR-67, GURUGRAM
BADSHAHPUR ST
GURUGRAM
01244732000
9643185145 (Number Shared by Promoter in Public)
martialbuildcon65@gmail.com
SANDEEP GUPTA
01244732000
9643185145 (Number Shared by Promoter in Public)
martialbuildcon65@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1481831-07-2017433800AXIS BANK HRERA Gurugram







2.9125 (Acre)
21688
184
2.9125 (Acre)
89 of 2010 dated 27.10.2010
Yes







24128.35 Lakhs
2903.00 Lakhs
9127.00 Lakhs
4198.25 Lakhs
7900.00 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS1.17
3CONSTRUCTION OF ROADS0.687
4PAVEMENTS0.436
5PARKS AND PLAYGROUNDS0
6GREEN BELTS0.258
7VEHICLE PARKINGS0.195
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.165
12ANY OTHER0
13RAIN WATER HARVESTING0.002
Total2.913




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVP/ GMDA No
WATER SUPPLYHSVP/ GMDA No
ELECTRICITYDHBVNL Yes
SEWAGE DISPOSALHSVP/ GMDA No
STORM WATER DRAINAGEHSVP/ GMDA No




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS168.16AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM170.35AS PER PROJECT REPORT
3STORM WATER DRAINAGE16.03AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM234.19AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL0AS PER PROJECT REPORT
6STREET LIGHTING54.31AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING383.97AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS0AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM65.06AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER1893.62AS PER PROJECT REPORT
15PARKING276.73AS PER PROJECT REPORT
16STP29.34AS PER PROJECT REPORT
17UNDERGROUND WATER TANK27.07AS PER PROJECT REPORT
18RAIN WATER HARVESTING6.20AS PER PROJECT REPORT
19ELECTRICAL SUB STATION873.22AS PER PROJECT REPORT


NA (date)
NA (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type RETAIL FOOD COURT/KIOSK MULTIPLEX OFFICES11548257208491






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
RETAIL FOOD COURT/KIOSK MULTIPLEX OFFICES208TOWER – STRUCTURE COMPLETE. FINISHING UNDER PROGRESS


23-11-2016
28-02-2024
28-02-2024
23-11-2016
16.19
28-02-2024


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
23-11-2016
16.19
28-02-2024


739
12
0
63
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops6004.19
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops81
Plots0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops247281239266
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops179158156152
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops184191191191
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0000
Shops1911918675
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops64
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements33
Water Supply System57.85
Sewerage treatment & garbage disposal0
Electricity Supply System37.55
Storm Water Drainage1.32
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other270
Electric sub tation85
Parking5
Rain Water Harvesting0
Renewable Energy4
Security Fire Fighting167
STP0
Street Light10
Underground water tank9

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0
Water Supply System2.65
Sewerage treatment & garbage disposal0
Electricity Supply System50.73
Storm Water Drainage2.95
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0.8
UGT0.23
Electrical Sub Station0.06
Security and Fire Fighting12.14
Street Lighting4.84

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements6.736.738.418.41
Water Supply System5.115.115.115.11
Sewerage treatment & garbage disposal0000
Electricity Supply System23.4211.7111.7111.71
Storm Water Drainage0.80.80.80.8
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other75.7475.7475.7494.68
Rain Water Harvesting0.310.370.430.5
Renewable energy3.93.9
Electric sub tation43.6652.3952.3952.39
Parking13.8416.619.3722.14
Security Fire Fighting15.3615.3615.3615.36
Street Light3.83.83.83.8
Underground water tank1.081.081.081.08
Renewable Energy3.93.9

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements8.418.418.418.41
Water Supply System5.115.116.0810.22
Sewerage treatment & garbage disposal0000
Electricity Supply System11.7111.717.037.03
Storm Water Drainage0.80.80.80.84
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other113.62151.49151.49151.49
Rain Water Harvesting0.50.50.5
Underground water tank1.081.351.351.35
Renewable energy3.93.93.94.55
Electric sub tation52.3952.3952.3952.39
Parking22.1422.1422.1422.14
Security Fire Fighting15.3615.3615.36
Street Light3.83.82.172.17
Security ire Fighting15.36
Rain water harvesting0.5

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.0411.7711.7710.09
Water Supply System10.2210.2210.2210.22
Sewerage treatment & garbage disposal0000
Electricity Supply System7.037.037.037.03
Storm Water Drainage1.121.121.120.98
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other151.49113.62113.62113.62
Parking22.1420.2819.3719.37
Underground water tank1.351.351.351.35
Renewable energy4.554.554.554.55
Rain Water Harvesting0.50.50.50.43
Street Light1.631.631.631.63
Security Fire Fighting19.2016.097.68
Electric sub tation52.3952.3952.3944.36
STP8.80
Security Fire Fighting17.2

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements10.098.413.362.05
Water Supply System6.816.813.413.27
Sewerage treatment & garbage disposal0000
Electricity Supply System7.037.033.042.34
Storm Water Drainage0.480.4800
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other96.3956.8137.8730.49
Renewable energy4.554.550.650.65
STP11.748.8
Underground water tank1.351.35
Electric sub tation43.6643.6634.9334.93
Parking16.612.650.8
Rain Water Harvesting0.370.31
Security Fire Fighting7.687.68
Street Light1.631.631.631.21
Security and Fire Fighting6.45
UGT0.25

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1.68
Water Supply System1.7
Sewerage treatment & garbage disposal0
Electricity Supply System2.34
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other18.94
Street Light0.54
Electric sub tation19.04
Renewable energy0.55












Particulars Remarks, if any
i. No. of Flats/Apartments constructed257
ii. No. of Flats/ Apartments booked208
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter25491.16 LakhsTaxes Extra
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter14187.09 LakhsTaxes Included
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter12167.84 LakhsTaxes Extra
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter0 LakhsTaxes Included
vii. Amount invested in the project upto the date of application16555.62 Lakhs
Land cost (If any)2703.00 Lakhs
Apartments6004.19 Lakhs
Infrastructure680.00 Lakhs
EDC/ Taxes Etc.7168.43 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession7572.73 Lakhs
(a) In respect of existing allottees0 Lakhs
(b) In respect of rest of the project7572.73 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
2771.00 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 Lakhs



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS168.1633.00
II. WATER SUPPLY SYSTEM170.3557.85
III. STORM WATER DRAINAGE16.031.32
IV. ELECTRICITY SUPPLY SYSTEM234.1937.55
V. SEWAGE TREATMENT & GARBAGE DISPOSAL00
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER1893.62270.00
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING276.735.00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM383.97167.00
XVII. OTHER FACILITIES AS PER PROJECT REPORT1055.20108.00









Yes
Yes
ICICI BANK LTD, SEC-54, SUNCITY GURGAON, HARYANA
039905005191
ICIC0000399
110229060
0399
1.Vyom Shakti (D-3/103, Paras City, E-3 Arera Colony, Huzur, R.S. Nagar, Bhopal – 482018, MP. 2. Mr. Pradeep Katiyar ( 357, Bakothi Purwa, PO Bakothi Khas, Kanpur Nagar – 209202, U.P.
Yes











Yes
No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENCEALREADY BEEN OBTAINED27-10-2010
II. ZONING PLANALREADY BEEN OBTAINED04-02-2016
III. BUILDING PLANALREADY BEEN OBTAINED30-11-2017
IV. ENVIRONMENT CLEARANCE ALREADY BEEN OBTAINED17-05-2019
V. ARAVALI ALREADY BEEN OBTAINED13-12-2012
VI. FORESTALREADY BEEN OBTAINED24-12-2012
VII. NOC FOR HEIGHT CLEARANCEALREADY BEEN OBTAINED20-06-2016
VIII. HARERA REGISTRATIONALREADY BEEN OBTAINED09-11-2017








Yes


Yes


AS PER HARERA NORMS













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSERCC SLAB
2WALL FINISHING DETAILSPAINTED/WHITE WASH MASONRY WALL/PARTITION
3KITCHEN DETAILSN.A.
4BATHROOM FITTINGSCHINAWARE & CP FITTINGS OF STANDARD MAKES, WASHBASIN WITH & WITHOUT COUNTER
5WOOD WORK ETCN.A.
6DOORS AND WINDOS FRAMESPOWDER COATED ALUMINIUM FRAME
7GLASS WORKGLASS THICKNESS OF 5 TO 12 MM
8ELECTRIC FITTINGSPUBLIC AREAS & TOILETS TO BE PROVIDED WITH LED LIGHT FIXTURES.
9CONDUCTING AND WIRING DETAILSIS APPROVED CONDUITS & WIRES
10CUPBOARD DETAILSN.A.
11WATER STORAGERCC TANK
12LIFT DETAILSSCHINDLER/THYSEENKRUP/FUJITEC/KONE
13EXTERNAL GLAZINGSPOWDER COATED ALUMINIUM GLAZING WITH GLASS OF 5-12 MM THICK GLASS
13.1WINDOWS/GLAZINGSPOWDER COATED ALUMINIUM GLAZING WITH GLASS OF 5-12 MM THICK GLASS
14DOORSALUMINIUM DOORS / GLASS DOORS
14.1MAIN DOORSALUMINIUM DOORS / GLASS DOORS
14.2INTERNAL DOORSMS/ALUMINIUM/WOODEN DOORS
15AIR CONDITIONINGCENTRAL CHILLED WATER AC SYSTEM FOR OFFICE & MULTIPLEX UPTO TAP OFF. PROVISION FOR WATER COOLED DX SYSTEM UPTO TAP OFF INSIDE SHOP
16ELECTRICAL FITTINGSPROVISION OF WIRE / CABLE UP TO DISTRIBUTION BOARD ISI /BIS APPROVED
17CNG PIPE LINEN.A.
18PROVISION OF WIFI AND BROADBAND FACILITYPROVISION OF ONT BOX ONLY
19EXTERNAL FINISHING/COLOUR SCHEMEPAINT/GLASS
20INTERNAL FINISHINGANTISKID TILES/IPS ON FLOOR, PAINT/WHITE WASH FINISH ON WALL & CEILING IN PUBLIC AREAS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORN.A.
1 . 2 WALLSN.A.
1 . 3 CEILINGN.A.
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORN.A.
2 . 2 WALLSN.A.
2 . 3 CEILINGN.A.
2 . 4 MODULAR WARDROBESN.A.
3 . MASTER TOILET
3 . 1 FLOORN.A.
3 . 2 WALLSN.A.
3 . 3 CEILINGN.A.
3 . 4 COUNTERSN.A.
3 . 5 SANITARY WARE/CP FITTINGSN.A.
3 . 6 FITTING/FIXTURESN.A.
4 . BED ROOMS
4 . 1 FLOORN.A.
4 . 2 WALLSN.A.
4 . 3 CEILINGN.A.
4 . 4 WARDROBESN.A.
5 . TOILET
5 . 1 FLOORN.A.
5 . 2 WALLSN.A.
5 . 3 CEILINGN.A.
5 . 4 COUNTERSN.A.
5 . 5 SANITARY WARE/CP FITTINGSN.A.
5 . 6 FIXTURESN.A.
6 . KITCHEN
6 . 1 FLOORN.A.
6 . 2 WALLSN.A.
6 . 3 CEILINGN.A.
6 . 4 COUNTERSN.A.
6 . 5 FIXTURESN.A.
6 . 6 KITCHEN APPLIANCESN.A.
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORN.A.
7 . 2 WALLS & CEILINGN.A.
7 . 3 TOILETN.A.
7 . 4 BALCONYN.A.
8 . SIT-OUTS
8 . 1 FLOORN.A.
8 . 2 WALLS & CEILINGN.A.
8 . 3 RAILINGSN.A.
8 . 4 FIXTURESN.A.












Sr. No.Document DescriptionDate of Document UploadView Document
1DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.12-02-2020 View Document
2CASH FLOW STATEMENT OF THE PROPOSED PROJECT12-02-2020 View Document
3IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN05-02-2020 View Document
4NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT05-02-2020 View Document
5ZONING PLAN05-02-2020 View Document
6DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD05-02-2020 View Document
7COPY OF LICENSE ALONG WITH SCHEDULE OF LAND05-02-2020 View Document
8IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN05-02-2020 View Document
9SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN05-02-2020 View Document
10A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS05-02-2020 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 The registration certificate issued for part of the project/phase vide Registration No. 348 of 2Ol7 dated 09.11 .2017 (Interim RERA, Panchkula) stand subsumed in this registration certificate after incorporating the additional FAR under TDR without affecting the obligations and liabilities of M/s M3M India Pvt. Ltd. and M/s Martial Buildcon Pvt. Ltd. towards the existing allottees. Earlier registration no. 348 of 2Ol7 comprises total FAR 19,613.449 sqm. 18-01-2023 View Document