HRERA GurugramTemp Project Id : RERA-GRG-PROJ-554-2020
Submission Date : 15-01-2020 11:53:55 AM
Applicant Type : Company
Project Type: NEW




RAHEJA DEVELOPERS LTD.
RAHEJA DEVELOPERS LTD. W4D,2O4/5, KESHAV KUNJ, WESTERN AVENUE, CARIAPPA MARG, SAINIK FARMS, NEW DETHI- 110062
9971091937 (Number Shared by Promoter in Public)
compliances@raheja.com
http://raheja.com
XXXX468E
U45400DL1990PLC042200
 
 


 
 


 
 


 
 







CHANDAN TOWER(TOWER-D)
RAHEJA VANYA SECTOR-99-A, GURUGRAM
GURGAON
GURUGRAM
9971091904 (Number Shared by Promoter in Public)
compliances@raheja.com
AJAY MOHANTY
9971091904 (Number Shared by Promoter in Public)
ajay.mohanty@raheja.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
150338703-07-2017994500ICICI BANKHRERA Gurugram







4.68 (Acre)
0
8.185
12.48675 (Acre)
64 of 2013 and 72 of 2014
No
Address     32, HOUSING SOCIETY, SOUTH EXTENSION PART-1, NDSE1, NEW DELHI
Address     Y-15, HAUZ KHAS, NEW DELHI
Address     32, HOUSING SOCIETY, SOUTH EXTENSION PART-1, NDSE1, NEW DELHI
Address     32, HOUSING SOCIETY, SOUTH EXTENSION PART-1, NDSE1, NEW DELHI
Annexure-B- COLLABORATION AGREEMENT
BEFORE THE GRANT OF LICENSE
Yes
YES
No
Yes
Yes







20815 Lakhs
5409 Lakhs
5862.9 Lakhs
3102 Lakhs
6440 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.2065
3CONSTRUCTION OF ROADS2.3880
4PAVEMENTS0.97
5PARKS AND PLAYGROUNDS2.4385
6GREEN BELTS0
7VEHICLE PARKINGS1.84
8ELECTRICITY SUB-STATION0
9CLUB HOUSE0.48
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0
Total8.323




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/GMDANo
WATER SUPPLYGMDANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALGMDANo
STORM WATER DRAINAGEGMDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS321SUBMITTED TO TOWN & COUNTRY PLANNING
2WATER SUPPLY SYSTEM453.71SUBMITTED TO TOWN & COUNTRY PLANNING
3STORM WATER DRAINAGE81.35SUBMITTED TO TOWN & COUNTRY PLANNING
4ELECTRICITY SUPPLY SYSTEM0YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL50SUBMITTED TO TOWN & COUNTRY PLANNING
6STREET LIGHTING14.37SUBMITTED TO TOWN & COUNTRY PLANNING
7SECURITY AND FIRE FIGHTING30.41SUBMITTED TO TOWN & COUNTRY PLANNING
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER0YET TO BE PREPARED


02-01-2017 (date)
02-01-2017 (date)
15-12-2017
31-12-2022
Plot Area(In Square Meter)Number of plots in the project
00


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings70.6221
Apartment/Shops/Other Buildings86.73841
Apartment/Shops/Other Buildings107.49431
Apartment/Shops/Other Buildings123.1561
Apartment/Shops/Other Buildings107.49181
Apartment/Shops/Other Buildings123.15151
Apartment/Shops/Other Buildings182.56391
Apartment/Shops/Other Buildings198.23131





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar












Yes
No
ICICI BANK, SAKET, NEW DELHI
017105008611
ICIC0000171
110229014
000171
Mr. Navin M. Raheja











No
No
Yes
Yes
Yes
Yes
No
No
No
No


No
No
Yes
Yes
Yes
No
No
Yes
Statutory Approvals Statutory Approvals StatusDate
I. AAI APPROVALALREADY BEEN OBTAINED31-10-2014
II. WATER SUPPLY ASSURANCEALREADY BEEN OBTAINED17-04-2017
III. SEWERAGE CONNECTION FOR STPALREADY BEEN OBTAINED21-04-2017
IV. ASSURANCE CERTIFICATE OF POWER SUPPLYALREADY BEEN OBTAINED18-11-2014
V. ENVIRONMENT CLEARANCEALREADY BEEN OBTAINED30-11-2017
VI. HUDA NOC FOR CONSTRUCTIONALREADY BEEN OBTAINED06-06-2017
VII. NOC FOR NON ARAVALLI HILLSALREADY BEEN OBTAINED17-04-2013
VIII. NON FOREST NOCALREADY BEEN OBTAINED18-03-2013
IX. RAINWATER HARVESTING NOCALREADY BEEN OBTAINED09-02-2017








Yes


Yes









RAHEJA ARANYA PHASE-II, SECTOR-11 & 14, SOHNA, MEWAT, GURUGRAM, HARYANA
45.803
0
402
0
164
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
236282362813038
Cost of the apartments000
Cost of the infrastructure000
Others costs000


11460 Lakhs
1385 Lakhs
9000 Lakhs
9000 Lakhs
Yes
01-10-2016
27-08-2022




KRISHNA HOUSING SCHEME, SECTOR- 14, SOHNA, GURUGRAM, HARYANA
10
1644
0
1509
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
21189211898935
Cost of the apartments000
Cost of the infrastructure000
Others costs000


15932 Lakhs
3679 Lakhs
5500 Lakhs
3300 Lakhs
Yes
31-07-2019
09-03-2020




TRINITY-I, SECTOR-84, GURUGRAM, HARYANA
2.281
245
0
116
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
803080301840
Cost of the apartments000
Cost of the infrastructure000
Others costs000


2644 Lakhs
182 Lakhs
6800 Lakhs
6800 Lakhs
Yes
19-06-2019
31-12-2022




MAHESHWARA (TOWER-A,B,C,D&E), SECTOR-11 & 14, SOHNA, GURUGRAM, HARYANA
3.753
276
0
112
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
275602756010659
Cost of the apartments000
Cost of the infrastructure000
Others costs000


1774 Lakhs
660 Lakhs
10000 Lakhs
4600 Lakhs
Yes
14-06-2021
03-04-2023




VANYA, TOWER A- GULMOHAR, SECTOR-99A, GURUGRAM, HARYANA
2.28
140
0
92
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
857685762210
Cost of the apartments000
Cost of the infrastructure000
Others costs000


1749 Lakhs
405 Lakhs
12000 Lakhs
6150 Lakhs
No
29-11-2022
31-12-2022




VANYA, TOWER B- AMALTAS, SECTOR- 99A, GURUGRAM, HARYANA
2.21
139
0
92
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
832283222145
Cost of the apartments000
Cost of the infrastructure000
Others costs000


645 Lakhs
102 Lakhs
12000 Lakhs
6150 Lakhs
Yes
08-12-2022
31-12-2022




VANYA, TOWER C-PALASH, SECTOR- 99A, GURUGRAM, HARYANA
2.28
140
0
80
0
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
857685761639
Cost of the apartments000
Cost of the infrastructure000
Others costs000


1466 Lakhs
411 Lakhs
12000 Lakhs
6150 Lakhs
No
08-12-2022
31-12-2022










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORLAMINATED WOODEN FLOOR
1 . 2 WALLSPLASTIC EMULSION PAINT
1 . 3 CEILINGOIL BOUND DISTEMPER WITH DESIGNER ENGINEERED CORNICE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORLAMINATED WOODEN FLOOR
2 . 2 WALLSPLASTIC EMULSION PAINT
2 . 3 CEILINGOIL BOUND DISTEMPER WITH DESIGNER ENGINEERED CORNICE
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCOMBINATION OF ONE OR MORE OF DESIGNER TILES/MARBLE
3 . 2 WALLSCOMBINATION OF ONE OR MORE OF DESIGNER TILES
3 . 3 CEILINGGYPBOARD/CALCIUM SILICATE/POP FALSE CEILING WITH INTEGRATED CFL LIGHT FITTINGS AND PROVISION FOR HIDING GEYSER OVER IT
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESSINGLE LEVER CP FITTINGS, WALL HUNG WC, SHOWER PANELS
4 . BED ROOMS
4 . 1 FLOORLAMINATED WOODEN FLOOR
4 . 2 WALLSPLASTIC EMULSION PAINT
4 . 3 CEILINGOIL BOUND DISTEMPER WITH DESIGNER ENGINEERED CORNICE
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORCOMBINATION OF ONE OR MORE OF DESIGNER TILES/MARBLE
5 . 2 WALLSCOMBINATION OF ONE OR MORE OF DESIGNER TILES
5 . 3 CEILINGGYPBOARD/CALCIUM SILICATE/POP FALSE CEILING WITH INTEGRATED CFL LIGHT FITTINGS AND PROVISION FOR HIDING GEYSER OVER IT
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESSINGLE LEVER CP FITTINGS, WALL HUNG WC, SHOWER PANELS
6 . KITCHEN
6 . 1 FLOORCOMBINATION OF ONE OR MORE OF DESIGNER TILES/GRANITE/MARBLE
6 . 2 WALLS2' HIGH GLAZED TILES ABOVE COUNTER AND OIL BOUND DISTEMPER ON REMAINING AREA
6 . 3 CEILINGOIL BOUND DISTEMPER
6 . 4 COUNTERSNA
6 . 5 FIXTURESGRANITE COUNTER, SS SINK AND CP FITTINGS
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD09-01-2020 View Document
2DEMARCATION PLAN09-01-2020 View Document
3CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT09-01-2020 View Document
4CASH FLOW STATEMENT OF THE PROPOSED PROJECT09-01-2020 View Document
5DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.09-01-2020 View Document
6IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN09-01-2020 View Document
7COPY OF LICENSE ALONG WITH SCHEDULE OF LAND09-01-2020 View Document
8SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN09-01-2020 View Document
9IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN09-01-2020 View Document
10NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT09-01-2020 View Document
11ZONING PLAN09-01-2020 View Document
12A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS09-01-2020 View Document