HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-790-2019
Submission Date : 25-01-2020 04:08:35 AM
Applicant Type : Company
Project Type: NEW




SAVYASACHI INFRASTRUCTURE PRIVATE LIMITED
251-252, SPAZEDGE BUILDING, TOWER-B, SECTOR- 47, SOHNA ROAD, GURUGRAM-122018
01244143335
9911200027 (Number Shared by Promoter in Public)
md@savyasachi.in
http://www.savyasachi.in
XXXX976B
U70109HR2013PTC049609
 
 


 
 


 
 







AMAYA GREENS
VILLAGE-HARCHANDPUR, SECTOR-77, (OLD SECTOR-10A, BAWAL)
BAWAL
REWARI
01244143335
9818110199 (Number Shared by Promoter in Public)
md@savyasachi.in
DIPAK CHAKRABORTY
01244143335
9818110199 (Number Shared by Promoter in Public)
md@savyasachi.in








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
181918426-12-2019425000.00YES BANK LTD.HRERA Panchkula







42491.93 (Sqr/mtrs)
61
53.37
10.50 (Sqr/mtrs)
100 of 2017 Dated 23.11.2017
No
Address     M-166, SECOND FLOOR, SOUTH CITY-I, GURUGRAM, HARYANA-122001
Address     G-116, GROUND FLOOR, SUSHANT LOK, PHASE-I, GURUGRAM-122009
Address     G-116, GROUND FLOOR, SUSHANT LOK, PHASE-I, GURUGRAM-122009
Address     G-116, GROUND FLOOR, SUSHANT LOK, PHASE-I, GURUGRAM-122009
Annexure-B- COLLABORATION AGREEMENT REVENUE RECORDS ETC
AFTER
Yes
PROVIDED
No
Yes
Yes







2670.72 Lakhs
1111.00 Lakhs
0 Lakhs
867.30 Lakhs
692.42 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD 22679.30
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS 0
3CONSTRUCTION OF ROADS 0
4PAVEMENTS 0
5PARKS AND PLAYGROUNDS 0
6GREEN BELTS 0
7VEHICLE PARKINGS 0
8ELECTRICITY SUB-STATION 0
9CLUB HOUSE 0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY 0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES 4251.00
12ANY OTHER 10676.23
13GREEN 3187.40
14COMMERCIAL 1698.00
Total42491.93




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHUDA/HSVPNo
WATER SUPPLYHUDA/HSVPNo
ELECTRICITYDHBVNNo
SEWAGE DISPOSALHUDA/HSVPNo
STORM WATER DRAINAGEHUDA/HSVPNo




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS158.92AS PER PROJECT REPORT
2WATER SUPPLY SYSTEM203.64AS PER PROJECT REPORT
3STORM WATER DRAINAGE66.76AS PER PROJECT REPORT
4ELECTRICITY SUPPLY SYSTEM265.17AS PER PROJECT REPORT
5SEWAGE TREATMENT & GARBAGE DISPOSAL127.74AS PER PROJECT REPORT
6STREET LIGHTING40.29AS PER PROJECT REPORT
7SECURITY AND FIRE FIGHTING0AS PER PROJECT REPORT
8PLAYGROUNDS AND PARKS4.81AS PER PROJECT REPORT
9CLUB HOUSE/COMMUNITY CENTRE0AS PER PROJECT REPORT
10SHOPPING AREA0AS PER PROJECT REPORT
11RENEWABLE ENERGY SYSTEM0AS PER PROJECT REPORT
12SCHOOL0AS PER PROJECT REPORT
13HOSPITAL/DISPENSARY0AS PER PROJECT REPORT
14ANY OTHER0AS PER PROJECT REPORT


NA (date)
NA (date)
26-02-2020
22-11-2022
Sr. No Plot Area(In Square Meter)Number of plots in the project
1 22679.30 211
Total211


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0.01

Expenditure to be made in each quarter (In Lakhs)

ParticularsExpenditure to be made in each quarter ()
Apr-JuneJuly-SepOct-DecJan-Mar




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2020
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System0045.25
Sewerage treatment & garbage disposal028.3842.58
Electricity Supply System000
Storm Water Drainage22.2533.3811.12
Parks and Playgrounds000
Clubhouse/community centres000
Shopping area000
Other000

ParticularsYear-2021
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0000
Water Supply System67.8867.8822.620
Sewerage treatment & garbage disposal42.5814.1900
Electricity Supply System0042.2172.32
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other0000

ParticularsYear-2022
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements15.9447.6747.6747.67
Water Supply System0000
Sewerage treatment & garbage disposal0000
Electricity Supply System72.3272.3200
Storm Water Drainage0000
Parks and Playgrounds001.203.61
Clubhouse/community centres0000
Shopping area0000
Other0000
Street Light5.7617.2717.27












Yes
Yes
IDFC BANK, NO. 3/A, GROUND FLOOR, MEGA CITY MALL, M. G. ROAD, GURUGRAM-122002
10051456356
IDFB0021002
110751011
21002
Mr Dipak Chakrobarty School, 59, Ganga Apartment, 2nd Floor, Alaknanda, Ali, South Delhi-110019 Mr Jai Parkash Ward No. 5, Pana Chulyan, Beri, Jhajjar, Haryana-124201
Provided











Yes
No
Yes
Yes
Yes
No
No
No
Yes
Yes


Yes
No
Yes
Yes
Yes
No
Yes
No
Statutory Approvals Statutory Approvals StatusDate
I. LAY OUT PLANALREADY BEEN OBTAINED23-11-2017
II. ZONING PLANALREADY BEEN OBTAINED07-05-2018
III. SITE PLANALREADY BEEN OBTAINED23-11-2017








Yes


Yes


Provided







AMAYA GREENS (FARRUKHNAGAR)
9.0375
0
209
0
15
Initially estimated cost (In Lakhs)Revised cost (In Lakhs)Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project
(Other than cost of land)
2488.382488.38832.22
Cost of the apartments000
Cost of the infrastructure1936.751936.75692.50
Others costs551.64551.64139.72


1348.60 Lakhs
296.51 Lakhs
0 Lakhs
0 Lakhs
No
31-12-2020
31-12-2020










SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENOT APPLICABLE
2WALL FINISHING DETAILSNOT APPLICABLE
3KITCHEN DETAILSNOT APPLICABLE
4BATHROOM FITTINGSNOT APPLICABLE
5WOOD WORK ETCNOT APPLICABLE
6DOORS AND WINDOS FRAMESNOT APPLICABLE
7GLASS WORKNOT APPLICABLE
8ELECTRIC FITTINGSNOT APPLICABLE
9CONDUCTING AND WIRING DETAILSNOT APPLICABLE
10CUPBOARD DETAILSNOT APPLICABLE
11WATER STORAGENOT APPLICABLE
12LIFT DETAILSNOT APPLICABLE
13EXTERNAL GLAZINGSNOT APPLICABLE
13.1WINDOWS/GLAZINGSNOT APPLICABLE
14DOORSNOT APPLICABLE
14.1MAIN DOORSNOT APPLICABLE
14.2INTERNAL DOORSNOT APPLICABLE
15AIR CONDITIONINGNOT APPLICABLE
16ELECTRICAL FITTINGSNOT APPLICABLE
17CNG PIPE LINENOT APPLICABLE
18PROVISION OF WIFI AND BROADBAND FACILITYNOT APPLICABLE
19EXTERNAL FINISHING/COLOUR SCHEMENOT APPLICABLE
20INTERNAL FINISHINGNOT APPLICABLE
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNOT APPLICABLE
1 . 2 WALLSNOT APPLICABLE
1 . 3 CEILINGNOT APPLICABLE
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNOT APPLICABLE
2 . 2 WALLSNOT APPLICABLE
2 . 3 CEILINGNOT APPLICABLE
2 . 4 MODULAR WARDROBESNOT APPLICABLE
3 . MASTER TOILET
3 . 1 FLOORNOT APPLICABLE
3 . 2 WALLSNOT APPLICABLE
3 . 3 CEILINGNOT APPLICABLE
3 . 4 COUNTERSNOT APPLICABLE
3 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
3 . 6 FITTING/FIXTURESNOT APPLICABLE
4 . BED ROOMS
4 . 1 FLOORNOT APPLICABLE
4 . 2 WALLSNOT APPLICABLE
4 . 3 CEILINGNOT APPLICABLE
4 . 4 WARDROBESNOT APPLICABLE
5 . TOILET
5 . 1 FLOORNOT APPLICABLE
5 . 2 WALLSNOT APPLICABLE
5 . 3 CEILINGNOT APPLICABLE
5 . 4 COUNTERSNOT APPLICABLE
5 . 5 SANITARY WARE/CP FITTINGSNOT APPLICABLE
5 . 6 FIXTURESNOT APPLICABLE
6 . KITCHEN
6 . 1 FLOORNOT APPLICABLE
6 . 2 WALLSNOT APPLICABLE
6 . 3 CEILINGNOT APPLICABLE
6 . 4 COUNTERSNOT APPLICABLE
6 . 5 FIXTURESNOT APPLICABLE
6 . 6 KITCHEN APPLIANCESNOT APPLICABLE
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNOT APPLICABLE
7 . 2 WALLS & CEILINGNOT APPLICABLE
7 . 3 TOILETNOT APPLICABLE
7 . 4 BALCONYNOT APPLICABLE
8 . SIT-OUTS
8 . 1 FLOORNOT APPLICABLE
8 . 2 WALLS & CEILINGNOT APPLICABLE
8 . 3 RAILINGSNOT APPLICABLE
8 . 4 FIXTURESNOT APPLICABLE












Sr. No.Document DescriptionDate of Document UploadView Document
1 JOINT DEVELOPMENT AGREEMENT 25-01-2020 View Document
2 LOI (LETTER OF INTENT) 25-01-2020 View Document
3 IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN 24-01-2020 View Document
4 COPY OF DEMAND DRAFT 25-01-2020 View Document
5 JAMABANDI 25-01-2020 View Document
6 ARAVALI NOC 24-01-2020 View Document
7 REGISTRIES 24-01-2020 View Document
8 AKS 25-01-2020 View Document
9 CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT 24-01-2020 View Document
10 BALANCE SHEET (2017-18) 24-01-2020 View Document
11 SPECIAL POWER OF ATTORNEY 24-01-2020 View Document
12 NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT 24-01-2020 View Document
13 COMPANY MASTER DATA 25-01-2020 View Document
14 COPY OF LICENSE ALONG WITH SCHEDULE OF LAND 24-01-2020 View Document
15 ZONING PLAN 24-01-2020 View Document
16 PROJECT REPORT 24-01-2020 View Document
17 MOA 25-01-2020 View Document
18 LETTER TO DRO 25-01-2020 View Document
19 CLARIFICATION LETTER BY FOREST 24-01-2020 View Document
20 CASH FLOW STATEMENT 25-01-2020 View Document
21 CASH FLOW STATEMENTS 24-01-2020 View Document
22 BALANCE SHEET 24-01-2020 View Document
23 SIZRA 25-01-2020 View Document
24 SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN 24-01-2020 View Document
25 FORM, ALLOTMENT & BBA 25-01-2020 View Document
26 ELECTRICAL LOAD DETAIL 24-01-2020 View Document
27 IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN 24-01-2020 View Document
28 LETTER TO TOWN & COUNTRY PLANNING TO CHANGE THE DEVELOPER 24-01-2020 View Document
29 INVENTORY 25-01-2020 View Document
30 GENERAL POWER OF ATTORNEY 24-01-2020 View Document
31 CASH FLOW STATEMENT OF THE PROPOSED PROJECT 25-01-2020 View Document
32 DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD 25-01-2020 View Document
33 QUARTERLY FINANCIAL AND PHYSICAL PROGRESS 24-01-2020 View Document
34 DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED. 25-01-2020 View Document
35 LOI 25-01-2020 View Document
36 FORM & ALLOTMENT LETTER & BUILDER BUYER AGREEMENT 24-01-2020 View Document
37 DIR 11 AND 12 25-01-2020 View Document
38 BALANCE SHEET (2016-17) 24-01-2020 View Document
39 COLLABORATION 24-01-2020 View Document
40 DEVELOPMENT WORK PLAN 25-01-2020 View Document
41 BANK DETAIL WITH BOARD RESOLUTION 25-01-2020 View Document
42 DETAIL OF ARCHITECT AND CA 25-01-2020 View Document