HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-814-2020
Submission Date : 07-03-2020 06:10:22 PM
Applicant Type : Firm
Project Type: NEW


S3 INFRABUILD LLP
2F-1-3, OZONE CENTER SEC-12, FARIDABAD
01292220365
9873656757 (Number Shared by Promoter in Public)
s3infrabuildllp@gmail.com
AAI9222
ADIFS1290F



















GREEN AVENUE
VILLAGE- KHERI KALAN, SECTOR-85, FARIDABAD, HARYANA
FARIDABAD
FARIDABAD
9811247182 (Number Shared by Promoter in Public)
S3INFRABUILDLLP@GMAIL.COM
GOVARDHAN LAL SHARMA
9811247182 (Number Shared by Promoter in Public)
GL.SHARMA@AURICHOMES.COM








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
122005907-03-2020262600IDFC FIRST BANKHRERA Panchkula







21524.183 (Sqr/mtrs)
2.25
2.28
21524.183 (Sqr/mtrs)
136 OF 2019
Yes







19000 Lakhs
5600 Lakhs
10600 Lakhs
1600 Lakhs
1200 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS5731.79
3CONSTRUCTION OF ROADS4430.00
4PAVEMENTS1050.00
5PARKS AND PLAYGROUNDS4362.50
6GREEN BELTS0
7VEHICLE PARKINGS6486.27
8ELECTRICITY SUB-STATION419.73
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY50.00
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES224.00
12ANY OTHER1530.50
Total24284.79




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS200YET TO BE PREPARED
2WATER SUPPLY SYSTEM100YET TO BE PREPARED
3STORM WATER DRAINAGE50YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM300YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL200YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING50YET TO BE PREPARED
8PLAYGROUNDS AND PARKS45YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE35YET TO BE PREPARED
10SHOPPING AREA250YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER50YET TO BE PREPARED


NA (date)
NA (date)
15-04-2020
25-04-2024
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings6064812
Apartment/Shops/Other Buildings29.56591
Apartment/Shops/Other Buildings29.40591





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments400700850
Shops000
Plots000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments850840800880
Shops005050
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments620720620620
Shops5050500
Plots0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments530580530530
Shops0000
Plots0000

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments530
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0505050
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0505050
Other0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area505000
Other0000

ParticularsYear-2023
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements50505050
Water Supply System25252525
Sewerage treatment & garbage disposal0000
Electricity Supply System75757575
Storm Water Drainage12.512.512.512.5
Parks and Playgrounds1501515
Clubhouse/community centres20000
Shopping area0000
Other1001010

ParticularsYear-2024
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements50
Water Supply System25
Sewerage treatment & garbage disposal50
Electricity Supply System75
Storm Water Drainage12.5
Parks and Playgrounds15
Clubhouse/community centres15
Shopping area0
Other5












Yes
No
NIT, FARIDABAD
10052839916
FDFB0021313
110751031
21313
RAJEEV AGGARWAL & HARI KISHAN GARG
YES











Yes
Yes
Yes
No
Yes
Yes
No
Yes
Yes
Yes


Yes
No
No
No
No
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. YET TO FILE FOR APPROVALYET TO FILE FOR APPROVALNA








Yes


Yes


YES













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSEVITRIFIED TILES
2WALL FINISHING DETAILSWHITE WASH/ O.B.D PAINT
3KITCHEN DETAILSCERAMIC TILES/ VITRIFIED TILES
4BATHROOM FITTINGSC.P. FITTING
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESPAINTED FLUSH DOOR WITH PRESS STEEL FRAMES
7GLASS WORKWINDOWS
8ELECTRIC FITTINGSISI MARKED SWITCHES
9CONDUCTING AND WIRING DETAILSISI MARKED
10CUPBOARD DETAILSNA
11WATER STORAGEOVERHEAD TANK FOR EACH TOWER
12LIFT DETAILSISI MARKED
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGS4 MM GLASS WITH M.S. FRAME SHUTTER
14DOORSPAINTED FLUSH DOOR WITH PRESS STEEL FRAMES
14.1MAIN DOORSPAINTED FLUSH DOOR WITH PRESS STEEL FRAMES
14.2INTERNAL DOORSPAINTED FLUSH DOOR WITH PRESS STEEL FRAMES
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSISI MARKED
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMESUPER FINE TEXTURE PAINT OF PLEASING SHADES
20INTERNAL FINISHINGWHITE WASH/ O.B.D PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSWHITE WASH/ O.B.D. PAINT
1 . 3 CEILINGWHITE WASH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSWHITE WASH/ O.B.D. PAINT
2 . 3 CEILINGWHITE WASH
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILES 1X1
3 . 2 WALLSCERAMIC TILES UP TO 7"-0" HT
3 . 3 CEILINGWHITE WASH
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSEUROPEAN W.C. IN ALL TOILETS WITH WASH BASIN
3 . 6 FITTING/FIXTURESC.P. FITTING
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILES
4 . 2 WALLSWHITE WASH/ O.B.D. PAINT
4 . 3 CEILINGWHITE WASH
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORCERAMIC TILES 1X1
5 . 2 WALLSCERAMIC TILES UP TO 7"-0" HT
5 . 3 CEILINGWHITE WASH
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSEUROPEAN W.C. IN ALL TOILETS WITH WASH BASIN
5 . 6 FIXTURESC.P. FITTING
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILES
6 . 2 WALLSO.B.D. PAINT
6 . 3 CEILINGWHITE WASH
6 . 4 COUNTERSGRANITE
6 . 5 FIXTURESSINGLE BOWL STAINLESS STEEL
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILES
7 . 2 WALLS & CEILINGWHITE WASH
7 . 3 TOILETNA
7 . 4 BALCONYCERAMIC TILES/ M.S. PAINTED RAILING
8 . SIT-OUTS
8 . 1 FLOORVITRIFIED TILES
8 . 2 WALLS & CEILINGWHITE WASH
8 . 3 RAILINGSM.S. PAINTED PALING
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1CASH FLOW STATEMENT OF THE PROPOSED PROJECT15-02-2020 View Document
2A COPY OF DD07-03-2020 ------
3BUILDING PLAN APPROVAL LATTER STP07-03-2020 ------
4BALANCE SHEET 2018-1930-01-2020 ------
5ZONING PLAN30-01-2020 View Document
6LLP AGREEMENT 230-01-2020 ------
7DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD30-01-2020 View Document
8LLP AG30-01-2020 ------
9BR FOR AUTHORIZED PERSON FOR RERE 30-01-2020 ------
10DEMARCATION PLAN30-01-2020 View Document
11BALANCE SHEET 2017-1830-01-2020 ------
12LLP AGREEMENT 330-01-2020 ------
13GST REGISTRATION CERTIFICATE30-01-2020 ------
14ALLOTMENT LATTER 31-01-2020 ------
15COPY OF LICENSE ALONG WITH SCHEDULE OF LAND30-01-2020 View Document
16IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN30-01-2020 View Document
17CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT30-01-2020 View Document
18SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN30-01-2020 View Document
19NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT30-01-2020 View Document
20COLLOABORATION30-01-2020 ------
21DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.30-01-2020 View Document
22SPA30-01-2020 ------
23ITR SHEET 2019-2030-01-2020 ------
24CERTIFICATE OF INCORPORATION30-01-2020 ------
25A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS30-01-2020 View Document
26GIST 30-01-2020 ------
27IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN30-01-2020 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Certificate of Covid Extension approved. 12-12-2024 View Document