UNIT NO. SB/C/5L/OFFICE/008,M3M URBANA,SECTOR-67, GURUGRAM MANESAR URBAN COMPLEX,GURUGRAM-122102, HARYANA
01244732000
9711348349 (Number Shared by Promoter in Public)
oliverealcon@rediffmail.com
http://www.trumptowersdelhincr.com
XXXX163E
U70100HR2011PTC043561
TRUMP TOWERS DELHI NCR
SECTOR-65, GURUGRAM
BADSHAHPUR ST
GURUGRAM
01244732000
9810365766 (Number Shared by Promoter in Public)
oliverealcon@rediffmail.com
NAVEEN SHARMA
01244732000
9810365766 (Number Shared by Promoter in Public)
oliverealcon@rediffmail.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.894
3
CONSTRUCTION OF ROADS
0.849
4
PAVEMENTS
0.20313
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0.103
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0.77912
13
RAIN WATER HARVESTING
0.003
Total
2.83125
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP/ GMDA
Yes
WATER SUPPLY
HSVP/ GMDA
Yes
ELECTRICITY
DHBVNL
Yes
SEWAGE DISPOSAL
HSVP/ GMDA
Yes
STORM WATER DRAINAGE
HSVP/ GMDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
350
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
2442
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
56
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
1643
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
15
AS PER PROJECT REPORT
6
STREET LIGHTING
70
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
1054
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
5
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
1359
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
2920
AS PER PROJECT REPORT
15
UNDERGROUND WATER TANK
109
AS PER PROJECT REPORT
16
RAIN WATER HARVESTING
16
AS PER PROJECT REPORT
17
ELECTRICAL SUB STATION
1331
AS PER PROJECT REPORT
15-01-2018 (date)
15-01-2018 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
14-05-2018
0.03
31-12-2024
674
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
7842.41
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
658.00
Shops
0
Plots
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
939.00
939
939
939
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
2511
2511
2990
2993
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
3732
3432
3484
3244
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
3192
2958
2958
2958
Shops
0
0
0
0
Plots
0
0
0
0
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
2300.00
342.00
342.00
342.00
Shops
0
0
0
0
Plots
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
3.06
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
0
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
3
Storm Water Drainage
0
0
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
0
Water Supply System
0
122.11
122.11
122.11
Sewerage treatment & garbage disposal
0
0.75
0.75
0.75
Electricity Supply System
48.14
65.72
82.15
98.58
Storm Water Drainage
0
0
0
0
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
Security Fire fighting
31.62
31.62
31.62
Underground water tank
5.47
5.47
5.47
5.47
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
0
31.50
Water Supply System
122.11
122.11
122.11
170.96
Sewerage treatment & garbage disposal
1.05
1.05
1.05
1.05
Electricity Supply System
98.58
98.58
164.30
164.30
Storm Water Drainage
0
2.82
3.38
3.94
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
108.69
108.69
Shopping area
0
0
0
0
Other
0
0
0
0
Security Fire fighting
52.70
Underground water tank
8.75
8.75
8.75
8.75
Rain water harvesting
1.60
1.60
1.60
Street Light
14.00
14.00
Security Fire fighting
31.62
52.70
73.77
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
31.50
31.50
42.00
42.00
Water Supply System
170.96
195.38
195.38
195.38
Sewerage treatment & garbage disposal
1.05
1.05
1.05
1.05
Electricity Supply System
164.30
164.30
142.78
49.29
Storm Water Drainage
5.07
6.20
6.76
5.63
Parks and Playgrounds
0
0
0.50
0.75
Clubhouse/community centres
108.69
122.28
135.87
135.87
Shopping area
0
0
0
0
Other
292.03
292.03
292.03
292.03
Street Light
14.00
3.50
3.50
3.50
Rain water harvesting
1.60
1.60
1.60
1.60
Underground water tank
10.94
10.94
10.94
7.66
Security Fire fighting
105.39
105.39
105.39
105.39
Electric sub station
133.15
199.72
Particulars
Year-2023
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
42.00
42.00
31.50
24.50
Water Supply System
195.38
170.96
170.96
122.11
Sewerage treatment & garbage disposal
1.05
1.05
0.75
0.75
Electricity Supply System
49.29
49.29
49.29
49.29
Storm Water Drainage
5.63
5.07
4.51
4.51
Parks and Playgrounds
0.75
0.75
0.75
0.75
Clubhouse/community centres
135.87
135.87
135.87
135.87
Shopping area
0
0
0
0
Other
292.03
292.03
292.03
292.03
Security Fire fighting
105.39
84.31
42.16
31.62
Street Light
3.50
3.50
3.50
2.80
Underground water tank
7.66
4.38
Rain water harvesting
1.60
1.60
1.60
Electric sub station
199.72
199.72
199.72
146.46
Particulars
Year-2024
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
21.00
3.50
3.50
3.50
Water Supply System
48.85
24.42
24.42
24.42
Sewerage treatment & garbage disposal
0.75
0
0
0
Electricity Supply System
49.29
16.43
16.43
16.43
Storm Water Drainage
2.82
0
0
0
Parks and Playgrounds
0.75
0
0
0
Clubhouse/community centres
54.35
13.59
13.59
13.59
Shopping area
0
0
0
0
Other
292.03
116.81
87.61
87.61
Electric sub station
133.15
39.94
39.94
39.94
Security Fire fighting
31.62
10.54
10.54
10.54
Street Light
2.10
0.70
0.70
0.70
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
0
ii. No. of Flats/ Apartments booked
94
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
70603.77 Lakhs
Taxes Extra
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
15245.6103 Lakhs
Taxes Included
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
55554.80 Lakhs
Taxes Extra
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
1629.42 Lakhs
Taxes Included
vii. Amount invested in the project upto the date of application
17694.34 Lakhs
Land cost (If any)
897.67 Lakhs
Apartments
7842.41 Lakhs
Infrastructure
3.06 Lakhs
EDC/ Taxes Etc.
8951.20 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
170318.71 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
170318.71 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
0 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
350
0
II. WATER SUPPLY SYSTEM
2442
0
III. STORM WATER DRAINAGE
56
0
IV. ELECTRICITY SUPPLY SYSTEM
1643
3.06
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
15
0
VI. CLUB HOUSE/COMMUNITY CENTRE
1359
0
VII. SCHOOL
0
0
VIII. ANY OTHER
2920
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
1054
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
1526
0
Yes
Yes
ICICI BANK, SUNCITY, SEC-54, GURUGRAM, HARYANA-122002
0777705996425
ICIC0000399
110229060
000399
1.Vyom Shakti (D-3/103, Paras City, E-3 Arera Colony, Huzur, R.S. Nagar, Bhopal – 482018, MP.
2. Mr. Pradeep Katiyar ( 357, Bakothi Purwa, PO Bakothi Khas, Kanpur Nagar – 209202, U.P.
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
No
No
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
16-10-2007
II. ZONING PLAN
ALREADY BEEN OBTAINED
22-05-2017
III. BUILDING PLAN
ALREADY BEEN OBTAINED
15-01-2018
IV. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
05-01-2015
V. ARAVALI
ALREADY BEEN OBTAINED
12-08-2014
VI. FOREST
ALREADY BEEN OBTAINED
30-07-2010
VII. NOC FOR HEIGHT CLEARANCE
ALREADY BEEN OBTAINED
20-07-2017
VIII. ELECTRICITY
ALREADY BEEN OBTAINED
22-11-2016
IX. HARERA REGISTRATION
ALREADY BEEN OBTAINED
28-11-2017
X. PERMISSION OF DEVELPOMENT RIGHT
ALREADY BEEN OBTAINED
12-10-2018
Yes
Yes
AS PER HARERA NORMS
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
MARBLE/ WOODEN FLOORING / TILE
2
WALL FINISHING DETAILS
PAINT ON PLASTER
3
KITCHEN DETAILS
POLISHED GRANITE/STONE COUNTER WITH STANDARD MAKE SS SINK AND CP FITTINGS
4
BATHROOM FITTINGS
MARBLE/ GRANITE/CORIAN COUNTER WITH STANDARD MAKE SANITARY FIXTURES AND CP FITTINGS
5
WOOD WORK ETC
MODULAR KITCHEN CABINETRY
6
DOORS AND WINDOS FRAMES
COMBINATION OF PANELLED/FLUSHED DOOR, CURTAIN GLAZING WITH SLIDING PANELS / POWDER COATED / ANODIZED ALUMINIUM WINDOWS
7
GLASS WORK
COMBINATION OF SINGLE/DOUBLE GLASS VARIOUS THICKNESS.
8
ELECTRIC FITTINGS
COMMON AREA LIGHTING, GEYSER IN ALL TOILETS
9
CONDUCTING AND WIRING DETAILS
IS APPROVED CONDUITS & COPPER WIRES
10
CUPBOARD DETAILS
N.A
11
WATER STORAGE
RCC TANK
12
LIFT DETAILS
SCHINDLER / KONE / OTIS /THAISON/HITACHI / OR EQUIVALENT
13
EXTERNAL GLAZINGS
COMBINATION OF STONE, EXTERNAL PAINT & CURTAIN GLAZING
13.1
WINDOWS/GLAZINGS
CURTAIN GLAZING / POWDER COATED / ANODIZED ALUMINIUM WINDOWS
14
DOORS
PANELLED/FLUSHED DOOR.
14.1
MAIN DOORS
FIRE RATED DOOR
14.2
INTERNAL DOORS
PANELLED/FLUSHED DOOR.
15
AIR CONDITIONING
VRF/VRV BASED AIR CONDITIONING SYSTEM
16
ELECTRICAL FITTINGS
COMMON AREA LIGHTING, GEYSER IN ALL TOILETS
17
CNG PIPE LINE
N.A.
18
PROVISION OF WIFI AND BROADBAND FACILITY
N.A.
19
EXTERNAL FINISHING/COLOUR SCHEME
COMBINATION OF STONE, EXTERNAL PAINT & CURTAIN GLAZING
20
INTERNAL FINISHING
COMBINATION OF SELECTED STONE/GRANITE/PANELLING AND PAINT.