VATIKA TRIANGLE, 4TH FLOOR, SUSHANT LOK, PHASE-I, BLOCK-A, M. G. ROAD, GURUGRAM-122 002.
01244177777
9810566938 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
http://www.vatikagroup.com
XXXX647G
U74899HR1998PLC054821
LIFESTYLE HOMES (BLOCK A)
SECTOR-83, VILLAGE SIHI
MANESAR
GURUGRAM
0000000000
8800772626 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
ARUP KUMAR DAS
0000000000
8800772626 (Number Shared by Promoter in Public)
vatika.rera@vatikagroup.com
As per sub-rule(2) of rule 3 of the Haryana Real Estate (Regulation and Development) Rules,2017, the fee for registration of the project as has been calculated as follows:
2. The aforesaid fees is hereby deposited vide following Drafts/ Banker’s Cheques:-
Sr No.
Draft/Cheque No.
Draft Date
Amount
Payee Bank
Payable To
1
56941
28-07-2017
107000
HDFC BANK LIMITED
HRERA Gurugram
12.83 (Acre)
175
168.331
12.83 (Acre)
License No. 113 of 2008 dated 01.06.2008, License No. 71 of 2010 dated 15.09.2010 and 62 of 2011 dated 02.07.2011.
No
Address VATIKA TRIANGLE, 4TH FLOOR, SUSHANT LOK, PHASE-I, BLOCK-A, M. G. ROAD, GURUGRAM-122 002
Address FLAT NO. 224A, 2ND FLOOR DEVIKA TOWER, 6, NEHRU PLACE NEW DELHI SOUTH DELHI - 110019
Address FLAT NO. 224A, 2ND FLOOR DEVIKA TOWER, 6, NEHRU PLACE NEW DELHI SOUTH DELHI - 110019
Address FLAT NO. 224A, 2ND FLOOR DEVIKA TOWER, 6, NEHRU PLACE NEW DELHI SOUTH DELHI - 110019
Annexure-B- COLLABORATION AGREEMENT, REVENUE RECORD, ETC.
BEFORE GRANT OF LICENSE
No
PROVIDED
No
Yes
Yes
3983.00 Lakhs
296.00 Lakhs
2430.00 Lakhs
270.00 Lakhs
987.00 Lakhs
Sr. No.
Land area under usage
Area of land (Square Meters)
1
PLOTS TO BE SOLD
809.36
2
LAND AREA TO BE USED FOR CONSTRUCTION OF APARTMENTS
10733.442
3
CONSTRUCTION OF ROADS
12842
4
PAVEMENTS
0
5
PARKS AND PLAYGROUNDS
7964.691
6
GREEN BELTS
0
7
VEHICLE PARKINGS
6375
8
ELECTRICITY SUB-STATION
0
9
CLUB HOUSE
354.617
10
SEWAGE AND SOLID WASTE TREATMENT FACILITY
0
11
AREA TO BE LEFT FOR TRANSFERRING TO THE GOVERNMENT FOR COMMUNITY SERVICES
0
12
ANY OTHER
12841.975
Total
51921.085
Facility
External/ connecting service to be provided by (Name the agency)
Whether Approval taken from the agency concerned. Yes/No (Annex details in folder C)
ROADS
HUDA/HSVP
No
WATER SUPPLY
HUDA/HSVP
No
ELECTRICITY
DHBVN
Yes
SEWAGE DISPOSAL
HUDA/HSVP
No
STORM WATER DRAINAGE
HUDA/HSVP
No
Sr. No.
Name of the facility
Estimated cost (In Lakhs)(Within the project area only)
Remarks: Yet to be prepared / Submitted to HUDA, Town & Country Planning Department/ as per project report etc. (Annex relevant documents showing costing details etc. in folder C)
1
INTERNAL ROADS AND PAVEMENTS
72.90
AS PER PROJECT REPORT
2
WATER SUPPLY SYSTEM
21.60
AS PER PROJECT REPORT
3
STORM WATER DRAINAGE
27.00
AS PER PROJECT REPORT
4
ELECTRICITY SUPPLY SYSTEM
40.50
AS PER PROJECT REPORT
5
SEWAGE TREATMENT & GARBAGE DISPOSAL
24.30
AS PER PROJECT REPORT
6
STREET LIGHTING
16.20
AS PER PROJECT REPORT
7
SECURITY AND FIRE FIGHTING
5.40
AS PER PROJECT REPORT
8
PLAYGROUNDS AND PARKS
13.50
AS PER PROJECT REPORT
9
CLUB HOUSE/COMMUNITY CENTRE
0
AS PER PROJECT REPORT
10
SHOPPING AREA
0
AS PER PROJECT REPORT
11
RENEWABLE ENERGY SYSTEM
0
AS PER PROJECT REPORT
12
SCHOOL
0
AS PER PROJECT REPORT
13
HOSPITAL/DISPENSARY
0
AS PER PROJECT REPORT
14
ANY OTHER
0
AS PER PROJECT REPORT
15
STP
16.20
YET TO BE PREPARED
16
RAIN WATER HARVESTING
5.40
YET TO BE PREPARED
17
ELECTRICAL SUB STATION
27.00
YET TO BE PREPARED
23-02-2012 (date)
23-02-2012 (date)
Sr. No.
Plot/ apartment type
Size of the plot/carpet area of the apartments
Total number of plots/apartments in the project
Plots/apartments booked/ sold upto the date of application
Yet to be sold/ booked
No. of towers to be/ being constructed for booked apartments
1
APARTMENT/SHOPS/OTHER BUILDINGS Type ANNEX
1069.68
62
44
18
1
Type
Number of apartments booked/ sold
Write or Annex the stage of construction of the booked/ sold apartments in folder C
ANNEX
44
0
25-02-2012
31-01-2018
31-01-2018
25-02-2012
88
30-01-2018
PROVIDED
PROVIDED
Plots
Booked/sold
Stage of handing over the possession (Write or Annex details)
PLOT
0
NOT APPLICABLE
25-02-2012
0
31-01-2018
NOT APPLICABLE
NOT APPLICABLE
72
0
0
23
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Apartments
2160.00
Shops
0
Plots
0
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
50.00
90.00
Shops
0
0
Plots
0
0
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Apartments
130.00
Shops
0
Plots
0
Expenditure incurred till the date of application (In Lakhs)
Particulars
Expenditure
Roads & Pavements
64.80
Water Supply System
19.20
Sewerage treatment & garbage disposal
21.60
Electricity Supply System
36.00
Storm Water Drainage
24.00
Parks and Playgrounds
12.00
Clubhouse/community centres
0
Shopping area
0
Other
0
Electrical Sub station
24.00
Rain Water Harvesting
4.80
Security and fire fighting
4.80
STP
14.40
Street lighting
14.40
Expenditure to be made in each quarter (In Lakhs)
Particulars
Year-2017
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
1.70
2.70
Water Supply System
0.80
0.80
Sewerage treatment & garbage disposal
0.90
0.90
Electricity Supply System
0.50
1.50
Storm Water Drainage
0.50
1.00
Parks and Playgrounds
0
0.50
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Street lighting
0.10
0.60
Security and fire fighting
0.20
0.20
STP
0.10
0.60
Rain Water Harvesting
0.20
0.20
Electrical Sub station
0
1.00
Particulars
Year-2018
Jan-Mar
Apr-June
July-Sep
Oct-Dec
Roads & Pavements
3.70
0
Water Supply System
0.80
0
Sewerage treatment & garbage disposal
0.90
0
Electricity Supply System
2.50
0
Storm Water Drainage
1.50
0
Parks and Playgrounds
1.00
0
Clubhouse/community centres
0
0
Shopping area
0
0
Other
0
0
Street lighting
1.10
0
Electrical Sub station
2.00
0
Rain Water Harvesting
0.20
0
STP
1.10
0
Security and fire fighting
0.20
0
Particulars
Remarks, if any
i. No. of Flats/Apartments constructed
62
To be Constructed
ii. No. of Flats/ Apartments booked
44
iii. Total amount sale value of booked Flats, on the date of application/end of last quarter
5452.95 Lakhs
iv. Total amount received from the allottees (booked Flats), on the date of application/end of last quarter
5014.97 Lakhs
v. Balance amount to be received from the allottees (booked Flats, after completion), on the date of application/end of last quarter
5014.97 Lakhs
vi. Balance amount due and recoverable from the allottees (booked Flats) as on the date of application /end of last quarter
437.98 Lakhs
vii. Amount invested in the project upto the date of application
3539.14 Lakhs
Land cost (If any)
296.00 Lakhs
Apartments
2160.00 Lakhs
Infrastructure
240.00 Lakhs
EDC/ Taxes Etc.
443.86 Lakhs
viii. Balance cost to be incurred for completion of the project and delivery of possession
443.86 Lakhs
(a) In respect of existing allottees
315.00 Lakhs
(b) In respect of rest of the project
128.86 Lakhs
ix. The amount of loan raised from the banks/ financial institutions/ private persons against the project Annex detail of the securities furnished to the banks/ financial institutions against the aforesaid loans in folder C
300 Lakhs
x. Total liabilities against the project up-to-date. (Annex details in folder C)
256.09 Lakhs
Particulars
Estimated expenditure planned to be incurred as per service plan estimates or the project report. (In Lakhs)
Actual expenditure incurred upto the date of application. (In Lakhs)
I. INTERNAL ROADS AND PAVEMENTS
72.90
64.80
II. WATER SUPPLY SYSTEM
21.60
19.20
III. STORM WATER DRAINAGE
27.00
24.00
IV. ELECTRICITY SUPPLY SYSTEM
40.50
36.00
V. SEWAGE TREATMENT & GARBAGE DISPOSAL
16.20
21.60
VI. CLUB HOUSE/COMMUNITY CENTRE
0
0
VII. SCHOOL
0
0
VIII. ANY OTHER
0
0
IX. SOLID WASTE COLLECTION & MGMT SYSTEM
0
0
X. CLUBHOUSE
0
0
XI. NEIGHBOURHOOD SHOPPING
0
0
XII. GREEN AREAS,PARKS,PLAYGROUNDS ETC.
13.50
12.00
XIII. COVERED PARKING
0
0
XIV. OPEN PARKING
0
0
XV. GARAGES
0
0
XVI. SECURITY SYSTEM
5.40
4.80
XVII. OTHER FACILITIES AS PER PROJECT REPORT
72.90
57.60
Yes
Yes
HDFC BANK LTD. FIP, MG ROAD, GURUGRAM HARYANA-122001
57500000181626
HDFC0000280
110240037
0280
1.Mr. Anil Bhalla
Hyde Park, Prakrati Marg, Sultanpur Farms, Gadaipur, South Delhi, Delhi 110030
2.Mr. Gautam Bhalla
LCG05 PHB, The Laburnam, Nathupur (67),Nathupur Gurgaon,Gurgaon, Haryana 122002
3. Mr. K V George
Flat No. 1504, Mohinder Apartment, Plot No 17, Sector 12, Dwarka, South West Delhi, Delhi 110075
4. Mrs Veena Bhomia
C1/577B,Rear Block,1st Floor, Near Euro Kids School,Palam Vihar,Choma (62), Gurgaon, Haryana 122017
Uploaded
Yes
No
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
Yes
No
Yes
Yes
Statutory Approvals
Statutory Approvals Status
Date
I. LAY OUT PLAN
ALREADY BEEN OBTAINED
23-02-2012
II. ZONING PLAN
ALREADY BEEN OBTAINED
09-09-2011
III. BUILDING PLAN
ALREADY BEEN OBTAINED
23-02-2012
IV. FLOOR PLAN
ALREADY BEEN OBTAINED
23-02-2012
V. APARTMENT PLANS
ALREADY BEEN OBTAINED
23-02-2012
VI. ELEVATION SECTION
ALREADY BEEN OBTAINED
23-02-2012
VII. SERVICE ESTIMATE
ALREADY BEEN OBTAINED
04-08-2014
Yes
Yes
Provided
“TURNING POINT” (PHASE - I) SECTOR 88B, VILLAGE HARSARU, SUB-TEHSIL HARSARU, DISTRICT GURUGRAM, STATE HARYANA
93588.71
703
0
99
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
33415.00
33415.00
4081.38
Cost of the apartments
25200.00
25200.00
453.31
Cost of the infrastructure
2800.00
2800.00
50.00
Others costs
5415.00
5415.00
3578.07
975.94 Lakhs
7752.46 Lakhs
15000.00 Lakhs
15000.00 Lakhs
No
30-01-2025
30-01-2025
“TOWN SQUARE” (BLOCK-D) SECTOR 82A, VILLAGE SHIKOHPUR, TEHSIL MANESAR, DISTRICT GURUGRAM, STATE HARYANA
13809.560
187
0
16
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
10586.00
10586.00
9646.93
Cost of the apartments
4500.00
4500.00
3835.50
Cost of the infrastructure
500.00
500.00
426.00
Others costs
5586.00
5586.00
5385.43
486.26 Lakhs
798.92 Lakhs
14600.00 Lakhs
14600.00 Lakhs
No
30-07-2018
30-07-2018
SOVEREIGN NEXT (PHASE - I) SECTOR-82A, VILLAGE SHIKOHPUR, TEHSIL MANESAR, DISTRICT GURUGRAM, STATE HARYANA
34519.201
151
0
81
0
Initially estimated cost (In Lakhs)
Revised cost (In Lakhs)
Expenditure incurred upto the date of application (In Lakhs)
Total cost of the project (Other than cost of land)
18175.00
18175.00
9849.29
Cost of the apartments
10350.00
10350.00
5266.00
Cost of the infrastructure
1150.00
1150.00
585.00
Others costs
6675.00
6675.00
3998.29
7602.94 Lakhs
4179.31 Lakhs
15000.00 Lakhs
15000.00 Lakhs
No
31-07-2022
31-07-2022
SPECIFICATION OF CONSTRUCTION
Specification of apartments and other buildings including the following:
1
FLOORING DETAILS OF VARIOUS PARTS OF HOUSE
REFER SECTION BELOW
2
WALL FINISHING DETAILS
REFER SECTION BELOW
3
KITCHEN DETAILS
REFER SECTION BELOW
4
BATHROOM FITTINGS
REFER SECTION BELOW
5
WOOD WORK ETC
NOT APPLICABLE
6
DOORS AND WINDOS FRAMES
ALUMINUM OR UPVC FRAME
7
GLASS WORK
ALUMINUM OR UPVC FRAME WINDOWS WITH CLEAR GLASS
8
ELECTRIC FITTINGS
IS COMPLIANT MODULAR SWITCHES / SOCKETS, SWITCHGEAR AND DISTRIBUTION BOXES FROM STANDARD MAKES AND BRAND
9
CONDUCTING AND WIRING DETAILS
IS COMPLIANT COPPER WIRING IN CONCEALED CONDUITS. ADEQUATE PROVISION FOR LIGHT POINTS, FAN POINTS, RECEPTACLES AND POWER POINTS IN ALL ROOMS
10
CUPBOARD DETAILS
NOT APPLICABLE
11
WATER STORAGE
OHT &UG; TANKS
12
LIFT DETAILS
SPACIOUS ELEVATORS WITH PLEASING INTERIORS
13
EXTERNAL GLAZINGS
NA
13.1
WINDOWS/GLAZINGS
ALUMINUM OR UPVC FRAME WINDOWS WITH CLEAR GLASS
14
DOORS
NA
14.1
MAIN DOORS
POLISHED VENEER DOOR WITH POLISHED HARDWOOD FRAME
14.2
INTERNAL DOORS
PAINTED HARDWOOD FRAMES AND FLUSH DOORS
15
AIR CONDITIONING
AIR-CONDITIONING THROUGH A COMBINATION OF SPLITS AND WINDOW AC’S IN ALL BEDROOMS AND LIVING ROOMS
16
ELECTRICAL FITTINGS
MENTIONED IN POINT NO.8 ABOVE
17
CNG PIPE LINE
PROVISION FOR SUPPLY OF PIPED NATURAL GAS / LPG SUPPLY TO THE KITCHEN
18
PROVISION OF WIFI AND BROADBAND FACILITY
NOT APPLICABLE
19
EXTERNAL FINISHING/COLOUR SCHEME
EXTERNAL GRADE ANTI FUNGAL / ANTI ALGAL PAINT FROM REPUTED MAKES AND BRANDS
20
INTERNAL FINISHING
MENTIONED IN DETAIL IN SECTION BELOW.
SPECIFICATION UNIT WISE
1 . LIVING/DINING/FOYER/FAMILY LOUNGE
1 . 1
FLOOR
POLISHED LAPATO OR MATT FINISHED VITRIFIED TILES OF REPUTED MAKE AND BRAND
1 . 2
WALLS
EMULSION PAINT ON SMOOTH PLASTERED WALLS.
1 . 3
CEILING
OBD ON PLASTER
2 . MASTER BEDROOM/DRESSROOM
2 . 1
FLOOR
LAMINATED WOODEN FLOORING
2 . 2
WALLS
EMULSION PAINT ON SMOOTH PLASTERED WALLS
2 . 3
CEILING
OBD ON PLASTE
2 . 4
MODULAR WARDROBES
NOT PROVIDED
3 . MASTER TOILET
3 . 1
FLOOR
MATT FINISHED/ANTI-SKID CERAMIC TILES OF A REPUTED MAKE AND BRAND
3 . 2
WALLS
MATT FINISHED WALL TILES UP TO DADO LEVEL. OIL BOUND DISTEMPER ON PLASTERED SURFACES ABOVE DADO LEVEL
3 . 3
CEILING
FALSE CEILING
3 . 4
COUNTERS
GRANITE COUNTER
3 . 5
SANITARY WARE/CP FITTINGS
WASH BASIN AND EUROPEAN WATER CLOSET (EWC) OF REPUTED MAKES AND BRANDS
3 . 6
FITTING/FIXTURES
SINGLE LEVER BASIN MIXER, CONCEALED SHOWER MIXER / DIVERTER WITH BATH SPOUT AND OVERHEAD SHOWER, HEALTH FAUCET ALONG WITH NECESSARY ANGLE VALVES ETC. OF REPUTED MAKES AND BRANDS
4 . BED ROOMS
4 . 1
FLOOR
LAMINATED WOODEN FLOORING
4 . 2
WALLS
EMULSION PAINT ON SMOOTH PLASTERED WALLS
4 . 3
CEILING
OBD ON PLASTER
4 . 4
WARDROBES
NOT PROVIDED
5 . TOILET
5 . 1
FLOOR
MATT FINISHED/ANTI-SKID CERAMIC TILES OF A REPUTED MAKE AND BRAND
5 . 2
WALLS
MATT FINISHED WALL TILES UP TO DADO LEVEL. OIL BOUND DISTEMPER ON PLASTERED SURFACES ABOVE DADO LEVEL
5 . 3
CEILING
FALSE CEILING
5 . 4
COUNTERS
NOT APPLICABLE
5 . 5
SANITARY WARE/CP FITTINGS
WASH BASIN AND EUROPEAN WATER CLOSET (EWC) OF REPUTED MAKES AND BRANDS
5 . 6
FIXTURES
SINGLE LEVER BASIN MIXER, CONCEALED SHOWER MIXER / DIVERTER WITH BATH SPOUT AND OVERHEAD SHOWER, HEALTH FAUCET ALONG WITH NECESSARY ANGLE VALVES ETC. OF REPUTED MAKES AND BRANDS
6 . KITCHEN
6 . 1
FLOOR
MATT FINISHED CERAMIC TILES
6 . 2
WALLS
2’ HIGH PREMIUM CERAMIC TILES DADO ABOVE COUNTER. OIL BOUND DISTEMPER ON PLASTER IN REMAINING AREAS
6 . 3
CEILING
OBD ON PLASTER
6 . 4
COUNTERS
GRANITE COUNTER TOP
6 . 5
FIXTURES
A DOUBLE BOWL SINK, MIXER,
6 . 6
KITCHEN APPLIANCES
COOK TOP & CHIMNEY INSTALLATION
7 . UTILITY ROOMS/UTILITY BALCONY/TOILET
7 . 1
FLOOR
MATT FINISHED CERAMIC TILES
7 . 2
WALLS & CEILING
PAINT ON PLASTER
7 . 3
TOILET
MATT FINISHED CERAMIC TILES ON FLOOR
7 . 4
BALCONY
MATT FINISHED / ANTI SKID CERAMIC TILES
8 . SIT-OUTS
8 . 1
FLOOR
MATT FINISHED / ANTI SKID CERAMIC TILES
8 . 2
WALLS & CEILING
PAINT ON PLASTER
8 . 3
RAILINGS
NOT APPLICABLE
8 . 4
FIXTURES
NOT APPLICABLE
Sr. No.
Document Description
Date of Document Upload
View Document
1
LOI
20-02-2020
------
2
SITE PLAN
20-02-2020
------
3
DECLARATION SUPPORTED BY AFFIDAVIT DULY SIGNED BY THE PROMOTER TO BE ENCLOSED.
CERTIFICATE FROM A CHARTERED ACCOUNTANT CERTIFYING THAT THE INFORMSTION PROVIDED BY THE APPLICANT IN FORM REP-1-C-X IS CORRECT AS PER THE BOOKS OF ACCOUNTS/ BALANCE SHEET OF THE APPLICANT