HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-806-2020
Submission Date : 23-01-2020 12:03:28 PM
Applicant Type : Company
Project Type: ONGOING




JOP INTERNATIONAL LIMITED
45/77 PUNJABI BAGH NEW DELHI 110026
01147323166
9811808234 (Number Shared by Promoter in Public)
INFO@JOPGROUP.IN
XXXX006E
U51909DL1999PL100149
 
 


 
 


 
 


 
 







JOP PALMS
GARHI BOHAR, SECTOR 28
ROHTAK
ROHTAK
9729255055 (Number Shared by Promoter in Public)
info@jopgroup.in
DEVENDER KUMAR
9729955055 (Number Shared by Promoter in Public)
info@jopgroup.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
187901013-07-2018287403VIJAYA BANKHRERA Panchkula
29991822-11-2017139413BANK OF BARODA, PUNJAB BAGH, NEW DELHIHRERA Panchkula







6.8875 (Acre)
1.75
1.75
6.8875 (Acre)
License No. 07 of 2013 dated 04.03.2013 which is valid upto 03.03.2017.
Yes







12500.00 Lakhs
1161.20 Lakhs
6076.85 Lakhs
948.05 Lakhs
4313.90 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS2.22
3CONSTRUCTION OF ROADS3.0291
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1.066
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION0.0708
9CLUB HOUSE0.198
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.0708
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0.20
12ANY OTHER0
13COMMERCIAL 0.0328
Total6.8875




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPNo
WATER SUPPLYHSVPNo
ELECTRICITYUHBVNLNo
SEWAGE DISPOSALHSVPNo
STORM WATER DRAINAGEHSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS236.88AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM176.15AS PER PROJECT REPORT
3STORM WATER DRAINAGE46.44AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM165.00AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL78.87AS PER PROJECT REPORT
6STREET LIGHTING10.56AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING125.00AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS25.00AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA30.00AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL50.00AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


17-07-2013 (date)
17-07-2013 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type 3 BHK89.001901335719
2APARTMENT/SHOPS/OTHER BUILDINGS Type 2 BHK62.00196851112
3APARTMENT/SHOPS/OTHER BUILDINGS Type 4 BHK138.00560561






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
3 BHK13314 TOWERS STRUCUTRE 100% COMPLETED, FINISHING WORKS STARTED AND 2 TOWERS PLINTH WORK COMPLETED.
2 BHK85STRUCTURE WORK UPTO 7TH FLOOR OUT OF 14TH FLOOR
4 BHK0ONLY DIGGING WORK COMPLETED


03-03-2014
31-03-2017
31-12-2022
03-03-2014
50
31-12-2022


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
03-03-2014
50
31-12-2022


402
120
0
144
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments4271.00
Shops21.00
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments75.24375
Shops0
Plots0

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments150.487575.24375150.4875150.4875
Shops09.0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments150.4875150.4875150.4875150.4875
Shops0000
Plots0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments150.4875150.4875300.975
Shops000
Plots000




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements82.00
Water Supply System17.61
Sewerage treatment & garbage disposal7.80
Electricity Supply System0
Storm Water Drainage43.00
Parks and Playgrounds20.00
Clubhouse/community centres0
Shopping area21.00
Other0
Security38.00

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements30.000020.00
Water Supply System26.420026.42
Sewerage treatment & garbage disposal0.00015.0035.00
Electricity Supply System50.00000.00
Storm Water Drainage1.00001.44
Parks and Playgrounds5.00000
Clubhouse/community centres0000
Shopping area0000
Other7.06000
School0
Security0

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0.0030.0030.0010.00
Water Supply System13.2113.2100
Sewerage treatment & garbage disposal8.00000
Electricity Supply System0.000065.00
Storm Water Drainage4.501.0000
Parks and Playgrounds05.002.000
Clubhouse/community centres0000
Shopping area00.000.000
Other0000
Security16.0016.0016.00

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements12.0025.0012.88
Water Supply System26.4226.4226.43
Sewerage treatment & garbage disposal8.005.070
Electricity Supply System0.000.0050.00
Storm Water Drainage00.000.00
Parks and Playgrounds2.005.005.59
Clubhouse/community centres000
Shopping area000
Other03.560
Security20.0019.00
School50.00












Particulars Remarks, if any
i. No. of Flats/Apartments constructed542
ii. No. of Flats/ Apartments booked218
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter13931.00 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter5295.00 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter8636.00 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter8636.00 Lakhs
vii. Amount invested in the project upto the date of application7962.10 Lakhs
Land cost (If any)1161.20 Lakhs
Apartments4271 Lakhs
Infrastructure40.00 Lakhs
EDC/ Taxes Etc.2489.90 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession4538.00 Lakhs
(a) In respect of existing allottees0 LakhsAs above
(b) In respect of rest of the project0 LakhsAs above
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 LakhsNIL
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 LakhsNIL



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS236.8882.00
II. WATER SUPPLY SYSTEM176.1517.61
III. STORM WATER DRAINAGE46.4443.00
IV. ELECTRICITY SUPPLY SYSTEM165.000
V. SEWAGE TREATMENT & GARBAGE DISPOSAL78.877.80
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL50.000
VIII. ANY OTHER10.560
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING30.0021.00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.25.0020.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM125.0038.00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
BANK OF BARODA, PUNJABI BAGH, NEW DELHI -110026
12990200000281
BARB0PUNJAB
110012027
001299
Bharat Agarewal, R/o 45/77 Punjabi Bagh, New Delhi
Annexed.











No
No
No
Yes
Yes
Yes
Yes
No
Yes
Yes


No
No
No
No
No
No
No
No
Statutory Approvals Statutory Approvals StatusDate
I. LICENSE NO. 7 OF 2013ALREADY BEEN OBTAINED04-03-2013
II. BUILDING PLANS APPROVAL ALREADY BEEN OBTAINED18-02-2014
III. ENVIRONMENTAL CLEARANCE ALREADY BEEN OBTAINED06-06-2014
IV. RENEWAL APPLICATION APPLIED FOR BUT YET TO RECEIVE06-02-2017








Yes


Yes


The clauses mentioned under RERA Rules shall have added into prospective agreements to be executed with the allottees.













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSETILES AS PER STANDARDS
2WALL FINISHING DETAILSOBD
3KITCHEN DETAILSGRANITE TOP, STAIN LESS STEEL SINK AND CP FITTINGS.
4BATHROOM FITTINGSWC, WASH BASIN AND CP FITTINGS.
5WOOD WORK ETCNOT APPLICABLE.
6DOORS AND WINDOS FRAMESPROVIDED AS PER STANDARD.
7GLASS WORKNOT APPLICABLE.
8ELECTRIC FITTINGSNOT APPLICABLE.
9CONDUCTING AND WIRING DETAILSCOPPER WIRING IN CONCEALED PVC CONDUITS WITH MCB SUPPORTED CIRCUITS & SUFFICIENT NO LIGHTS AND POWER POINTS & TELEPHONE POINTS.
10CUPBOARD DETAILSNOT APPLICABLE.
11WATER STORAGEUGT AND OHT
12LIFT DETAILS25 LIFTS PROVIDED
13EXTERNAL GLAZINGSUPVC
13.1WINDOWS/GLAZINGSAS PER STANDARDS
14DOORSAS PER STANDARDS
14.1MAIN DOORSFLUSH DOOR WITH HARDWARE FITTINGS
14.2INTERNAL DOORSFLUSH DOOR WITH HARDWARE FITTINGS
15AIR CONDITIONINGAS PER STANDARDS
16ELECTRICAL FITTINGSAS PER STANDARDS
17CNG PIPE LINENOT APPLICABLE.
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMEWATER PROOF PAINT
20INTERNAL FINISHINGOBD PAINTS
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFIED TILES
1 . 2 WALLSOBD
1 . 3 CEILINGPAINT OBD
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILES
2 . 2 WALLSPAINT (OBD)
2 . 3 CEILINGPAINT (OBD)
2 . 4 MODULAR WARDROBESNO
3 . MASTER TOILET
3 . 1 FLOORTILES
3 . 2 WALLSTILE
3 . 3 CEILINGPAINT OBD
3 . 4 COUNTERSNO
3 . 5 SANITARY WARE/CP FITTINGSYES
3 . 6 FITTING/FIXTURESNO
4 . BED ROOMS
4 . 1 FLOORTILE
4 . 2 WALLSPAINT OBD
4 . 3 CEILINGPAINT OBD
4 . 4 WARDROBESNO
5 . TOILET
5 . 1 FLOORTILE
5 . 2 WALLSTILE
5 . 3 CEILINGPAINT OBD
5 . 4 COUNTERSNO
5 . 5 SANITARY WARE/CP FITTINGSYES
5 . 6 FIXTURESNO
6 . KITCHEN
6 . 1 FLOORTILE
6 . 2 WALLSTILE UPTO 2 FT ABOVE THE PLATFORM
6 . 3 CEILINGPAINT OBD
6 . 4 COUNTERSGRANITE TOP
6 . 5 FIXTURESHANDLES, STEEL SINK WITH CP FITTINGS.
6 . 6 KITCHEN APPLIANCESNO
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORTILE
7 . 2 WALLS & CEILINGPAINT OBD
7 . 3 TOILETN/A
7 . 4 BALCONYYES
8 . SIT-OUTS
8 . 1 FLOORTILE
8 . 2 WALLS & CEILINGPAINT (OBD)
8 . 3 RAILINGSMS RAILING WITH OIL PAINT
8 . 4 FIXTURESNO












Sr. No.Document DescriptionDate of Document UploadView Document
1IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN15-01-2020 View Document
2DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.15-01-2020 View Document
3NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT15-01-2020 View Document
4IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN15-01-2020 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND15-01-2020 View Document
6CASH FLOW STATEMENT OF THE PROPOSED PROJECT15-01-2020 View Document