As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
0
03-02-2020
0.00
NOT APPLICABLE
HRERA Gurugram
3.47 (Acre)
250
250
8.356 (Acre)
86 of 2010 (23-10-2010)
No
Address 232 B, FOURTH FLOOR, OKHLA INDUSTRIAL ESTATE, PHASE III, NEW DELHI - 110020
Annexure-B- DEVELOPER
AFTER GRANT OF LICENSE
No
N/A
No
No
Yes
38411.34 Lakhs
2982.39 Lakhs
13557.91 Lakhs
2935.18 Lakhs
18935.8 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
0
3
CONSTRUCTION OF ROADS
0
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
0
6
GREEN BELTS
0
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
0
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0
Total
0
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
N/A
No
WATER SUPPLY
GMDA
Yes
ELECTRICITY
DHVBN
Yes
SEWAGE DISPOSAL
GMDA
Yes
STORM WATER DRAINAGE
GMDA
Yes
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
210.84
SUBMITTED TO TOWN & COUNTRY PLANNING
2
WATER SUPPLY SYSTEM
1136.63
SUBMITTED TO TOWN & COUNTRY PLANNING
3
STORM WATER DRAINAGE
170.50
SUBMITTED TO TOWN & COUNTRY PLANNING
4
ELECTRICITY SUPPLY SYSTEM
954.780
SUBMITTED TO TOWN & COUNTRY PLANNING
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
64.28
SUBMITTED TO TOWN & COUNTRY PLANNING
6
STREET LIGHTING
20.12
SUBMITTED TO TOWN & COUNTRY PLANNING
7
SECURITY AND FIRE FIGHTING
287.43
SUBMITTED TO TOWN & COUNTRY PLANNING
8
PLAYGROUNDS AND PARKS
0
SUBMITTED TO TOWN & COUNTRY PLANNING
9
CLUB HOUSE/COMMUNITY CENTRE
0
SUBMITTED TO TOWN & COUNTRY PLANNING
10
SHOPPING AREA
0
SUBMITTED TO TOWN & COUNTRY PLANNING
11
RENEWABLE ENERGY SYSTEM
0
SUBMITTED TO TOWN & COUNTRY PLANNING
12
SCHOOL
0
SUBMITTED TO TOWN & COUNTRY PLANNING
13
HOSPITAL/DISPENSARY
0
SUBMITTED TO TOWN & COUNTRY PLANNING
14
ANY OTHER
0
SUBMITTED TO TOWN & COUNTRY PLANNING
15
STP
56.50
SUBMITTED TO TOWN & COUNTRY PLANNING
16
RAIN WATER HARVESTING
34.10
SUBMITTED TO TOWN & COUNTRY PLANNING
22-08-2019 (date)
22-08-2019 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type SHOPS
674.17
0
0
0
0
2
APARTMENT/SHOPS/OTHER BUILDINGS Type RESTAURANT
156.00
0
0
0
0
3
APARTMENT/SHOPS/OTHER BUILDINGS Type FOOD COURT
324.66
0
0
0
0
4
APARTMENT/SHOPS/OTHER BUILDINGS Type CAFé
198.97
0
0
0
0
5
APARTMENT/SHOPS/OTHER BUILDINGS Type OFFICES
37695.10
0
0
0
0
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
0
0
15-11-2015
30-06-2019
28-11-2019
15-11-2015
100
28-11-2019
OCCUPATION CERTIFICATE RECEIVED ON 28TH NOV 2019. SAME HAS BEEN SUBMITTED IN HARERA.
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
15-11-2015
100
28-11-2019
420
0
514
52
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
0
Shops
33790.43
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2019
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
0
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
189.8
Water Supply System
1023.0
Sewerage treatment & garbage disposal
57.8
Electricity Supply System
859.3
Storm Water Drainage
153.4
Parks and Playgrounds
0
Clubhouse/community centres
0
Shopping area
0
Other
0
Rain water harvesting
30.7
Security and Firefighting
258.7
STP
50.9
Street Lighting
18.1
Expenditure to be made in each quarter (In Lakhs)
Particulars
Expenditure to be made in each quarter (2019)
Apr-June
July-Sep
Oct-Dec
Jan-Mar
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
0
ii. No. of Flats/ Apartments booked
0
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
31158.58 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
28408.77 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
2749.81 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
1134.90 Lakhs
vii. Amount invested in the project upto the date of application
0 Lakhs
Land cost (If any)
2982.39 Lakhs
Apartments
13557.91 Lakhs
Infrastructure
2935.18 Lakhs
EDC/ Taxes Etc.
18935.8 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
4179.8 Lakhs
(a) In respect of existing allottees
0 Lakhs
(b) In respect of rest of the project
4179.8 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
12000 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
9560 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
210.84
189.8
II. WATER SUPPLY SYSTEM
1136.63
1023.0
III. STORM WATER DRAINAGE
170.50
153.4
IV. ELECTRICITY SUPPLY SYSTEM
954.78
859.3
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
64.28
57.8
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
0
0
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
287.43
258.7
XVII. OTHER FACILITIES AS PER PROJECT REPORT
110.72
99.6
Yes
Yes
HDFC BANK LTD., VATIKA ATRIUM, A BLOCK GOLF COURSE ROAD, SECTOR-53, GURUGRAM
05720350000605
HDFC0000572
110240093
000572
Authorised Signatory
Yes
Yes
No
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. AIRPORT AUTHORITY OF INDIA
ALREADY BEEN OBTAINED
14-07-2012
II. AIRPORT AUTHORITY OF INDIA RENEWAL
ALREADY BEEN OBTAINED
29-04-2017
III. ENVIRONMENT CLEARANCE
ALREADY BEEN OBTAINED
26-06-2013
IV. ENVIRONMENT CLEARANCE RENEWAL
ALREADY BEEN OBTAINED
13-07-2018
V. CONSENT TO ESTABLISH
ALREADY BEEN OBTAINED
20-02-2016
VI. BUILDING PLAN
ALREADY BEEN OBTAINED
22-08-2019
VII. ELECTRICAL SLD
ALREADY BEEN OBTAINED
30-09-2019
VIII. FIRE SCHEME
ALREADY BEEN OBTAINED
16-12-2019
IX. FIRE NOC
ALREADY BEEN OBTAINED
07-10-2019
X. OCCUPATION CERTIFICATE
ALREADY BEEN OBTAINED
28-11-2019
Yes
Yes
N/A
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following: