8800693505 (Number Shared by Promoter in Public)
info@pareena.in
http://www.pareena.in
XXXX883J
U70109DL2009PTC188725
LAXMI APARTMENTS
VILLAGE GOPAL PUR, SECTOR-99, GURUGRAM
HARSARU ST
GURUGRAM
01244078333
9818146886 (Number Shared by Promoter in Public)
info@pareena.in
MUKESH KUMAR GUPTA
01244078333
9818146886 (Number Shared by Promoter in Public)
info@pareena.in
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
1090
17-07-2017
1342100
IDBI BANK
HRERA Gurugram
5 (Acre)
225
225
5 (Acre)
license no 106 of 2014 dated 14-08-2014
Yes
13556 Lakhs
3095 Lakhs
8260 Lakhs
454.64 Lakhs
1746.36 Lakhs
Sr. No.
Land area under usage
Area of land (Acres)
1
PLOTS TO BE SOLD
0
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
1.061
3
CONSTRUCTION OF ROADS
1.369
4
PAVEMENTS
0.6
5
PARKS AND PLAYGROUNDS
0.741
6
GREEN BELTS
0.34
7
VEHICLE PARKINGS
0
8
ELECTRICITY SUB-STATION
0.103
9
CLUB HOUSE
0.048
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
0.087
13
PROPOSED
0.271
14
RAIN
0.013
Total
4.633
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HARYANA SHAHARI VIKAS PRADHIKARAN
No
WATER SUPPLY
HARYANA SHAHARI VIKAS PRADHIKARAN
No
ELECTRICITY
DAKSHIN HARYANA BIJLI VITRAN NIGAM
No
SEWAGE DISPOSAL
HARYANA SHAHARI VIKAS PRADHIKARAN
No
STORM WATER DRAINAGE
HARYANA SHAHARI VIKAS PRADHIKARAN
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
56.39
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
27.67
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
29.95
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
22.15
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
21.91
AS PER PROJECT REPORT
6
STREET LIGHTING
7.67
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
55.21
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
10.07
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
50.20
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
PARKING
14.59
AS PER PROJECT REPORT
16
STP EQUIPMENTS
38.37
AS PER PROJECT REPORT
17
UNDERGRAOUND WATER TANK
50.80
AS PER PROJECT REPORT
18
RAIN WATER HARVESTING
6.91
AS PER PROJECT REPORT
NA (date)
NA (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-1
42.135
402
399
3
9
2
APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-2
39.468
402
401
1
9
3
APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-3
59.38
33
0
33
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
TYPE-1
400
AS ANNEXURE
TYPE-2
401
AS ANNEXURE
TYPE-3
0
AS ANNEXURE
09-12-2016
14-09-2020
14-09-2020
19-07-2018
90
31-05-2020
AS ATTACHED ANNEXURE
AS ATTACHED ANNEXURE
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
0
09-05-2019
20
30-05-2020
0
0
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
6237.34
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
700
600
722.66
Shops
120
20.65
0
Plots
0
0
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
0
Water Supply System
0
Sewerage treatment & garbage disposal
0
Electricity Supply System
0
Storm Water Drainage
0
Parks and Playgrounds
0
Clubhouse/community centres
25.00
Shopping area
0
Other
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2020
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
56.39
Water Supply System
27.67
Sewerage treatment & garbage disposal
21.91
Electricity Supply System
29.82
Storm Water Drainage
29.95
Parks and Playgrounds
10.07
Clubhouse/community centres
50.20
Shopping area
120
Other
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
837
ii. No. of Flats/ Apartments booked
800
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
14293.06892 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
13580.69945 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
712.36947 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
712.36947 Lakhs
vii. Amount invested in the project upto the date of application
10012.86 Lakhs
Land cost (If any)
3095 Lakhs
Apartments
8260 Lakhs
Infrastructure
454.64 Lakhs
EDC/ Taxes Etc.
1746.36 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
3143.14 Lakhs
(a) In respect of existing allottees
3143.14 Lakhs
(b) In respect of rest of the project
4000 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
2800 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
900 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
56.39
50
II. WATER SUPPLY SYSTEM
27.67
22.65
III. STORM WATER DRAINAGE
29.95
0
IV. ELECTRICITY SUPPLY SYSTEM
22.15
20
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
21.91
20
VI. CLUB HOUSE/COMMUNITY CENTRE
50.20
45
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
10.07
7.62
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
14.59
14
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
55.21
49.65
XVII. OTHER FACILITIES AS PER PROJECT REPORT
103.75
76.05
Yes
Yes
HDFC BANK LTD JMD MEGAPOLIS
57500000138331
HDFC0003648
110240344
003648
Surender Kumar Verma resi. of Flat no. 3, the palms apartments plot no. 13B, sector 6 Dwarka, new delhi 110075 and Virender Verma resi. of Flat no. 2, the palms apartments plot no. 13B, sector 6 Dwarka, new delhi 110075
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
No
No
Statutory Approvals
Statutory Approvals Status
Date
I. BUILDING APPROVAL PLAN
ALREADY BEEN OBTAINED
25-07-2015
II. ENVIRONMENTAL CLEARANCE
ALREADY BEEN OBTAINED
15-03-2016
III. CTE
ALREADY BEEN OBTAINED
07-12-2016
IV. FOREST NOC
ALREADY BEEN OBTAINED
20-10-2015
V. ARVALI NOC
ALREADY BEEN OBTAINED
30-10-2015
VI. HEIGHT NOC
ALREADY BEEN OBTAINED
30-10-2015
Yes
Yes
MICASA VILLAGE NURPUR-JHARSA BADSHAPUR SECTOR 68, GURUGRAM, HARYANA
13.48275
952
0
417
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
42093
0
19902.82
Cost of the apartments
30467
0
12779
Cost of the infrastructure
800
0
200
Others costs
13201.67
0
6923.82
22888 Lakhs
13400.9 Lakhs
10000 Lakhs
5250 Lakhs
No
30-06-2022
30-06-2022
THE ELITE RESIDENCIES/ EXPRESS HEIGHTS
4.741
236
0
155
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
15853.01
0
7166.45
Cost of the apartments
9314.75
0
5088.50
Cost of the infrastructure
856.44
0
170.55
Others costs
5681.82
0
1907.4
7130.94 Lakhs
7332.96 Lakhs
2500 Lakhs
1500 Lakhs
No
31-07-2020
31-10-2020
COBAN RESIDENCES
10.5875
544
0
234
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
40327.48
0
15964.99
Cost of the apartments
19696.28
0
6687.17
Cost of the infrastructure
792.49
0
100
Others costs
28565.71
0
9177.82
12247.98 Lakhs
15427.12 Lakhs
5000 Lakhs
3500 Lakhs
No
11-03-2024
11-03-2024
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
TILES
2
WALL FINISHING DETAILS
OIL BOUND DISTEMPER
3
KITCHEN DETAILS
TILES
4
BATHROOM FITTINGS
UP TO 5 FEET TILES AND OIL BOUND DISTEMPER IN OTHER AREAS
5
WOOD WORK ETC
NO
6
DOORS AND WINDOS FRAMES
PAINTED MS Z SECTION
7
GLASS WORK
WINDOW GLASS IN 4MM THIK
8
ELECTRIC FITTINGS
USE OF ISI MARKED PRODUCTS FOR WIRINGS, SWITCHES AND CIRCUITS
9
CONDUCTING AND WIRING DETAILS
USE OF ISI MARKED PRODUCTS FOR WIRINGS
10
CUPBOARD DETAILS
NO
11
WATER STORAGE
OVERHEAD WATER TANK AND UNDERGROUND WATER TANK
12
LIFT DETAILS
10 PERSON AND 13 PERSONS LIFT IN EACH TOWER
13
EXTERNAL GLAZINGS
NO
13.1
WINDOWS/GLAZINGS
M.S. CHOKKAT, M.S. Z SECTION
14
DOORS
PAINTED HARDWOOD
14.1
MAIN DOORS
PAINTED HARDWOOD
14.2
INTERNAL DOORS
PAINTED HARDWOOD
15
AIR CONDITIONING
NO
16
ELECTRICAL FITTINGS
NO
17
CNG PIPE LINE
NO
18
PROVISION OF WIFI AND BROADBAND FACILITY
NO
19
EXTERNAL FINISHING/COLOUR SCHEME
OIL BOUND DISTEMPER
20
INTERNAL FINISHING
OIL BOUND DISTEMPER
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
TILES
1 . 2
WALLS
OIL BOUND DISTEMPER
1 . 3
CEILING
OIL BOUND DISTEMPER
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
TILES
2 . 2
WALLS
OIL BOUND DISTEMPER
2 . 3
CEILING
OIL BOUND DISTEMPER
2 . 4
MODULAR WARDROBES
NO
3 . MASTER TOILET
3 . 1
FLOOR
TILES
3 . 2
WALLS
UP TO 5 FEET TILES AND OIL BOUND DISTEMPER IN OTHER AREAS
3 . 3
CEILING
OIL BOUND DISTEMPER
3 . 4
COUNTERS
NO
3 . 5
SANITARY WARE/CP FITTINGS
MODERN AND ELEGANT
3 . 6
FITTING/FIXTURES
MODERN AND ELEGANT
4 . BED ROOMS
4 . 1
FLOOR
TILES
4 . 2
WALLS
OIL BOUND DISTEMPER
4 . 3
CEILING
OIL BOUND DISTEMPER
4 . 4
WARDROBES
NO
5 . TOILET
5 . 1
FLOOR
TILES
5 . 2
WALLS
UP TO 5 FEET TILES AND OIL BOUND DISTEMPER IN OTHER AREAS
5 . 3
CEILING
OIL BOUND DISTEMPER
5 . 4
COUNTERS
NO
5 . 5
SANITARY WARE/CP FITTINGS
MODERN AND ELEGANT
5 . 6
FIXTURES
MODERN AND ELEGANT
6 . KITCHEN
6 . 1
FLOOR
TILES
6 . 2
WALLS
OIL BOUND DISTEMPER
6 . 3
CEILING
OIL BOUND DISTEMPER
6 . 4
COUNTERS
MARBLE SLAB
6 . 5
FIXTURES
TILES UP TO 02 FEET HIGH ABOVE MARBLE COUNTER AND OIL BOUND DISTEMPER IN REST OF THE AREAS