HRERA PanchkulaTemp Project Id : RERA-PKL-PROJ-788-2019
Submission Date : 24-12-2019 10:29:30 AM
Applicant Type : Individual
Project Type: NEW




UDAY BHAN
ROHTAS SINGH
01244275594
 (Number Shared by Promoter in Public)
zapy1617@gmail.com
https://haryanarera.gov.in
XXXX304H
_______________









KESHV KUNJ SECTOR 32
V.P.O MAJRA GURDAS
REWARI
REWARI
9958753242
9958753242 (Number Shared by Promoter in Public)
zapy1617@gmail.com
UDAY BHAN
9958753242
9958753242 (Number Shared by Promoter in Public)
zapy1617@gmail.com








As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
-----------------------------------------------------------------------------------------------------------------------
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-

Sr No.Draft/Cheque No.Draft DateAmountPayee BankPayable To
13818-07-2017168000AXIS BANKHRERA Panchkula







5.5125 (Acre)
200
200
5.5125 (Acre)
9 of 2017
Yes







0 Lakhs
0 Lakhs
0 Lakhs
427.10 Lakhs
95.49 Lakhs




Sr. No.Land area under usageArea of land (Square Meters)
1PLOTS TO BE SOLD11052
2LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS0
3CONSTRUCTION OF ROADS0
4PAVEMENTS0
5PARKS AND PLAYGROUNDS1666
6GREEN BELTS0
7VEHICLE PARKINGS0
8ELECTRICITY SUB-STATION80
9CLUB HOUSE0
10SEWAGE AND SOLID WASTE TREATMENT FACILITY0
11AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES2223
12ANY OTHER0
Total15021




FacilityExternal/ connecting service to be provided by (Name the agency)Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADSHSVPYes
WATER SUPPLYHSVPYes
ELECTRICITYDHBVNLYes
SEWAGE DISPOSALHSVPYes
STORM WATER DRAINAGEHSVPYes




Sr. No.Name of the facilityEstimated cost (In Lakhs)(Within the project area only)Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1INTERNAL ROADS AND PAVEMENTS94.20SUBMITTED TO HUDA
2WATER SUPPLY SYSTEM147.50SUBMITTED TO HUDA
3STORM WATER DRAINAGE38.00SUBMITTED TO HUDA
4ELECTRICITY SUPPLY SYSTEM0SUBMITTED TO HUDA
5SEWAGE TREATMENT & GARBAGE DISPOSAL72.90SUBMITTED TO HUDA
6STREET LIGHTING9.70SUBMITTED TO HUDA
7SECURITY AND FIRE FIGHTING0SUBMITTED TO HUDA
8PLAYGROUNDS AND PARKS0SUBMITTED TO HUDA
9CLUB HOUSE/COMMUNITY CENTRE0SUBMITTED TO HUDA
10SHOPPING AREA0SUBMITTED TO HUDA
11RENEWABLE ENERGY SYSTEM0SUBMITTED TO HUDA
12SCHOOL0SUBMITTED TO HUDA
13HOSPITAL/DISPENSARY0SUBMITTED TO HUDA
14ANY OTHER10.20SUBMITTED TO HUDA


NA (date)
NA (date)
01-07-2017
30-04-2019
Plot Area(In Square Meter)Number of plots in the project
11052109


TypeCarpet area(In Square Meter)Number of apartmentsNumber of towers
Apartment/Shops/Other Buildings000





Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Apartments0
Shops0
Plots0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Apartments0
Shops0
Plots0




Expenditure incurred till the date of application (In Lakhs)

ParticularsExpenditure
Roads & Pavements0
Water Supply System0
Sewerage treatment & garbage disposal0
Electricity Supply System0
Storm Water Drainage0
Parks and Playgrounds0
Clubhouse/community centres0
Shopping area0
Other0

Expenditure to be made in each quarter (In Lakhs)

ParticularsYear-2018
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements0085.0927.85
Water Supply System0000
Sewerage treatment & garbage disposal00026.10
Electricity Supply System0000
Storm Water Drainage0000
Parks and Playgrounds0000
Clubhouse/community centres0000
Shopping area0000
Other033.8000

ParticularsYear-2019
Jan-MarApr-JuneJuly-SepOct-Dec
Roads & Pavements000
Water Supply System40.5500
Sewerage treatment & garbage disposal50.9900
Electricity Supply System030.720
Storm Water Drainage000
Parks and Playgrounds30.5300
Clubhouse/community centres000
Shopping area000
Other0.79016.70












No
No
SCO NO 20 GF SECTOR 10A GURGAON PIN-122001
91702008442675
UTIB0001264
110211103
1264
Uday Bhan ,Address:-1606A Housing board colony Sector 10A gurgaon
No default / This is first project











Yes
Yes
Yes
No
No
No
No
No
No
No


Yes
No
Yes
No
Yes
Yes
No
No
Statutory Approvals Statutory Approvals StatusDate
I. COMPLETION FROM DTCP RECIVEDALREADY BEEN OBTAINED25-10-2019
II. ELECTRICAL APPROVAL FROM DHBVNLALREADY BEEN OBTAINED16-07-2018
III. SERVICE PLAN APPROVAL BY DTCPALREADY BEEN OBTAINED30-01-2019








Yes


Yes


we are using the Draft as suggested by HRERA same language













SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1FLOORING DETAILS OF VARIOUS PARTS OF HOUSENA BECAUSE PLOTTED COLONY
2WALL FINISHING DETAILSNA
3KITCHEN DETAILSNA
4BATHROOM FITTINGSNA
5WOOD WORK ETCNA
6DOORS AND WINDOS FRAMESNA
7GLASS WORKNA
8ELECTRIC FITTINGSNA
9CONDUCTING AND WIRING DETAILSNA
10CUPBOARD DETAILSNA
11WATER STORAGENA
12LIFT DETAILSNA
13EXTERNAL GLAZINGSNA
13.1WINDOWS/GLAZINGSNA
14DOORSNA
14.1MAIN DOORSNA
14.2INTERNAL DOORSNA
15AIR CONDITIONINGNA
16ELECTRICAL FITTINGSNA
17CNG PIPE LINENA
18PROVISION OF WIFI AND BROADBAND FACILITYNA
19EXTERNAL FINISHING/COLOUR SCHEMENA
20INTERNAL FINISHINGNA
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1 FLOORNA
1 . 2 WALLSNA
1 . 3 CEILINGNA
2 . MASTER BEDROOM/DRESSROOM
2 . 1 FLOORNA
2 . 2 WALLSNA
2 . 3 CEILINGNA
2 . 4 MODULAR WARDROBESNA
3 . MASTER TOILET
3 . 1 FLOORNA
3 . 2 WALLSNA
3 . 3 CEILINGNA
3 . 4 COUNTERSNA
3 . 5 SANITARY WARE/CP FITTINGSNA
3 . 6 FITTING/FIXTURESNA
4 . BED ROOMS
4 . 1 FLOORNA
4 . 2 WALLSNA
4 . 3 CEILINGNA
4 . 4 WARDROBESNA
5 . TOILET
5 . 1 FLOORNA
5 . 2 WALLSNA
5 . 3 CEILINGNA
5 . 4 COUNTERSNA
5 . 5 SANITARY WARE/CP FITTINGSNA
5 . 6 FIXTURESNA
6 . KITCHEN
6 . 1 FLOORNA
6 . 2 WALLSNA
6 . 3 CEILINGNA
6 . 4 COUNTERSNA
6 . 5 FIXTURESNA
6 . 6 KITCHEN APPLIANCESNA
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1 FLOORNA
7 . 2 WALLS & CEILINGNA
7 . 3 TOILETNA
7 . 4 BALCONYNA
8 . SIT-OUTS
8 . 1 FLOORNA
8 . 2 WALLS & CEILINGNA
8 . 3 RAILINGSNA
8 . 4 FIXTURESNA












Sr. No.Document DescriptionDate of Document UploadView Document
1COPY OF LICENSE ALONG WITH SCHEDULE OF LAND21-12-2019 View Document
2DEMARCATION PLAN22-12-2019 View Document
3COMPLETION CERTIFICATE BY DTCP PAGE 122-12-2019 ------
4COMPLETION CERTIFICATE PAGE 222-12-2019 ------
5ELECTRICAL APPROVAL PAGE222-12-2019 ------
6ZONING PLAN22-12-2019 View Document
7SERVICE PLAN SHOWING ROAD PLAN23-12-2019 ------
8A COMPLETE SET OF THE LAST APPROVED BUILDING PLANS24-12-2019 View Document
9ELECTRICAL LOAD AND OTHER APPROVAL BY DHBVNL DT16.07.2018 PAGE 122-12-2019 ------
10CASH FLOW STATEMENT OF THE PROPOSED PROJECT24-12-2019 View Document
11SERVICE PLAN SHOWING STROME WATER23-12-2019 ------
12CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT24-12-2019 View Document
13SERVICE PLANS SHOWING THE SERVICES ON THE LAYOUT PLAN23-12-2019 View Document
14IN CASE OF GROUP HOUSING/ COMMERCIAL SITES, A COPY OF THE APPROVED SITE PLAN24-12-2019 View Document
15NON DEFAULT CERTIFICATE FROM A CHARTERED ACCOUNTANT24-12-2019 View Document
16DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.24-12-2019 View Document
17COMMUNITY SITE LATEST MUTATION22-12-2019 ------
18SERVICE PLAN SHOWING WATER SUPPLY23-12-2019 ------
19DOCUMENTS RELATING TO THE ENTRY OF LICENSE AND COLLABORATION AGREEMENT IN THE REVENUE RECORD24-12-2019 View Document
20COMMUNITY SITE MUTATION SHOWING THAT SITE TRANSFERED TO DTCP22-12-2019 ------
21IN CASE OF PLOTTED COLONY, THE LATEST LAYOUT PLAN22-12-2019 View Document












Sr. No.Document DescriptionDate of Document UploadView Document
1 Completion Certificate uploaded 12-06-2023 View Document