HRERA GurugramTemp Project Id : RERA-GRG-PROJ-543-2019
Submission Date : 31-12-2019 10:14:10 AM
Applicant Type : Company
Project Type: ONGOING




ALTON BUILDTECH INDIA PVT. LTD.
ADANI HOUSE, PLOT NO 83, INSTITUTIONAL AREA, SECTOR 32, GURUGRAM 122001
01242555155
9910661818 (Number Shared by Promoter in Public)
aangan-gurgaon@adanirealty.com
http://adanirealty.com/aangan
XXXX626P
U70200GJ2013PTC094186
 
 


 
 


 
 


 
 







AANGAN/PHASE II
SECTOR 88A & 89A
HARSARU ST
GURUGRAM
9990136813 (Number Shared by Promoter in Public)
prem.hatwal@adani.com
MR PREM HATWAL
9990136813 (Number Shared by Promoter in Public)
prem.hatwal@adani.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
1541102-12-2017179225AXIS BANKHRERA Gurugram







1.8125 (Acre)
5.0699
4.6761
1.8125 (Acre)
27 Of 2016 (16.12.2016)
Yes







5647 Lakhs
872 Lakhs
3806 Lakhs
285 Lakhs
684 Lakhs




Sr. No.Land area under usageArea of land (Acres)
1PLOTS TO BE SOLD0
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0.3247
3CONSTRUCTION OF ROADS0.4359
4PAVEMENTS0.2349
5PARKS AND PLAYGROUNDS0.2561
6GREEN BELTS0.1605
7VEHICLE PARKINGS0.3707
8ELECTRICITY SUB-STATION0.0409
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0.0077
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES0
12ANY OTHER0.3519
Total2.1833




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/GMDANo
WATER SUPPLYHUDA/GMDANo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHUDA/GMDANo
STORM WATER DRAINAGEHUDA/GMDANo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS58YET TO BE PREPARED
2WATER SUPPLY SYSTEM14YET TO BE PREPARED
3STORM WATER DRAINAGE13YET TO BE PREPARED
4ELECTRICITY SUPPLY SYSTEM157YET TO BE PREPARED
5SEWAGE TREATMENT & GARBAGE DISPOSAL41YET TO BE PREPARED
6STREET LIGHTING0YET TO BE PREPARED
7SECURITY AND FIRE FIGHTING0YET TO BE PREPARED
8PLAYGROUNDS AND PARKS0YET TO BE PREPARED
9CLUB HOUSE/COMMUNITY CENTRE0YET TO BE PREPARED
10SHOPPING AREA0YET TO BE PREPARED
11RENEWABLE ENERGY SYSTEM0YET TO BE PREPARED
12SCHOOL0YET TO BE PREPARED
13HOSPITAL/DISPENSARY0YET TO BE PREPARED
14ANY OTHER2YET TO BE PREPARED


12-07-2017 (date)
28-11-2017 (date)


Sr. No.Plot/ apartment type Size of the plot/carpet area of the apartmentsTotal number of plots/apartments in the projectPlots/apartments booked/ sold upto the date of applicationYet to be sold/ bookedNo. of towers to be/ being constructed for booked apartments
1APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-116012011821
2APARTMENT/SHOPS/OTHER BUILDINGS Type TYPE-126011811441
3APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 110.916960961
4APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 210.033170171
5APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 311.812210211
6APARTMENT/SHOPS/OTHER BUILDINGS Type SHOP TYPE 411.597480481






TypeNumber of apartments booked/ sold Write or Annex the stage of construction of the booked/ sold apartments in folder C
TYPE-111180
TYPE-121140


22-12-2017
15-12-2022
14-06-2024
22-12-2017
0
15-12-2022
ATTACHED
ANNEXURE-C


PlotsBooked/soldStage of handing over the possession (Write or Annex details)
PLOT00
22-12-2017
0
15-12-2022


0
38
0
229
0





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments756
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0381
Shops00
Plots00

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments381381381381
Shops0000
Plots0000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments381381
Shops00
Plots00




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements1212
Water Supply System33
Sewerage treatment & garbage disposal88
Electricity Supply System3131
Storm Water Drainage33
Parks and Playgrounds00
Clubhouse/community centres00
Shopping area00
Other11

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements121212
Water Supply System333
Sewerage treatment & garbage disposal888
Electricity Supply System313131
Storm Water Drainage330
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other110












Particulars Remarks, if any
i. No. of Flats/Apartments constructed420
ii. No. of Flats/ Apartments booked234
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter6162 LakhsExcluding Taxes
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter2864 LakhsIncluding Taxes
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter3112 LakhsUndemand sale price including taxes
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter355 LakhsUnpaid demand including taxes
vii. Amount invested in the project upto the date of application2050 Lakhs
Land cost (If any)872 Lakhs
Apartments756 Lakhs
Infrastructure0 Lakhs
EDC/ Taxes Etc.422 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession3597 LakhsTotal Estimated project cost (Rs 5647 Lakhs) Less Cost incured upto 30.09.2019 (Rs 2050 Lakhs)
(a) In respect of existing allottees2999 Lakhs
(b) In respect of rest of the project598 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project
Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
0 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C) 0 LakhsNo major overdue, only current bills of vendors and contractor are outstanding



Particulars Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS580
II. WATER SUPPLY SYSTEM140
III. STORM WATER DRAINAGE130
IV. ELECTRICITY SUPPLY SYSTEM1570
V. SEWAGE TREATMENT & GARBAGE DISPOSAL410
VI. CLUB HOUSE/COMMUNITY CENTRE00
VII. SCHOOL00
VIII. ANY OTHER20
IX. SOLID WASTE COLLECTION & MGMT SYSTEM00
X. CLUBHOUSE00
XI. NEIGHBOURHOOD SHOPPING00
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.00
XIII. COVERED PARKING00
XIV. OPEN PARKING00
XV. GARAGES00
XVI. SECURITY SYSTEM00
XVII. OTHER FACILITIES AS PER PROJECT REPORT00









Yes
Yes
HDFC BANK LTD, SCO – 7, SECTOR 31-32, MAIN MARKET, GURUGRAM, HARYANA - 122001
50200040767791
HDFC0000622
11024111
0622
Mr. Sanjay Kumar Mishra
Uploaded











Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes


Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals Statutory Approvals StatusDate
I. AIRPORT HEIGHT CLEARANCE NOCALREADY BEEN OBTAINED02-01-2015
II. FOREST NOCALREADY BEEN OBTAINED12-01-2018
III. CONSENT TO ESTABLISHALREADY BEEN OBTAINED14-06-2019
IV. ENVIRONMENTAL CLEARANCEALREADY BEEN OBTAINED02-05-2019
V. LICENCEALREADY BEEN OBTAINED16-12-2016
VI. HUDA CONSTRUCTION WATER NOCALREADY BEEN OBTAINED05-08-2015
VII. ELECTRICAL LOAD AVAILABILITYAPPLIED FOR BUT YET TO RECEIVENA
VIII. FIRE SCHEME APPROVALAPPLIED FOR BUT YET TO RECEIVENA
IX. SERVICE ESTIMATE PLANSYET TO FILE FOR APPROVALNA








Yes


Yes















SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSE1 HABITABLE SPACES- VITRIFED TILE. 2 TOILET & BALCONY - CERAMIC TILE
2WALL FINISHING DETAILSOBD PAINT
3KITCHEN DETAILS1. KITCHEN PLATE FORM -GREEN MARBLE. 2 DADO ABOVE PLATFORM-CERAMIC (600 MM HEIGHT)
4BATHROOM FITTINGSC.P FITTING
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMES1. DOOR FRAME -WOODEN 2 WINDOWS- M S Z SECTION
7GLASS WORKNA
8ELECTRIC FITTINGSLED FITTING IN COMMON AREAS
9CONDUCTING AND WIRING DETAILSPVC CONDUITING & COPPER WIRING
10CUPBOARD DETAILSNA
11WATER STORAGERCC OVER HEAD & UNDER GROUND TANK
12LIFT DETAILSTWO NOS IN EACH TOWER ( 1 PASSENGER & 1 STRETCHER CUM FIRE LIFT )
13EXTERNAL GLAZINGS10 MM THICK TOUGHEN GLASS FOR AANGAN WADI & COMMUNITY HALL
13.1WINDOWS/GLAZINGS4 MM THICK PLAIN GLASS / FROASTED GLASS IN TOILET
14DOORSFLUSH DOOR
14.1MAIN DOORS32 MM THICK FLUSH DOOR BOTH SIDE LAMINATED
14.2INTERNAL DOORS30 MM THICK FLUSH WITH PAINTING
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSELECTRICAL POINTS WITH SWTCH & SOCKET AND DB
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMEWHEATHER PROOF PAINT ( WHITE AND BEIGE)
20INTERNAL FINISHINGOBD PAINT
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORVITRIFED TILE
1 . 2 WALLSOBD PAINT
1 . 3 CEILINGWHITE WASH
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORVITRIFIED TILE
2 . 2 WALLSOBD PAINT
2 . 3 CEILINGWHITE WASH
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORCERAMIC TILE
3 . 2 WALLSCERMIC TILE UPTO 2100 MM & OBD
3 . 3 CEILINGWHITE WASH
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSCHINA WARE & CP FITTING
3 . 6 FITTING/FIXTURES NA
4 . BED ROOMS
4 . 1 FLOORVITRIFIED TILE
4 . 2 WALLSOBD PAINT
4 . 3 CEILINGWHITE WASH
4 . 4 WARDROBES NA
5 . TOILET
5 . 1 FLOORCERAMIC TILE
5 . 2 WALLSCERMIC TILE UPTO 2100 MM & OBD PAINT
5 . 3 CEILINGWHITE WASH
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSCHINA WARE & CP FITTING
5 . 6 FIXTURES NA
6 . KITCHEN
6 . 1 FLOORVITRIFIED TILE
6 . 2 WALLSCERAMIC (600 MM HEIGHT) ABOVE COUNTER REST OBD PAINT
6 . 3 CEILINGWHITE WASH
6 . 4 COUNTERSGREEN MARBLE.
6 . 5 FIXTURESSS SINK & CP FITTING
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORCERAMIC TILE
7 . 2 WALLS & CEILINGWHEATHER PROOF PAINT
7 . 3 TOILETNA
7 . 4 BALCONYCERAMIC TILE
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1CASH FLOW STATEMENT OF THE PROPOSED PROJECT31-12-2019 View Document
2IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN31-12-2019 View Document
3DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.31-12-2019 View Document
4SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN31-12-2019 View Document
5COPY OF LICENSE ALONG WITH SCHEDULE OF LAND31-12-2019 View Document
6IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN31-12-2019 View Document
7CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT31-12-2019 View Document
8ZONING PLAN31-12-2019 View Document
9NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT31-12-2019 View Document
10DEMARCATION PLAN31-12-2019 View Document
11DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD31-12-2019 View Document
12A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS31-12-2019 View Document