PLOT NO. 18, SECOND FLOOR, SECTOR 44, GURGAON 122002, HARYANA
01244738000
9811533566 (Number Shared by Promoter in Public)
amb@ambgroup.in
http://www.ambgroup.in
XXXX216G
U70109DL2012PTC230154
AMB SELFIE SQUARE
SECTOR 37D, GURUGRAM, HARYANA
HARSARU ST
GURUGRAM
01244738000
9810190065 (Number Shared by Promoter in Public)
amb@ambgroup.in
P S BAJWA
01244738000
9810190065 (Number Shared by Promoter in Public)
amb@ambgroup.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
3110
29-07-2017
275000
AXIS BANK LIMITED
HRERA Gurugram
2
28023
31-07-2017
260000
AXIS BANK LIMITED
HRERA Gurugram
3.775 (Acre)
23799.00
1.75
3.775 (Acre)
14 of 2014 Dated 10.06.2014
Yes
29549.31 Lakhs
3690.40 Lakhs
10069.64 Lakhs
1850.00 Lakhs
13939.27 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0.7281
3
CONSTRUCTION OF ROADS
1.4784
4
PAVEMENTS
1.1539
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0.4146
Total
3.775
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HSVP / GMDA
No
WATER SUPPLY
HSVP / GMDA
Yes
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HSVP / GMDA
No
STORM WATER DRAINAGE
HSVP / GMDA
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
200
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
500
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
700
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
975
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
200
AS PER PROJECT REPORT
6
STREET LIGHTING
200
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
300
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
0
YET TO BE PREPARED
9
CLUB HOUSE/COMMUNITY CENTRE
0
YET TO BE PREPARED
10
SHOPPING AREA
0
YET TO BE PREPARED
11
RENEWABLE ENERGY SYSTEM
100
AS PER PROJECT REPORT
12
SCHOOL
0
YET TO BE PREPARED
13
HOSPITAL/DISPENSARY
0
YET TO BE PREPARED
14
ANY OTHER
0
YET TO BE PREPARED
15
PARKING
123
YET TO BE PREPARED
16
UNDER GROUND WATER TANK
50
AS PER PROJECT REPORT
17
ELECTRICAL SUB STATION
75
AS PER PROJECT REPORT
18
RAIN WATER HARVESTING
50
AS PER PROJECT REPORT
16-07-2014 (date)
16-07-2014 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type ANCHOR
1538
132
132
0
1
2
APARTMENT/SHOPS/OTHER BUILDINGS Type FOOD STALL
96
10
10
0
1
3
APARTMENT/SHOPS/OTHER BUILDINGS Type KIOSK
527
40
34
6
1
4
APARTMENT/SHOPS/OTHER BUILDINGS Type OFFICE
6985
225
198
27
1
5
APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS
4058
245
242
3
1
6
APARTMENT/SHOPS/OTHER BUILDINGS Type RESTAURANT
418
3
3
0
1
7
APARTMENT/SHOPS/OTHER BUILDINGS Type MULTIPLEX
1970
5
5
0
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
ANCHOR
132
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
FOOD STALL
10
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
KIOSK
34
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
OFFICE
198
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
SHOP
242
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
RESTAURANT
3
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
MULTIPLEX
5
THREE BASEMENT, GROUND FLOOR, FIRST FLOOR COMPLETED, WORK IN PROGRESS FOR SECOND FLOOR
01-10-2015
31-03-2022
31-03-2022
01-10-2020
0
31-12-2021
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
01-10-2020
0
31-12-2021
513
0
0
71
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
165.78
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
1144.13
Plots
0
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
1182.46
920.35
1180.55
1338.37
Plots
0
0
0
0
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
0
0
0
Shops
974.22
669.39
469.39
588.61
Plots
0
0
0
0
Particulars
Year-2022
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
1073.32
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
Water Supply System
0
87.5
Sewerage treatment & garbage disposal
0
0
Electricity Supply System
0
121.87
Storm Water Drainage
0
68.18
Parks and Playgrounds
0
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
SECURITY
15
Particulars
Year-2021
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
0
0
100
100
Water Supply System
175
175
175
87.5
Sewerage treatment & garbage disposal
0
0
100
100
Electricity Supply System
243.75
243.75
243.75
121.87
Storm Water Drainage
136.36
136.36
136.36
22.72
Parks and Playgrounds
0
0
0
0
Clubhouse/community centres
0
0
0
0
Shopping area
0
0
0
0
Other
0
0
0
0
SECURITY
90
90
90
15
RAIN WATER HARVESTING
15
30
5
UNDERGROUND WATER TANK
25
STREET LIGHT
100
100
RENEWAL ENERGY SYSTE
83.33
ELECTRIC SUB STATION
37.5
RENEWAL ENERGY SYSTEM
16.66
CONSTRUCTION OF CIRCULATION ROAD
0
ELECTRICITY SUB STATION
37.5
PARKING
0
UNDER GROUND WATER TANK
25
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
660
ii. No. of Flats/ Apartments booked
623
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
29362.84 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
13907.28 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
14843.36 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
612.20 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
3690.40 Lakhs
Apartments
0 Lakhs
Infrastructure
5337.39 Lakhs
EDC/ Taxes Etc.
7530.76 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
12970.75 Lakhs
(a) In respect of existing allottees
12062.80 Lakhs
(b) In respect of rest of the project
907.95 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
144.92 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
700
0
II. WATER SUPPLY SYSTEM
750
0
III. STORM WATER DRAINAGE
550
0
IV. ELECTRICITY SUPPLY SYSTEM
1050
0
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
200
0
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
123
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
300
0
XVII. OTHER FACILITIES AS PER PROJECT REPORT
300
0
Yes
Yes
AXIS BANK LIMITED B-6, LAJPAT NAGAR-II, NEW DELHI-10024
913020022600957
UTIB0000126
110211017
000126
Manoj Sethi, Saurabh Mukand
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
No
No
No
No
No
Yes
No
No
No
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LICENCE
ALREADY BEEN OBTAINED
10-06-2014
II. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
26-11-2014
III. NOC FOR WATER - CONSTRUCTION
ALREADY BEEN OBTAINED
08-07-2014
IV. NOC FOR WATER-DRINKING
ALREADY BEEN OBTAINED
14-05-2015
V. HEIGHT NOC
ALREADY BEEN OBTAINED
04-08-2014
VI. BUILDING PLAN APPROVAL
ALREADY BEEN OBTAINED
16-07-2014
VII. FOREST NOC
ALREADY BEEN OBTAINED
25-07-2014
VIII. ARAVALI NOC
ALREADY BEEN OBTAINED
28-07-2014
IX. ELECTRICAL LOAD
ALREADY BEEN OBTAINED
10-12-2015
X. RERA REGISTRATION
ALREADY BEEN OBTAINED
17-08-2017
Yes
Yes
As Per HARERA Norms
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: